Home / Browse projects / Mumbai Suburban, Maharashtra / PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT
PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT
RG-MH-97727 · RERA P51800013076 · Last updated on MahaRERA portal: 10 Mar 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 45 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT is a Others project by MEERA ENTERPRISES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013076 on 14 Sep 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 45 months from the original filing.
At a glance
Project
- NamePATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT
- TypeOthers
- Location
- Kurla
- Mumbai Suburban
- 400081
- Pincode400081
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800013076
- ReraGenie IDRG-MH-97727
Builder
- NameMEERA ENTERPRISES
- Entity typePartnership
- PartnersPANDHARINATH NAGA PATIL, VRUNDAVAN PANDURANG WANI
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Sep 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Mar 2022)
- Buildings2 building records
- Documents filed106 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PATIL PRASAD AND SHANTI SADAN BUILDING PHASE 1 WING A | NA | 12 | 0 | 0 | 0 | 0 |
| PATIL PRASAD AND SHANTI SADAN PHASE 2 WING B | NA | 19 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 10 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
PATIL PRASAD AND SHANTI SADAN BUILDING PHASE 1 WING A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
PATIL PRASAD AND SHANTI SADAN PHASE 2 WING B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 10 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed4
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| PATIL PRASAD AND SHANTI SADAN BUILDING PHASE 1 WING A | 1 | 2 | 3 |
| PATIL PRASAD AND SHANTI SADAN PHASE 2 WING B | 1 | 0 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ASHISH BHATT |
| Architect | RAMESH TAMBAT |
| Engineer | VINAYAK CHOPDEKAR AND ASSOCIATES |
| Chartered Accountant | Y S Muzumdar |
| Partner | Role in project |
|---|---|
| MEERA ENTERPRISES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterSir, the project is delayed due to the Covid 19 and lack of funds , recession in the market, this is to bring to your notice that our project is near to the completion and we have received and uploaded part occupation certificate for above mentioned project. we have some unsold inventory in this project which needs to be sell but due to the expiry of the project we are not able to sell. Hence we applied for further extension of this project.
Reason as filed by the promoterThe construction work for the units in the project is completed and the units are ready for fit out possession. Further elevators for the projects are procured from Kone Elevators India Pvt. Ltd. for which we are in contract with them. In the same light the company promised us to complete the installation of the elevator along with PWD license and handover the elevator to us by 30th November 2021. However, they failed to comply with the same and repeatedly failed for all the consecutive months till march 2022 and as the lift is still not completed till date by them, for the same reasons we wer
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 25/2015 | BOMBAY SMALL CAUSES COURT | CROSS EXAMINATION OF EVIDENCE |
| 114/2016 | BOMBAY SMALL CAUSES COURT | DISPOSED OF |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Feb 2025
Documents filed106
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: ME FORM3.pdf | 10 Mar 2025 |
| Certificates of CA (Form 3)File: ME FORM 3.pdf | 10 Mar 2025 |
| Certificates of CA (Form 3)File: ME FORM 3 .pdf | 10 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf | 10 Mar 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.PDF | 3 Mar 2025 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation Memorandum.pdf | 3 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC COPY.pdf | 3 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A March 2022.pdf | 10 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A March 2021.pdf | 10 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March 2022.pdf | 10 Jun 2023 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate (4).pdf | 9 Jun 2023 |
| Declaration in FORM BFile: Form B Rera.pdf | 5 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory dotom.pdf | 5 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory dotom.pdf | 5 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 for AY 2021 2022.pdf | 28 Mar 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration.pdf | 11 Mar 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certifcate 1Q.pdf | 26 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certifcate 1Q (2).pdf | 26 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 1Q II.pdf | 26 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certifcate 2Q.pdf | 26 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2Q II.pdf | 26 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2Q III.pdf | 26 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2Q III.pdf | 26 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 3Q.pdf | 26 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 3Q II.pdf | 26 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 4Q.pdf | 26 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 4Q II.pdf | 26 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 1Q.pdf | 26 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 1Q I.pdf | 26 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 2Q.pdf | 26 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 2Q.pdf | 26 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 2Q.pdf | 26 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 2Q II.pdf | 26 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 3Q.pdf | 26 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 3Q II.pdf | 26 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 4Q.pdf | 26 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 4Q II.pdf | 26 Oct 2021 |
| Certificates of CA (Form 3)File: RERA 1Q.pdf | 26 Oct 2021 |
| Certificates of CA (Form 3)File: RERA 1Q I.pdf | 26 Oct 2021 |
| Certificates of CA (Form 3)File: RERA 2Q.pdf | 26 Oct 2021 |
| Certificates of CA (Form 3)File: RERA 2Q I.pdf | 26 Oct 2021 |
| Certificates of CA (Form 3)File: RERA 2Q.pdf | 26 Oct 2021 |
| Certificates of CA (Form 3)File: RERA 2Q I.pdf | 26 Oct 2021 |
| Certificates of CA (Form 3)File: RERA 3Q.pdf | 26 Oct 2021 |
| Certificates of CA (Form 3)File: RERA 3Q I.pdf | 26 Oct 2021 |
| Certificates of CA (Form 3)File: RERA 4Q II.pdf | 26 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Form 5 for the year 2019-2020.pdf | 26 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA form 5 for the year 2020-2021.pdf | 26 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: 2249121_FurtherCC_signed.pdf | 3 Mar 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF | 14 Nov 2019 |
| Certificates of CA (Form 3)File: Form3.PDF | 13 Nov 2019 |
| Certificates of CA (Form 3)File: Form 3.PDF | 13 Nov 2019 |
| Certificates of CA (Form 3)File: Form 3.PDF | 13 Nov 2019 |
| Certificates of CA (Form 3)File: Form 3.PDF | 13 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF | 10 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF | 10 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF | 10 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 (2).PDF | 10 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form2.PDF | 10 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.PDF | 26 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificiate Form 1.PDF | 26 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.PDF | 26 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.PDF | 26 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF | 1 Oct 2019 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC.pdf | 20 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF | 28 May 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 28 May 2018 |
| Certificates of CA (Form 3)File: Form 3.pdf | 28 May 2018 |
| Building plan approvalFile: LETTER 1.pdf | 31 Aug 2017 |
| Building plan approvalFile: LETTER 2.pdf | 31 Aug 2017 |
| Building plan approvalFile: LETTER 3.pdf | 31 Aug 2017 |
| Building plan approvalFile: LETTER 4.pdf | 31 Aug 2017 |
| Building plan approvalFile: IOD PLAN.pdf | 31 Aug 2017 |
| Layout approvalFile: layout- sub division plan.pdf | 31 Aug 2017 |
| Layout approvalFile: IOD PLAN.pdf | 31 Aug 2017 |
| PAN CardFile: pan card.pdf | 31 Aug 2017 |
| Copy of the legal title reportFile: Title Search Report.pdf | 31 Aug 2017 |
| Details of encumbrancesFile: encumbrance certificate_1 (1).pdf | 31 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: layout- sub division plan.pdf | 31 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: IOD PLAN.pdf | 31 Aug 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 106 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kurla6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 269 registered projects within 2 km.
Ekvira and Saishakti
Magnaacasa Infrastructures and Realtors Pr
SENROOFS PHASE - III
PIONEER HOUSING
THE ALTEZZA
M/s. VIPL Varasiddhi Infra Project LLP
SUPREMO PHASE I SALVIA D WING
K V BUILDHOME LLP
SUPREMO PHASE II, WING C known as SAKURA
K V BUILDHOME LLP
Aveza Phase 2
Tata Housing Development Company Limited
See every Mumbai Suburban project, with the district possession charts
Builder: MEERA ENTERPRISES
Meera Enterprises has 2 registrations on MahaRERA, including ASIAN GALAXY B WING and PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT?
The registered promoter entity is MEERA ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT?
The professionals named in the filing: Architect: ASHISH BHATT; Architect: RAMESH TAMBAT; Engineer: VINAYAK CHOPDEKAR AND ASSOCIATES; Chartered Accountant: Y S Muzumdar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback