Home / Browse projects / Pune, Maharashtra / PLATINUM PARK

Registration lapsed No litigation declared Residential / Group Housing project

PLATINUM PARK

By SAFFRON PROPERTIES AND SCHEMES

RG-MH-20165 · RERA P52100008065 · Last updated on MahaRERA portal: 21 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 42 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
1Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

PLATINUM PARK is a Residential / Group Housing project by SAFFRON PROPERTIES AND SCHEMES in Pune, Maharashtra, registered with MahaRERA as P52100008065 on 18 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 42 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePLATINUM PARK
  • TypeResidential / Group Housing
  • Location
    • man
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100008065
  • ReraGenie IDRG-MH-20165

Builder

  • NameSAFFRON PROPERTIES AND SCHEMES
  • Entity typePartnership
  • PartnersPURAB JETHANAND CHHABRIA, RAVINDRA BABANRAO KASAR, SANTOSH ANKUSH MOHITE, KISHOR ANKUSH MOHITE, PARITOSH RAJENDRA AGARWAL, PAWAN JETHANAND CHHABRIA

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 30 Jun 2021)
  • Buildings2 building records
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA120000
B WINGNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 21 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

A WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B WING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 21 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed173

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots173
Closed/Covered86
Open Space87
BuildingClosed/CoveredOpen SpaceTotal
A WING434487
B WING434386

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
RAMKRUSHNA EKNATH PARKHIManPune
ANANTA EKNATH PARKHIManPune

Approvals and building plan

Permissible FSI9564.47
Proposed, not sanctioned9,564 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNORTH MAIN ROAD KOREGOAN PARK PUNE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV K A ARCHITECTURE
EngineerVINAY ASHOK SHAH
PartnerRole in project
SAFFRON PROPERTIES AND SCHEMES-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013247Jun 2021 → Jun 2023

Reason as filed by the promoterWork completed upto 90 % final stage work will be completed in next 3 months and the documentation part needs further 2 months to receive cc for the project.

EXT52100009252Jun 2021 → Jun 2022

Reason as filed by the promoterREASON FOR DELAY IS DUE TO COVID 19 THATS WHY ITS GETTING LATE TO THE COMPLETION PROCESS. SO PLEASE ACCEPT OUR REQUEST AND MAKE CHANGES.

EXT52100018386Jun 2021 → Dec 2024

Reason as filed by the promoterThe project is complete and the completion certificate or 179 out of 181 flats is already uploaded. form 4 along with this completion status is uploaded. this extension is required merely to update the project once final completion is received. The possession for the sold flats is already given hence consent not taken

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000228362Ankush ShrivastavM/s Saffron Properties and Schemes02/03/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Sep 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Sep 2023

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 platinum park.pdf21 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: society certificate.pdf21 Jan 2025
Declaration in FORM BFile: NEW FORM B for ext.pdf27 May 2024
Other - TechnicalFile: Undertaking for complaince forms.pdf22 May 2024
CERSAI detailsFile: Cersai report page_merged.pdf21 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A Platinum Park 22-23.pdf4 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Data 2023.pdf4 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf4 Mar 2024
Declaration in FORM BFile: Form B 2024 (2).pdf23 Dec 2023
Disclosure of sold/ booked inventoryFile: Sold unsold inventory 2024-5-11.pdf23 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Certificate - Form 5- CA - signed.pdf23 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 4.pdf18 Sep 2023
Certificates of CA (Form 3)File: form 3.pdf18 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 platinum park final.pdf16 Sep 2023
Certificates of CA (Form 3)File: FORM-3 final platinum park.pdf16 Sep 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC platinum park final.pdf16 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Platinum Park.pdf17 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory saffron.pdf17 Jan 2023
Certificates of CA (Form 3)File: Form-3 saffron.pdf17 Jan 2023
Certificates of CA (Form 5)File: Form-5 saffron.pdf17 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5 saffron.pdf17 Jan 2023
Details of encumbrances concerned to FinanceFile: No Encumbrance legal.pdf25 Dec 2022
Details of encumbrances concerned to LegalFile: No Encumbrance legal.pdf25 Dec 2022
Proforma of Allotment letterFile: Allotment letter PP.pdf25 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A bank ac declaration PP.pdf25 Dec 2022
Deviation Report with respect to Allotment letterFile: Deviation allotment letter PP.pdf25 Dec 2022
Certificates of CA (Form 3)File: form 3.pdf31 Aug 2021
Declaration about Commencement CertificateFile: SAFFRON CERTIFICATE.pdf16 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 210811 - RERA Certificate ( arch Signed)_compressed.pdf14 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PLATINUM PARK_compressed.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A final.pdf14 Aug 2021
Disclosure of sold/ booked inventoryFile: Sold unsold FINAL_compressed.pdf14 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form5 2018-19.pdf22 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5 2019-2020.pdf22 Feb 2021
Layout approvalFile: REVISED LAYOUT FOR UPLODING.pdf19 Sep 2020
Copy of the legal title reportFile: partnership deed compressed.pdf19 Sep 2020
Copy of Layout Approval (in case of layout)File: REVISED LAYOUT FOR UPLODING.pdf19 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: revised commencement certificate feb 2020 compressed.pdf19 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 AR PLATINUM PARK compressed.pdf19 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 AR PLATINUM PARK compressed.pdf19 Sep 2020
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE compressed.pdf19 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PLATINUM PARK compressed.pdf18 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PLATINUM PARK compressed.pdf18 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 PLATINUM PARK compressed.pdf18 Sep 2020
Details of encumbrancesFile: sanction letter - Capri Bank.pdf14 Aug 2019
Certificates of CA (Form 5)File: Form 5 Saffron - Platinum Park F Y 2017-18.pdf30 Sep 2018
Layout approvalFile: Sanction Plan.pdf29 Jul 2017
Building plan approvalFile: Sanction Plan.pdf29 Jul 2017
PAN CardFile: Firm PAN Card.pdf29 Jul 2017
Copy of the legal title reportFile: Search Report - New.pdf29 Jul 2017
Details of encumbrancesFile: Encumbrance.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Sanction Plan.pdf29 Jul 2017
Building Plan Approval (IOD)File: Sanction Plan.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf29 Jul 2017
Declaration in FORM BFile: Form B.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf29 Jul 2017
Certificates of CA (Form 3)File: Saffron- CA Certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: Agreement To Sale and Allotement Letter.pdf29 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 42 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PLATINUM PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Man13,700+ in Pune

2 kmPLATINUM PARKCompleted 37Lapsed / revoked 14Other 38Dot size: filed unitsN

Filed coordinates, straight-line distance. 89 registered projects within 2 km.

Builder: SAFFRON PROPERTIES AND SCHEMES

SAFFRON PROPERTIES AND SCHEMES has 1 registration on MahaRERA, including PLATINUM PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that PLATINUM PARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PLATINUM PARK is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PLATINUM PARK?

The registered promoter entity is SAFFRON PROPERTIES AND SCHEMES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PLATINUM PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PLATINUM PARK?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PLATINUM PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PLATINUM PARK?

The professionals named in the filing: Architect: V K A ARCHITECTURE; Engineer: VINAY ASHOK SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PLATINUM PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PLATINUM PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PLATINUM PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.