ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Pinnacle 9 Sadashiv A - Building

Registered No litigation declared Others project

Pinnacle 9 Sadashiv A - Building

By Pinnacle Neostar Corporation Pvt. Ltd.

RG-MH-20360 · RERA P52100008353 · Last updated on MahaRERA portal: 22 Feb 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
3 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 60%
0Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

Pinnacle 9 Sadashiv A - Building is a Others project by Pinnacle Neostar Corporation Pvt. Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100008353 on 18 Aug 2017. Possession is promised by 30 Dec 2026.

At a glance

Project

  • NamePinnacle 9 Sadashiv A - Building
  • TypeOthers
  • Location
    • Sadashiv peth
    • Pune
    • Pune (M Corp.)
    • Pune City
    • 411030
  • Pincode411030
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100008353
  • ReraGenie IDRG-MH-20360

Builder

  • NamePinnacle Neostar Corporation Pvt. Ltd.
  • Entity typeCompany
  • Other registrations1 more →

Key dates

this monthRegisteredAug 2017PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Aug 2017
  • Promised completion30 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
9 SADASHIV ANA130000
9 SADASHIV B BUILDINGNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 60%.

9 SADASHIV A51%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
9 SADASHIV B BUILDING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 22 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes25%
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes20%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed95

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots95
Closed/Covered95

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,413 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI20348.34
Proposed, not sanctioned12,761 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAUKIK APTS, CTS 870, BHANDARKAR ROAD, PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAKASH KULKARNI
Chartered AccountantSPCM & ASSOCIATE
Chartered AccountantCA VIDHI S SHAH
PartnerRole in project
Pinnacle Neostar Corporation Pvt. Ltd.-

Litigation declared2

CaseCourtStatus
7/15, 8/15, 9/15/2015DISTRICT COURTPending
1164/2014CJSDPending

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Feb 2023

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: 1.pdf22 Feb 2023
Layout approvalFile: 2.pdf22 Feb 2023
Layout approvalFile: 3.pdf22 Feb 2023
Building plan approvalFile: PLAN 1-19 new.pdf22 Feb 2023
Copy of Layout Approval (in case of layout)File: 1.pdf22 Feb 2023
Copy of Layout Approval (in case of layout)File: 2.pdf22 Feb 2023
Copy of Layout Approval (in case of layout)File: 3.pdf22 Feb 2023
Building Plan Approval (IOD)File: PLAN 1-19 new.pdf22 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: CC DP 1.pdf22 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: CC 2.pdf22 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC sadashiv 9.pdf22 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1.pdf21 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf21 Oct 2022
Certificates of CA (Form 3)File: SIGNED FORM 3.pdf21 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MARCH-21.pdf12 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MARCH 22.pdf12 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUNE.pdf12 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MARCH -21.pdf12 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 March22.pdf12 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUNE.pdf12 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A MARCH 21.pdf12 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2A March22.pdf12 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A JUNE.pdf12 Aug 2022
Certificates of CA (Form 3)File: FORM 3 MARCH-21.pdf12 Aug 2022
Certificates of CA (Form 3)File: FORM 3 MARCH 22.pdf12 Aug 2022
Certificates of CA (Form 3)File: FORM 3 JUNE.pdf12 Aug 2022
Details of encumbrancesFile: Pinnacle Neostar.pdf31 Aug 2021
Declaration about Commencement CertificateFile: Pinnacle Neostar.pdf31 Aug 2021
Details of encumbrancesFile: Mortgage Deed.pdf20 May 2021
OtherFile: Mortgage Deed.pdf18 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Sadashiv AB 1819.pdf24 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Sadashiv AB 1920.pdf24 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: sadashiv AB Wing Fomr 5-compressed.pdf13 Dec 2019
Building plan approvalFile: HPSC6011.pdf19 Mar 2018
Building Plan Approval (IOD)File: HPSC6011.pdf19 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: ilovepdf_merged(1)-ilovepdf-compressed(2).pdf19 Mar 2018
Layout approvalFile: 9 Sadashiv_CC-ilovepdf-compressed.pdf29 Jul 2017
Building plan approvalFile: 12-ilovepdf-compressed.pdf29 Jul 2017
PAN CardFile: PAN Neostar.pdf29 Jul 2017
Copy of the legal title reportFile: Adv Amar Nikam Search Report .pdf29 Jul 2017
Details of encumbrancesFile: Scan0005001.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 9 Sadashiv_CC-ilovepdf-compressed.pdf29 Jul 2017
Building Plan Approval (IOD)File: 12-ilovepdf-compressed.pdf29 Jul 2017
Declaration in FORM BFile: neo star.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archit certi_9sadashiv A B .pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg cert (9 sadashivA_B).pdf29 Jul 2017
Certificates of CA (Form 3)File: 9 Sadashiv A wing CA certificate-ilovepdf-compressed.pdf29 Jul 2017
Proforma of Allotment letterFile: Proforma Draft 9 sadashiv.pdf29 Jul 2017
Proforma of Allotment letterFile: Draft agreement A Building 9 Sadashiv.pdf29 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Pinnacle 9 Sadashiv A - Building on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pune13,700+ in Pune

2 kmPinnacle 9 Sadashiv A - Completed 188Lapsed / revoked 132Other 188Dot size: filed unitsN

Filed coordinates, straight-line distance. 508 registered projects within 2 km.

Builder: Pinnacle Neostar Corporation Pvt. Ltd.

Pinnacle Neostar Corporation Pvt. Ltd. has 2 registrations on MahaRERA, including 9 Sadashiv C building and Pinnacle 9 Sadashiv A - Building. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Pinnacle 9 Sadashiv A - Building is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Pinnacle 9 Sadashiv A - Building?

The registered promoter entity is Pinnacle Neostar Corporation Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Pinnacle 9 Sadashiv A - Building?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Pinnacle 9 Sadashiv A - Building?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Pinnacle 9 Sadashiv A - Building?

The professionals named in the filing: Architect: PRAKASH KULKARNI; Chartered Accountant: SPCM & ASSOCIATE; Chartered Accountant: CA VIDHI S SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pinnacle 9 Sadashiv A - Building?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pinnacle 9 Sadashiv A - Building. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pinnacle 9 Sadashiv A - Building to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.