Perinsheri Pinnac Greens
By F. S. Mazda & Pinnac Housing Associates LLP
RG-MH-04840 · RERA P52100021115 · Last updated on MahaRERA portal: 8 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 41 months
- 6 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Perinsheri Pinnac Greens is a Residential / Group Housing project by F. S. Mazda & Pinnac Housing Associates LLP in Pune, Maharashtra, registered with MahaRERA as P52100021115 on 31 May 2019. Possession is promised by 30 Nov 2026. The completion date has moved by 41 months from the original filing. 44 of the 72 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete.
At a glance
Project
- NamePerinsheri Pinnac Greens
- TypeResidential / Group Housing
- Location
- Paud Road
- Kothrud
- Haveli
- Pune
- 411038
- Pincode411038
- RERA no.P52100021115
- ReraGenie IDRG-MH-04840
Builder
- NameF. S. Mazda & Pinnac Housing Associates LLP
- Entity typeOthers
- Named personsPinnac Housing Private Limited, Pinnac AECL Consultancy Private Limited, Dinesh Vasant Chandratre, Prasad P. Zaple, Sunil Shridhar Deshpande
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 May 2019
- Promised completion30 Nov 2026
- Revised completionRevised to 30 Nov 2026 (originally 30 Jun 2023)
- Buildings2 building records
- Documents filed181 files
Current status
Figures as on 8 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing B | NA | 14 | 12 | 24 | 0 | 24 |
| Wing A | NA | 14 | 12 | 48 | 0 | 48 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 8 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
Wing B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 8 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 90% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 67% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed72
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing B | 24 | 24 |
| Wing A | 48 | 48 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing A | NA | Rs 30.00 cr | Rs 30.00 cr |
| Wing B | NA | Rs 14.55 cr | Rs 14.55 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pinnac AECL Consultancy Pvt Ltd |
| Architect | PINNAC CONSULTING PVT LTD |
| Engineer | PINNAC CONSULTING PVT LTD |
| Engineer | NITIN PARGAONKAR |
| Chartered Accountant | PRAKASH WALGUDE & ASSOCIATES |
| Partner | Role in project |
|---|---|
| F. S. Mazda & Pinnac Housing Associates LLP | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project is getting completed and we are applying for Occupancy Certificate. Hence required extension.
Reason as filed by the promoterThe scheme Perinsheri Pinnac Greens (said Project) was registered vide MahaRERA No. P52100021115 and the Certificate was issued on 31.05.2019. We had revised the layout and had applied to the MahaRERA Authority and as per our application we were issued the revised Certificate on 30.09.2021. In the last week of March, 2020, the constructed activity could not be started due to the lock down imposed because of Covid 19 pandemic. After the lock down relaxations was issued, we had to delay the start of construction activity due to non-availability of continuous labor. During the second and third lo
Reason as filed by the promoterThe project has faced an unforeseen delay due to the ongoing installation and commissioning of the lift systems. The lift installation process is currently in progress and is expected to take approximately 45 days for completion. Furthermore, following the completion of the lift installation, the process of obtaining the necessary lift license is anticipated to take an additional 30 days. This licensing process involves inspections and approvals from the competent authority, which are beyond our direct control but mandatory for getting occupancy certificate. We assure you that we are making ev
Reason as filed by the promoterThe project work is extended due delay in approval of Sanctioned Plan from the competent authority. Hence the delayed the construction activities. We have completed the project 70% and further activities are in progress. Request you to grant the extension as soon as possible so that we can complete the construction and get the occupancy certificate from the authority.
Reason as filed by the promoterWe would like to inform you that our project has experienced an unforeseen delay primarily due to the delayed approval of the Sanctioned Plan from the competent authority. Consequently, the commencement and progress of the construction activities were affected. We are pleased to inform you that approximately 95% of the project work has been completed, and the remaining activities are in progress. In light of the circumstances, we respectfully request MahaRERA to grant an extension of the project completion period at the earliest. This will enable us to complete the remaining construction work
Reason as filed by the promoterOC OF THE PROJECT IS RECEIVED. APPLYING FOR EXTENSION TO COMPLETE THE PROCEDURE ON MAHARERA PORTAL. ALSO TO UPLOAD NEW CC AND PLANS AND TO GET APPLICATION CORRECTED.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 May 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Apr 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Apr 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Nov 2026
Documents filed181
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 181 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1.pdf | 8 Sep 2026 |
| Withdrawal Update Form 1File: FORM 1.pdf | 8 Sep 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 8 Sep 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 8 Sep 2026 |
| Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q2.pdf | 8 Sep 2026 |
| Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q2.pdf | 8 Sep 2026 |
| Withdrawal Update Form 1File: FORM 1.pdf | 13 Aug 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 13 Aug 2026 |
| Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q2.pdf | 13 Aug 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A.pdf | 13 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certitificate 31122025.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: Form 2-31122025.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q2.pdf | 27 Jan 2026 |
| Form 5 (FY 2024-2025)File: PPG-From 5-2024-2025_0001.pdf | 12 Nov 2025 |
| Form 5 (FY 2023-2024)File: PPG-From 5-2023-2024_0001.pdf | 12 Nov 2025 |
| Form 5 (FY 2022-2023)File: Form 5 PPG -2022-23.pdf | 12 Nov 2025 |
| Form 2A (FY 2024-2025)File: Certificate No. 06 - Form 2A PPG-March 2025.pdf | 11 Nov 2025 |
| Form 2A (FY 2019-2020)File: Certificate No. 01 - Form 2A PPG-March 2020.pdf | 11 Nov 2025 |
| Form 2A (FY 2020-2021)File: Certificate No. 02 - Form 2A PPG-March 2021.pdf | 11 Nov 2025 |
| Form 2A (FY 2021-2022)File: Certificate No. 03 - Form 2A PPG-March 2022.pdf | 11 Nov 2025 |
| Form 2A (FY 2022-2023)File: Certificate No. 04 - Form 2A PPG-March 2023.pdf | 11 Nov 2025 |
| Form 2A (FY 2023-2024)File: Certificate No. 05 - Form 2A PPG-March 2024.pdf | 11 Nov 2025 |
| Form 2A (FY 2024-2025)File: Certificate No. 06 - Form 2A PPG-March 2025.pdf | 11 Nov 2025 |
| Withdrawal Update Form 1File: PPG - FORM 1 - 25-26 Q1.pdf | 7 Nov 2025 |
| Withdrawal Update Form 1File: PPG - FORM 1 - 25-26 Q1.pdf | 7 Nov 2025 |
| Withdrawal Update Form 1File: PPG - FORM 1 - 25-26 Q2.pdf | 7 Nov 2025 |
| Withdrawal Update Form 2File: PPG - FORM 2 - 25-26 Q1.pdf | 7 Nov 2025 |
| Withdrawal Update Form 2File: PPG - FORM 2 - 25-26 Q1.pdf | 7 Nov 2025 |
| Withdrawal Update Form 2File: PPG - FORM 2 - 25-26 Q2.pdf | 7 Nov 2025 |
| Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q1.pdf | 7 Nov 2025 |
| Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q1.pdf | 7 Nov 2025 |
| Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q2.pdf | 7 Nov 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 31032025.pdf | 24 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate 31032025.pdf | 24 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032025.pdf | 24 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Declaration-Sold Unsold Inventory 31032025.pdf | 24 Apr 2025 |
| Declaration in FORM BFile: Form B - PPG - April 2025.pdf | 26 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PPG - Form 1 - DEC 2024.pdf | 26 Dec 2024 |
| Certificates of CA (Form 3)File: PPG - Form 3 - DEC 2024.pdf | 26 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PPG - Form 2 - DEC 2024.pdf | 26 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: PPG - Sold Unsold - DEC 2024.pdf | 26 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: PPG - Form 2A - DEC 2024.pdf | 26 Dec 2024 |
| Certificates of CA (Form 3)File: PHALLP - RERA form 3 - May 24.pdf | 1 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: PHALLP - RERA form 5 - 23-24.pdf | 1 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: PHALLP - RERA form 5 - 23-24.pdf | 1 Jul 2024 |
| Declaration in FORM BFile: Form B - PPG - June 2024.pdf | 13 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 5 PPG -2022-23.pdf | 6 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 PPG -2022-23.pdf | 6 May 2024 |
| Layout approvalFile: plan 1-11.pdf | 29 Apr 2024 |
| Building plan approvalFile: plan 2-11.pdf | 29 Apr 2024 |
| Building plan approvalFile: plan 3-11.pdf | 29 Apr 2024 |
| Building plan approvalFile: plan 4-11.pdf | 29 Apr 2024 |
| Building plan approvalFile: plan 5-11.pdf | 29 Apr 2024 |
| Building plan approvalFile: plan 6-11.pdf | 29 Apr 2024 |
| Building plan approvalFile: plan 7-11.pdf | 29 Apr 2024 |
| Building plan approvalFile: plan 8-11.pdf | 29 Apr 2024 |
| Building plan approvalFile: plan 9-11.pdf | 29 Apr 2024 |
| Building plan approvalFile: plan 10-11.pdf | 29 Apr 2024 |
| Building plan approvalFile: plan 11-11.pdf | 29 Apr 2024 |
| Copy of Layout Approval (in case of layout)File: plan 1-11.pdf | 29 Apr 2024 |
| Building Plan Approval (IOD)File: plan 2-11.pdf | 29 Apr 2024 |
| Building Plan Approval (IOD)File: plan 3-11.pdf | 29 Apr 2024 |
| Building Plan Approval (IOD)File: plan 4-11.pdf | 29 Apr 2024 |
| Building Plan Approval (IOD)File: plan 5-11.pdf | 29 Apr 2024 |
| Building Plan Approval (IOD)File: plan 6-11.pdf | 29 Apr 2024 |
| Building Plan Approval (IOD)File: plan 7-11.pdf | 29 Apr 2024 |
| Building Plan Approval (IOD)File: plan 8-11.pdf | 29 Apr 2024 |
| Building Plan Approval (IOD)File: plan 9-11.pdf | 29 Apr 2024 |
| Building Plan Approval (IOD)File: plan 10-11.pdf | 29 Apr 2024 |
| Building Plan Approval (IOD)File: plan 11-11.pdf | 29 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC 01.pdf | 29 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certiifcate 31032024.pdf | 29 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032024.pdf | 29 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory 31032024.pdf | 29 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate 31032024.pdf | 29 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PPG Form 1 Architect Certificate Q3 31122023.pdf | 21 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PPG Form 2 Q2 30092023.pdf | 21 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PPG Form 2 Q3 31122023.pdf | 21 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: PPG Disclosure of Sold Booked Inventory Q3 31122023.pdf | 21 Jan 2024 |
| Certificates of CA (Form 3)File: PPG Form 3 CA Certificate 31122023.pdf | 21 Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 181 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Perinsheri Pinnac Greens on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kothrud13,700+ in Pune
Pratik Nagar Palladio Kothrud Central
Vilas Javdekar Infinitee Developers Pvt. L
NEW FRIENDS
MAJESTIQUE DUROPOLIS PRIVATE LIMITED
SARVATRA CO-OP HSG SOCIETY LTD
Suryakant Kakade
Kshitij Residency
Yash Buildcon
MAYUK
MAYUR CORPORATION
Pune Baner Project-Tower 4 and 5
Goel Ganga Ventures India Private Limited
Builder: F. S. Mazda & Pinnac Housing Associates LLP
F. S. Mazda & Pinnac Housing Associates LLP has 1 registration on MahaRERA, including Perinsheri Pinnac Greens. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Perinsheri Pinnac Greens is delayed beyond 30 Nov 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Perinsheri Pinnac Greens?
The registered promoter entity is F. S. Mazda & Pinnac Housing Associates LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Perinsheri Pinnac Greens?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Perinsheri Pinnac Greens?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Perinsheri Pinnac Greens?
The professionals named in the filing: Architect: Pinnac AECL Consultancy Pvt Ltd; Architect: PINNAC CONSULTING PVT LTD; Engineer: PINNAC CONSULTING PVT LTD; Engineer: NITIN PARGAONKAR; Chartered Accountant: PRAKASH WALGUDE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Perinsheri Pinnac Greens?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback