Home / Browse projects / Pune, Maharashtra / Playtor Paud C- Phase 2

Registration lapsed No litigation declared Residential / Group Housing project

Playtor Paud C- Phase 2

By SANGAM REALTY

RG-MH-08702 · RERA P52100002910 · Last updated on MahaRERA portal: 20 May 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 60 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
13 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
2Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

Playtor Paud C- Phase 2 is a Residential / Group Housing project by SANGAM REALTY in Pune, Maharashtra, registered with MahaRERA as P52100002910 on 4 Aug 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 60 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NamePlaytor Paud C- Phase 2
  • TypeResidential / Group Housing
  • Location
    • Paud-Mulshi Road
    • Next to Tehsil Office
    • Paud
    • Mulshi
    • Pune
    • 412108
  • Pincode412108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002910
  • ReraGenie IDRG-MH-08702

Builder

  • NameSANGAM REALTY
  • Entity typePartnership
  • PartnersSANTOSH MOTILAL BHANSALI, NANDKUMAR SOPAN GADHAVE
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live4 lapsed, de-registered or revoked

Key dates

28 months past promisethis monthRegisteredAug 2017First promiseJun 2019Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Aug 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 30 Jun 2019)
  • Buildings2 building records
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C2NA80000
C4NA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

C278%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
C475%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities18

As on 20 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes30%
Landscaping & Tree PlantingYes90%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes100%
Compound WallYes80%
EarthworkYes100%
Retaining WallYes100%

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,479 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Vrushali Sandeep SatavLavalePune

Approvals and building plan

Permissible FSI4770.28
Proposed, not sanctioned4,022 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchII- 5C , MITTAL COURT, 224 , NARIMAN POINT, MUMBAI- 400021

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAVINASH NAWATHE
EngineerSSPA
PartnerRole in project
SANGAM REALTY-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100002065Jun 2019 → Jun 2020

Reason as filed by the promoterDue to delay in getting permissions of plinth checking certificate from PMRDA, Pune, we here request you that, we require 1 year extension for completion of our Playtor Paud C - Phase 2 projects situated at Gat No. 245 & 266, village Paud, Tal. Mulshi, Dist. Pune. Please may kindly be allow 1 year extension.

EXT52100012069Jun 2019 → Jun 2024

Reason as filed by the promoterrequest for commencement certificate and building material was shortaged

EXT52100008977Jun 2019 → Dec 2021

Reason as filed by the promoterAttached list of Allottes have consented to extend Rera date of completion of the project form 29/12/2020 to 30/09/2022.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000289968POOJA VILAS KULKARNISANGAM REALTY29/12/2023
CC12501234ajay ramdas pardeshiSANGAM REALTY14/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_Sanagm Realty_Ph-2.pdf20 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Paud C Phase II.pdf19 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sangam Phase 2 C2 Building.pdf24 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sangam Phase 2 C4 Building.pdf24 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate Paud C Ph 2.pdf24 Jan 2020
Certificates of CA (Form 3)File: Form 3_CA Cartificate_Paud C Ph 2.pdf24 Jan 2020
Certificates of CA (Form 3)File: Form 3 Sangam 2019 Paud C Ph 2 Signed_compressed.pdf24 Jan 2020
Certificates of CA (Form 5)File: Form 5_CA- Paud C ph 2 - 09-01-2020.PDF22 Jan 2020
Certificates of CA (Form 5)File: Form 5_CA-Paud C ph 2.pdf9 Jan 2019
Details of encumbrancesFile: Index 2 Release Edelweiss.pdf21 Dec 2018
Details of encumbrancesFile: Index 2 Mortgage Deed Fullerton.pdf21 Dec 2018
Proforma of Allotment letterFile: Revised Allotment (Booking) letter_RERA.pdf14 Nov 2017
Certificates of CA (Form 3)File: Form 3_CA Cert_Promoter_Paud C Ph 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3_CA Cert_Co-Promoter_Paud C Ph 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3_CA Cert_Promoter-Co-Pro_Paud C Ph 2.pdf31 Jul 2017
Declaration in FORM BFile: Form B_Promoter_Paud C Ph 2.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer Cert_Paud C Ph 2.pdf29 Jul 2017
Proforma of Allotment letterFile: 6_Sale Agreement_Paud C_Ph 2.pdf29 Jul 2017
Proforma of Allotment letterFile: Allotment letter.pdf29 Jul 2017
Building plan approvalFile: IOD_Paud C ph 2.pdf26 Jul 2017
Building Plan Approval (IOD)File: IOD_Paud C ph 2.pdf26 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cer_Form 1_Paud C2.pdf19 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cer_Form 1_Paud C4.pdf19 Jul 2017
Details of encumbrancesFile: Encum Index 1137-17_Paud D.pdf15 Jul 2017
Layout approvalFile: scan976_2.pdf8 Jul 2017
PAN CardFile: Pan -Sangam Realty.pdf8 Jul 2017
Copy of the legal title reportFile: Gat No-266_Title Report.pdf8 Jul 2017
Copy of Layout Approval (in case of layout)File: scan976_2.pdf8 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commisment Certificate_Paud C_Revised.pdf8 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 60 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Playtor Paud C- Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Next to Tehsil Office13,700+ in Pune

2 kmPlaytor Paud C- Phase 2Completed 2Lapsed / revoked 3Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: SANGAM REALTY

SANGAM REALTY has 5 registrations on MahaRERA, including Playtor Paud C- Phase 1 and Playtor Paud C- Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Playtor Paud C- Phase 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Playtor Paud C- Phase 2 is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Playtor Paud C- Phase 2?

The registered promoter entity is SANGAM REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Playtor Paud C- Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Playtor Paud C- Phase 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Playtor Paud C- Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Playtor Paud C- Phase 2?

The professionals named in the filing: Architect: AVINASH NAWATHE; Engineer: SSPA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Playtor Paud C- Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Playtor Paud C- Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Playtor Paud C- Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.