Home / Browse projects / Pune, Maharashtra / PAYAL CO OP HSG SOC
PAYAL CO OP HSG SOC
RG-MH-24157 · RERA P52100009888 · Last updated on MahaRERA portal: 29 Jan 2021
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PAYAL CO OP HSG SOC is a Residential / Group Housing project by SUFAL ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100009888 on 22 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2019. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NamePAYAL CO OP HSG SOC
- TypeResidential / Group Housing
- Location
- LANE NO.14
- PRABHAT ROAD
- Pune (M Corp.)
- Pune City
- Pune
- 411004
- Pincode411004
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100009888
- ReraGenie IDRG-MH-24157
Builder
- NameSUFAL ASSOCIATES
- Entity typePartnership
- PartnerVAISHALI RAJESH VYAS
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on22 Aug 2017
- Promised completion30 Dec 2019
- Revised completionRevised to 30 Dec 2019 (originally 31 Dec 2018)
- Buildings1 building record
- Documents filed33 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PAYAL CO OP HSG SOC | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Jan 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
PAYAL CO OP HSG SOC: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 29 Jan 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| PAYAL CO OP HSG SOC | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRASAD D MAHAJAN |
| Partner | Role in project |
|---|---|
| SUFAL ASSOCIATES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) WE ARE WAITING FOR DECISION OF LOCAL BODY AUTHORITY(PUNE MUNICIPAL CORPORATION) REGARDING ROAD EXCAVATION FOR LAYING THE ELECTRICAL CABLES REQUIRED FOR SUPPLYING ELECTRICITY TO THE EXISTING MEMBERS AND NEW FLAT PURCHASERS OF PAYAL SOCIETY, 2) SIMILARLY GETTING THE REQUIRED NOC'S FROM THE LOCAL BODY AUTHORITY (PUNE MUNICIPAL CORPORATION ) IS IN PROGRESS HENCE WE REQUIRE PERMISSION FOR EXTENSION OF THE PROJECT
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Jun 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Mar 2020
Documents filed33
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: DECLARATION.pdf | 29 Jan 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: compltion certificate payal 1.pdf | 3 Mar 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: complition certificate payal 2.pdf | 3 Mar 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 PAYAL.pdf | 3 Mar 2020 |
| Building plan approvalFile: 1_compressed.pdf | 4 Jun 2019 |
| Building plan approvalFile: 2_compressed.pdf | 4 Jun 2019 |
| Building Plan Approval (IOD)File: 1_compressed.pdf | 4 Jun 2019 |
| Building Plan Approval (IOD)File: 2_compressed.pdf | 4 Jun 2019 |
| Certificates of CA (Form 5)File: SUFAL ASSOCIATES ( PAYAL ) FORM-5.pdf | 7 Feb 2019 |
| Building plan approvalFile: plan 1.pdf | 5 Dec 2018 |
| Building plan approvalFile: 2.pdf | 5 Dec 2018 |
| Building Plan Approval (IOD)File: plan 1.pdf | 5 Dec 2018 |
| Building Plan Approval (IOD)File: 2.pdf | 5 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate payal.pdf | 5 Dec 2018 |
| Building plan approvalFile: Payal 1 sanction plan-ilovepdf-compressed (1).pdf | 27 Sep 2017 |
| Building plan approvalFile: Payal 2 sanction plan-ilovepdf-compressed (1).pdf | 27 Sep 2017 |
| Building Plan Approval (IOD)File: Payal 1 sanction plan-ilovepdf-compressed (1).pdf | 27 Sep 2017 |
| Building Plan Approval (IOD)File: Payal 2 sanction plan-ilovepdf-compressed (1).pdf | 27 Sep 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate payal.pdf | 27 Sep 2017 |
| Layout approvalFile: k prat payal.pdf | 31 Jul 2017 |
| Building plan approvalFile: payal sanction plan pmc 2.pdf | 31 Jul 2017 |
| Building plan approvalFile: payal sanction plan pmc 1.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: payal soc legal title serch report.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Encumbrance payal.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: k prat payal.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: payal sanction plan pmc 1.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: payal sanction plan pmc 2.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: affidavit cum declartion sufal Associates B form.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Payal ARCHITECT CERTIFICATE.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: payal Engineer Certificate RERA.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: payal CA Certificate.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Agreement copy Payal soc.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Allotment letter payal soc.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 33 filed documents as one ZIP, foldered, with a manifest
Keep PAYAL CO OP HSG SOC on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PRABHAT ROAD13,700+ in Pune
Filed coordinates, straight-line distance. 282 registered projects within 2 km.
VENKATESH ERANDWANE CENTRAL - BUILDING-B1 - PH
SHREE VENKATESH BUILDCON PVT LTD
One Place-F.C. Road Phase 3
PALASH REALTORS LLP
45 NIRVAANA HILL - C2 WING
SINEW DEVELOPERS PRIVATE LIMITED
VENKATESH ERANDWANE CENTRAL - BUILDING-B2 - PH
SHREE VENKATESH BUILDCON PVT LTD
VENKATESH ERANDWANE CENTRAL - BUILDING-B3 - PH
SHREE VENKATESH BUILDCON PVT LTD
One Place-F.C Road Phase 2
PALASH REALTORS LLP
Builder: SUFAL ASSOCIATES
SUFAL ASSOCIATES has 1 registration on MahaRERA, including PAYAL CO OP HSG SOC. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if PAYAL CO OP HSG SOC is delayed beyond 30 Dec 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PAYAL CO OP HSG SOC?
The registered promoter entity is SUFAL ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PAYAL CO OP HSG SOC?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PAYAL CO OP HSG SOC?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PAYAL CO OP HSG SOC?
The professionals named in the filing: Architect: PRASAD D MAHAJAN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PAYAL CO OP HSG SOC?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback