Home / Browse projects / Pune, Maharashtra / PAWAR PLAZZA
PAWAR PLAZZA
RG-MH-17400 · RERA P52100029028 · Last updated on MahaRERA portal: 26 Apr 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 19 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PAWAR PLAZZA is a Commercial project by VAISHNAVI SPACE CREATOR in Pune, Maharashtra, registered with MahaRERA as P52100029028 on 23 Apr 2021. Possession was promised by 25 Mar 2025 and is now 19 months past that date. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NamePAWAR PLAZZA
- TypeCommercial
- Location
- NR.Indira college
- Tathawade
- Tathwade
- Mulshi
- Pune
- 411033
- Pincode411033
- RERA no.P52100029028
- ReraGenie IDRG-MH-17400
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on23 Apr 2021
- Promised completion25 Mar 2025
- Revised completionRevised to 25 Mar 2025 (originally 31 Mar 2023)
- Buildings1 building record
- Documents filed51 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| COMMERCIAL BUILDING | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 85%.
COMMERCIAL BUILDING: 77% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 58% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 26 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed12
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mr.SUNIL RAMCHANDRA PAWAR | Tathwade | Pune |
| GURUNATH PAWAR | Pune (M Corp.) | Pune |
| SUNNY JYOTIBA PAWAR | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KIMAYA ASSOCIATES |
| Engineer | AADHAR ENGINEERS |
| Chartered Accountant | CA VIREN RAMESHBHAI POKAR |
| Partner | Role in project |
|---|---|
| VAISHNAVI SPACE CREATOR | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterwe have delayed our project due to slow booking due to covide effect as well as internal fund issue due to slower booking still we have completed almost 80% of work only finishing work pending.
Reason as filed by the promoterDelay due to covide-19 pendemic.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12501718 | Vikram Kachru | VAISHNAVI SPACE CREATOR | 26/05/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Apr 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jan 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed51
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 - QUERTER ENDED -31-3-2024.pdf | 26 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2-QUERTER ENDED -31-3-2024.pdf | 26 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD - QUERTER ENDED -31-3-2024.pdf | 26 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3-FOR QUERTER ENDED -31-3-2024.pdf | 26 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 17 Apr 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200303503197_For_Debtor_Based_Search_08_04_2024_22_13_29_965.pdf | 8 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORGANIZATION.pdf | 8 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5.pdf | 8 Apr 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPARATE BANK ACCOUNT DISCLOSURE.pdf | 8 Apr 2024 |
| Declaration in FORM BFile: FORM-B-PROMOTERS.pdf | 29 Mar 2024 |
| Declaration in FORM BFile: FORM-B- CO-PROMOTERS.pdf | 29 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1-ARCHITECT CERTIFICATE.pdf | 29 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2-ENGINEER CERTIFICATE.pdf | 29 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2-ENGINEER CERTIFICATE.pdf | 29 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A.pdf | 29 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5.pdf | 29 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: ANNEXTURE -A - SOLD UNSOLD.pdf | 24 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3- 13-12-2023.pdf | 13 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3.pdf | 7 Dec 2023 |
| Declaration about Commencement CertificateFile: DECLARATION TO COMMENCEMENT (1).pdf | 21 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf | 21 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM-2A-2019-20.pdf | 21 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A-2020-21.pdf | 21 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM-2A-2021-22.pdf | 21 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 21 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5-2019-20.pdf | 21 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5-2020-21.pdf | 21 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5-2021-22.pdf | 21 Mar 2023 |
| Layout approvalFile: LAYOUT_compressed.pdf | 27 Jan 2022 |
| Building plan approvalFile: COMMERCIAL -BASMENT-GROUND-1ST FLOOR PLAN_compressed.pdf | 27 Jan 2022 |
| Building plan approvalFile: COMMERCIAL ALLIVATION PLAN_compressed.pdf | 27 Jan 2022 |
| Building plan approvalFile: COMMERCIAL 2-3-4 FLOOR PLAN_compressed.pdf | 27 Jan 2022 |
| Building plan approvalFile: SECTION AND ELIVATION PLAN_compressed.pdf | 27 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: LAYOUT_compressed.pdf | 27 Jan 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: COMMERCIAL -BASMENT-GROUND-1ST FLOOR PLAN_compressed.pdf | 27 Jan 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: COMMERCIAL ALLIVATION PLAN_compressed.pdf | 27 Jan 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: COMMERCIAL 2-3-4 FLOOR PLAN_compressed.pdf | 27 Jan 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: SECTION AND ELIVATION PLAN_compressed.pdf | 27 Jan 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT_compressed.pdf | 27 Jan 2022 |
| Copy of the legal title reportFile: LEGAL TITLE REPORT_compressed.pdf | 17 Apr 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 17 Apr 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT NEW_compressed.pdf | 7 Apr 2021 |
| Layout approvalFile: LAYOUT PLAN_compressed.pdf | 16 Mar 2021 |
| Building plan approvalFile: FLOOR PLAN.pdf | 16 Mar 2021 |
| PAN CardFile: COMPANY PAN.pdf | 16 Mar 2021 |
| Details of encumbrancesFile: NO ENCUMBRENCE.pdf | 16 Mar 2021 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN_compressed.pdf | 16 Mar 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: FLOOR PLAN.pdf | 16 Mar 2021 |
| Declaration in FORM BFile: FORM B- PROMOTORE.pdf | 16 Mar 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_compressed.pdf | 16 Mar 2021 |
| Proforma of Allotment letterFile: AGREEMENT TO SALES_compressed.pdf | 16 Mar 2021 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| STARWOOD | S NO 58 OPP INDIRA COLLEGE MUMBAI PUNE HIGHWAY TATHWADE PUNE 33 | 58 | Completed | Apr 2017 | Apr 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 51 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep PAWAR PLAZZA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Tathawade13,700+ in Pune
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: VAISHNAVI SPACE CREATOR
Vaishnavi Space Creator has 3 registrations on MahaRERA, including Star Woods Phase I and Star Woods Phase II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that PAWAR PLAZZA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PAWAR PLAZZA is delayed beyond 25 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PAWAR PLAZZA?
The registered promoter entity is VAISHNAVI SPACE CREATOR, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PAWAR PLAZZA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PAWAR PLAZZA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PAWAR PLAZZA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PAWAR PLAZZA?
The professionals named in the filing: Architect: KIMAYA ASSOCIATES; Engineer: AADHAR ENGINEERS; Chartered Accountant: CA VIREN RAMESHBHAI POKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PAWAR PLAZZA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback