Home / Browse projects / Pune, Maharashtra / Perinsheri Pinnac Greens

Registered No litigation declared Residential / Group Housing project

Perinsheri Pinnac Greens

By F. S. Mazda & Pinnac Housing Associates LLP

RG-MH-04840 · RERA P52100021115 · Last updated on MahaRERA portal: 8 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 41 months
  • 6 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 41 months from the original
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
28 of 72Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 181 documents Report an error

Perinsheri Pinnac Greens is a Residential / Group Housing project by F. S. Mazda & Pinnac Housing Associates LLP in Pune, Maharashtra, registered with MahaRERA as P52100021115 on 31 May 2019. Possession is promised by 30 Nov 2026. The completion date has moved by 41 months from the original filing. 44 of the 72 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete.

At a glance

Project

  • NamePerinsheri Pinnac Greens
  • TypeResidential / Group Housing
  • Location
    • Paud Road
    • Kothrud
    • Haveli
    • Pune
    • 411038
  • Pincode411038
  • RERA no.P52100021115
  • ReraGenie IDRG-MH-04840

Builder

  • NameF. S. Mazda & Pinnac Housing Associates LLP
  • Entity typeOthers
  • Named personsPinnac Housing Private Limited, Pinnac AECL Consultancy Private Limited, Dinesh Vasant Chandratre, Prasad P. Zaple, Sunil Shridhar Deshpande

Key dates

this monthRegisteredMay 2019First promiseJun 2023Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 May 2019
  • Promised completion30 Nov 2026
  • Revised completionRevised to 30 Nov 2026 (originally 30 Jun 2023)
  • Buildings2 building records
  • Documents filed181 files

Current status

61%44 of 72 units booked
100.0%Work done, per cost certificate

Figures as on 8 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing BNA141224024
Wing ANA141248048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

Wing B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingYes0%
Community BuildingsYes90%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes67%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed72

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots72
Closed/Covered72
BuildingClosed/CoveredTotal
Wing B2424
Wing A4848

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,300 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Aug 2025

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI7018.1
Proposed, not sanctioned3,349 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAbhishek Complex Happy Colony Kothrud Pune
Estimated costRs 44.55 cr
Cost incurredRs 44.55 cr
Work done100.0%
BuildingWingEstimatedIncurred
Wing ANARs 30.00 crRs 30.00 cr
Wing BNARs 14.55 crRs 14.55 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPinnac AECL Consultancy Pvt Ltd
ArchitectPINNAC CONSULTING PVT LTD
EngineerPINNAC CONSULTING PVT LTD
EngineerNITIN PARGAONKAR
Chartered AccountantPRAKASH WALGUDE & ASSOCIATES
PartnerRole in project
F. S. Mazda & Pinnac Housing Associates LLP-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100023006Jun 2023 → Dec 2024

Reason as filed by the promoterThe project is getting completed and we are applying for Occupancy Certificate. Hence required extension.

EXT52100016568Jun 2023 → Jun 2024

Reason as filed by the promoterThe scheme Perinsheri Pinnac Greens (said Project) was registered vide MahaRERA No. P52100021115 and the Certificate was issued on 31.05.2019. We had revised the layout and had applied to the MahaRERA Authority and as per our application we were issued the revised Certificate on 30.09.2021. In the last week of March, 2020, the constructed activity could not be started due to the lock down imposed because of Covid 19 pandemic. After the lock down relaxations was issued, we had to delay the start of construction activity due to non-availability of continuous labor. During the second and third lo

EXT52100025811Jun 2023 → Apr 2025

Reason as filed by the promoterThe project has faced an unforeseen delay due to the ongoing installation and commissioning of the lift systems. The lift installation process is currently in progress and is expected to take approximately 45 days for completion. Furthermore, following the completion of the lift installation, the process of obtaining the necessary lift license is anticipated to take an additional 30 days. This licensing process involves inspections and approvals from the competent authority, which are beyond our direct control but mandatory for getting occupancy certificate. We assure you that we are making ev

EXT52100028309Jun 2023 → Aug 2025

Reason as filed by the promoterThe project work is extended due delay in approval of Sanctioned Plan from the competent authority. Hence the delayed the construction activities. We have completed the project 70% and further activities are in progress. Request you to grant the extension as soon as possible so that we can complete the construction and get the occupancy certificate from the authority.

EA07112518267Jun 2023 → Jan 2026

Reason as filed by the promoterWe would like to inform you that our project has experienced an unforeseen delay primarily due to the delayed approval of the Sanctioned Plan from the competent authority. Consequently, the commencement and progress of the construction activities were affected. We are pleased to inform you that approximately 95% of the project work has been completed, and the remaining activities are in progress. In light of the circumstances, we respectfully request MahaRERA to grant an extension of the project completion period at the earliest. This will enable us to complete the remaining construction work

EA14082622137Jun 2023 → Nov 2026

Reason as filed by the promoterOC OF THE PROJECT IS RECEIVED. APPLYING FOR EXTENSION TO COMPLETE THE PROCEDURE ON MAHARERA PORTAL. ALSO TO UPLOAD NEW CC AND PLANS AND TO GET APPLICATION CORRECTED.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Nov 2026

Documents filed181

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 181 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf8 Sep 2026
Withdrawal Update Form 1File: FORM 1.pdf8 Sep 2026
Withdrawal Update Form 2File: FORM 2.pdf8 Sep 2026
Withdrawal Update Form 2File: FORM 2.pdf8 Sep 2026
Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q2.pdf8 Sep 2026
Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q2.pdf8 Sep 2026
Withdrawal Update Form 1File: FORM 1.pdf13 Aug 2026
Withdrawal Update Form 2File: FORM 2.pdf13 Aug 2026
Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q2.pdf13 Aug 2026
Form 2A (FY 2025-2026)File: FORM 2A.pdf13 Aug 2026
Withdrawal Update Form 1File: Form 1 - Architect Certitificate 31122025.pdf27 Jan 2026
Withdrawal Update Form 2File: Form 2-31122025.pdf27 Jan 2026
Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q2.pdf27 Jan 2026
Form 5 (FY 2024-2025)File: PPG-From 5-2024-2025_0001.pdf12 Nov 2025
Form 5 (FY 2023-2024)File: PPG-From 5-2023-2024_0001.pdf12 Nov 2025
Form 5 (FY 2022-2023)File: Form 5 PPG -2022-23.pdf12 Nov 2025
Form 2A (FY 2024-2025)File: Certificate No. 06 - Form 2A PPG-March 2025.pdf11 Nov 2025
Form 2A (FY 2019-2020)File: Certificate No. 01 - Form 2A PPG-March 2020.pdf11 Nov 2025
Form 2A (FY 2020-2021)File: Certificate No. 02 - Form 2A PPG-March 2021.pdf11 Nov 2025
Form 2A (FY 2021-2022)File: Certificate No. 03 - Form 2A PPG-March 2022.pdf11 Nov 2025
Form 2A (FY 2022-2023)File: Certificate No. 04 - Form 2A PPG-March 2023.pdf11 Nov 2025
Form 2A (FY 2023-2024)File: Certificate No. 05 - Form 2A PPG-March 2024.pdf11 Nov 2025
Form 2A (FY 2024-2025)File: Certificate No. 06 - Form 2A PPG-March 2025.pdf11 Nov 2025
Withdrawal Update Form 1File: PPG - FORM 1 - 25-26 Q1.pdf7 Nov 2025
Withdrawal Update Form 1File: PPG - FORM 1 - 25-26 Q1.pdf7 Nov 2025
Withdrawal Update Form 1File: PPG - FORM 1 - 25-26 Q2.pdf7 Nov 2025
Withdrawal Update Form 2File: PPG - FORM 2 - 25-26 Q1.pdf7 Nov 2025
Withdrawal Update Form 2File: PPG - FORM 2 - 25-26 Q1.pdf7 Nov 2025
Withdrawal Update Form 2File: PPG - FORM 2 - 25-26 Q2.pdf7 Nov 2025
Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q1.pdf7 Nov 2025
Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q1.pdf7 Nov 2025
Withdrawal Update Form 3File: PPG - FORM 3 - 25-26 Q2.pdf7 Nov 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 31032025.pdf24 Apr 2025
Certificates of CA (Form 3)File: Form 3 CA Certificate 31032025.pdf24 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032025.pdf24 Apr 2025
Disclosure of sold/ booked inventoryFile: Declaration-Sold Unsold Inventory 31032025.pdf24 Apr 2025
Declaration in FORM BFile: Form B - PPG - April 2025.pdf26 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PPG - Form 1 - DEC 2024.pdf26 Dec 2024
Certificates of CA (Form 3)File: PPG - Form 3 - DEC 2024.pdf26 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PPG - Form 2 - DEC 2024.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: PPG - Sold Unsold - DEC 2024.pdf26 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: PPG - Form 2A - DEC 2024.pdf26 Dec 2024
Certificates of CA (Form 3)File: PHALLP - RERA form 3 - May 24.pdf1 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: PHALLP - RERA form 5 - 23-24.pdf1 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: PHALLP - RERA form 5 - 23-24.pdf1 Jul 2024
Declaration in FORM BFile: Form B - PPG - June 2024.pdf13 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 5 PPG -2022-23.pdf6 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 PPG -2022-23.pdf6 May 2024
Layout approvalFile: plan 1-11.pdf29 Apr 2024
Building plan approvalFile: plan 2-11.pdf29 Apr 2024
Building plan approvalFile: plan 3-11.pdf29 Apr 2024
Building plan approvalFile: plan 4-11.pdf29 Apr 2024
Building plan approvalFile: plan 5-11.pdf29 Apr 2024
Building plan approvalFile: plan 6-11.pdf29 Apr 2024
Building plan approvalFile: plan 7-11.pdf29 Apr 2024
Building plan approvalFile: plan 8-11.pdf29 Apr 2024
Building plan approvalFile: plan 9-11.pdf29 Apr 2024
Building plan approvalFile: plan 10-11.pdf29 Apr 2024
Building plan approvalFile: plan 11-11.pdf29 Apr 2024
Copy of Layout Approval (in case of layout)File: plan 1-11.pdf29 Apr 2024
Building Plan Approval (IOD)File: plan 2-11.pdf29 Apr 2024
Building Plan Approval (IOD)File: plan 3-11.pdf29 Apr 2024
Building Plan Approval (IOD)File: plan 4-11.pdf29 Apr 2024
Building Plan Approval (IOD)File: plan 5-11.pdf29 Apr 2024
Building Plan Approval (IOD)File: plan 6-11.pdf29 Apr 2024
Building Plan Approval (IOD)File: plan 7-11.pdf29 Apr 2024
Building Plan Approval (IOD)File: plan 8-11.pdf29 Apr 2024
Building Plan Approval (IOD)File: plan 9-11.pdf29 Apr 2024
Building Plan Approval (IOD)File: plan 10-11.pdf29 Apr 2024
Building Plan Approval (IOD)File: plan 11-11.pdf29 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: CC 01.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certiifcate 31032024.pdf29 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31032024.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory 31032024.pdf29 Apr 2024
Certificates of CA (Form 3)File: Form 3 CA Certificate 31032024.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PPG Form 1 Architect Certificate Q3 31122023.pdf21 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PPG Form 2 Q2 30092023.pdf21 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PPG Form 2 Q3 31122023.pdf21 Jan 2024
Disclosure of sold/ booked inventoryFile: PPG Disclosure of Sold Booked Inventory Q3 31122023.pdf21 Jan 2024
Certificates of CA (Form 3)File: PPG Form 3 CA Certificate 31122023.pdf21 Jan 2024

How this compares with Pune

61%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 41 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Perinsheri Pinnac Greens on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kothrud13,700+ in Pune

Builder: F. S. Mazda & Pinnac Housing Associates LLP

F. S. Mazda & Pinnac Housing Associates LLP has 1 registration on MahaRERA, including Perinsheri Pinnac Greens. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Perinsheri Pinnac Greens is delayed beyond 30 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Perinsheri Pinnac Greens?

The registered promoter entity is F. S. Mazda & Pinnac Housing Associates LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Perinsheri Pinnac Greens?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Perinsheri Pinnac Greens?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Perinsheri Pinnac Greens?

The professionals named in the filing: Architect: Pinnac AECL Consultancy Pvt Ltd; Architect: PINNAC CONSULTING PVT LTD; Engineer: PINNAC CONSULTING PVT LTD; Engineer: NITIN PARGAONKAR; Chartered Accountant: PRAKASH WALGUDE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Perinsheri Pinnac Greens?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Perinsheri Pinnac Greens. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Perinsheri Pinnac Greens to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.