Home / Browse projects / Pune, Maharashtra / PLATINUM 9

Registration lapsed No litigation declared Commercial project

PLATINUM 9

By HNK BUILDTECH LLP

RG-MH-04739 · RERA P52100020126 · Last updated on MahaRERA portal: 19 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA
  • Rs 20.00 crore secured on the land, in favour of Aditya Birla Capital Limited

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
8 of 11Construction stages donefurthest along: Podiums (if any), 0%
126 of 258Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 152 documents Report an error

PLATINUM 9 is a Commercial project by HNK BUILDTECH LLP in Pune, Maharashtra, registered with MahaRERA as P52100020126 on 29 Mar 2019. Possession was promised by 30 Dec 2025 and is now 10 months past that date. 132 of the 258 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePLATINUM 9
  • TypeCommercial
  • Location
    • PUNE
    • Baner
    • Haveli
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100020126
  • ReraGenie IDRG-MH-04739

Builder

  • NameHNK BUILDTECH LLP
  • Entity typePartnership
  • PartnersHITESH BHAGWAN OSWAL, NAIMESH PACHAN PATEL, HASMUKH NARAYAN PATEL
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredMar 2019PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on29 Mar 2019
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed152 files

Current status

51%132 of 258 units booked
96.2%Work done, per cost certificate

Figures as on 19 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PLATINUM 9NA13120258258

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

PLATINUM 9: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 19 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Open Space50

Land and ownership8

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,225 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Capital Limited
Secured amountRs 20.00 crore
CERSAI search filedYes
Declared on29 Jan 2026
LandownerVillageDistrict
BALASAHEB SADASHIV MURKUTEBanerPune
MARUTI BALASAHEB MURKUTEBanerPune
SHAIQ PATHANaundhePune
ASIF PATHANaundhePune
BABUL PATHANaundhePune
SHAHIQ BABUL PATHANaundhePune
BABUL RUSTUMKHAN PATHANaundhePune
ASIF YASIN PATHANaundhePune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI29223.92
Proposed, not sanctioned14,612 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK LTD GRND FLR NAGRAS TOWER BUILDING A SHOP NO 2 S NO 162 4a 5a DP ROAD PUNE 411007
Estimated costRs 52.00 cr
Cost incurredRs 50.00 cr
Work done96.15%
BuildingWingEstimatedIncurred
PLATINUM 9NARs 50.00 crRs 48.00 cr
-NARs 2.00 crRs 2.00 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVk A Architecture
EngineerBARAVKAR D N
EngineerPATIL.S.R
Chartered AccountantPGMJ AND ASSOCIATES
Chartered AccountantNITISH VAIDYA & ASSOCIATES
Chartered AccountantPGMJ & ASSOCIATES
PartnerRole in project
HNK BUILDTECH LLP-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000053844Mr. Mukunda Tukaram TapkirHNK Buildtech LLP through its Partner Hitesh Bhagwan Oswal27/12/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed152

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 152 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: Form 2A FY 23-24.pdf19 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf16 Feb 2026
Withdrawal Update Form 1File: Form 1 FY 25-26 Q3.pdf16 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf16 Feb 2026
Withdrawal Update Form 2File: Form 2 FY 25-26 Q3.pdf16 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf16 Feb 2026
Withdrawal Update Form 3File: Form 3 FY 25-26 Q3.pdf16 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf14 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf14 Feb 2026
Withdrawal Update Form 3File: FORM3.pdf14 Feb 2026
Form 5 (FY 2024-2025)File: Form5 FY 24-25.pdf11 Feb 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf17 Jul 2025
Certificates of CA (Form 3)File: Form 3.pdf17 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Jul 2025
Disclosure of sold/ booked inventoryFile: sold unsold.pdf17 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf13 Apr 2025
Certificates of CA (Form 3)File: Form 3 Qtr 4 Final.pdf13 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Revised Form 2.pdf13 Apr 2025
Disclosure of sold/ booked inventoryFile: Revise Sold Circular 4th.pdf13 Apr 2025
Certificates of CA (Form 3)File: Form 3 Q3 2024-25.pdf18 Jan 2025
Certificates of CA (Form 3)File: Form 3 Q3 2024-25.pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf17 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold circular.pdf17 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FINAL FORM 5.pdf25 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf17 Oct 2024
Certificates of CA (Form 3)File: Form 3.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -Q2.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Circular Q2.pdf17 Oct 2024
Details of encumbrancesFile: Final Disclosure.pdf8 Aug 2024
Disclosure for secured/unsecured finance availed for the projectFile: Final Disclosure.pdf8 Aug 2024
Other - FinanceFile: Mortgage deed_compressed_11zon.pdf8 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Final Form 1.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf19 Jul 2024
Certificates of CA (Form 3)File: Form 3 Final Signed PS 1 (2).pdf19 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf18 Jul 2024
Copy of the legal title reportFile: New Search Title upload.pdf28 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect Cerfificate.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf16 Apr 2024
Certificates of CA (Form 3)File: Final Form 3 (Q4 23-24)-Upload.pdf16 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect certificate.pdf10 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf10 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf10 Jan 2024
Certificates of CA (Form 3)File: Final Form 3.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 CA SIGNED.pdf31 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Final.pdf30 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold circular.pdf30 Nov 2023
Certificates of CA (Form 3)File: Upload Form 3.pdf8 Nov 2023
Certificates of CA (Form 3)File: Revised Upload.pdf11 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf13 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf13 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf13 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold circular.pdf13 Jul 2023
Certificates of CA (Form 3)File: Form 3 Final upload.pdf13 Jul 2023
Certificates of CA (Form 3)File: Form 3 (CA Signed).pdf8 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 FY 18-19-SIGN.pdf8 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf27 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf27 Apr 2023
Certificates of CA (Form 3)File: Form 3 Upload.pdf20 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (Promoter Signed).pdf18 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf28 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf28 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf28 Dec 2022
Certificates of CA (Form 3)File: Form 3 (Promoter Signed).pdf28 Dec 2022
Certificates of CA (Form 3)File: Form 3 (Promoter Signed).pdf9 Dec 2022
Layout approvalFile: 1-15.pdf22 Nov 2022
Building plan approvalFile: 2-15.pdf22 Nov 2022
Building plan approvalFile: 3-15.pdf22 Nov 2022
Building plan approvalFile: 4-15.pdf22 Nov 2022
Building plan approvalFile: 5-15.pdf22 Nov 2022
Building plan approvalFile: 6-15.pdf22 Nov 2022
Building plan approvalFile: 7-15.pdf22 Nov 2022
Building plan approvalFile: 8-15.pdf22 Nov 2022
Building plan approvalFile: 9-15.pdf22 Nov 2022
Building plan approvalFile: 10-15.pdf22 Nov 2022
Building plan approvalFile: 11-15.pdf22 Nov 2022
Building plan approvalFile: 12-15.pdf22 Nov 2022

How this compares with Pune

51%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PLATINUM 9 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE13,700+ in Pune

2 kmPLATINUM 9Completed 102Lapsed / revoked 31Other 134Dot size: filed unitsN

Filed coordinates, straight-line distance. 267 registered projects within 2 km.

Builder: HNK BUILDTECH LLP

HNK BUILDTECH LLP has 2 registrations on MahaRERA, including PLATINUM 9 and PLATINUM GLORY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that PLATINUM 9 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PLATINUM 9 is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PLATINUM 9?

The registered promoter entity is HNK BUILDTECH LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PLATINUM 9?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PLATINUM 9?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PLATINUM 9?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PLATINUM 9?

The professionals named in the filing: Architect: Vk A Architecture; Engineer: BARAVKAR D N; Engineer: PATIL.S.R; Chartered Accountant: PGMJ AND ASSOCIATES; Chartered Accountant: NITISH VAIDYA & ASSOCIATES; Chartered Accountant: PGMJ & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PLATINUM 9?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PLATINUM 9. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PLATINUM 9 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.