ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT

Registration lapsed No litigation declared Others project

PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT

By MEERA ENTERPRISES

RG-MH-97727 · RERA P51800013076 · Last updated on MahaRERA portal: 10 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 45 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 106 documents Report an error

PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT is a Others project by MEERA ENTERPRISES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013076 on 14 Sep 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 45 months from the original filing.

At a glance

Project

  • NamePATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT
  • TypeOthers
  • Location
    • Kurla
    • Mumbai Suburban
    • 400081
  • Pincode400081
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800013076
  • ReraGenie IDRG-MH-97727

Builder

  • NameMEERA ENTERPRISES
  • Entity typePartnership
  • PartnersPANDHARINATH NAGA PATIL, VRUNDAVAN PANDURANG WANI
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredSep 2017First promiseMar 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Sep 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Mar 2022)
  • Buildings2 building records
  • Documents filed106 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PATIL PRASAD AND SHANTI SADAN BUILDING PHASE 1 WING ANA120000
PATIL PRASAD AND SHANTI SADAN PHASE 2 WING BNA190000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 10 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

PATIL PRASAD AND SHANTI SADAN BUILDING PHASE 1 WING A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PATIL PRASAD AND SHANTI SADAN PHASE 2 WING B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered2
Open Space2
BuildingClosed/CoveredOpen SpaceTotal
PATIL PRASAD AND SHANTI SADAN BUILDING PHASE 1 WING A123
PATIL PRASAD AND SHANTI SADAN PHASE 2 WING B101

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,193 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6925.7
Proposed, not sanctioned5,340 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1 AND 2 CHAPHEKAR BANDHU MARG

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHISH BHATT
ArchitectRAMESH TAMBAT
EngineerVINAYAK CHOPDEKAR AND ASSOCIATES
Chartered AccountantY S Muzumdar
PartnerRole in project
MEERA ENTERPRISES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800016734Mar 2022 → Dec 2025

Reason as filed by the promoterSir, the project is delayed due to the Covid 19 and lack of funds , recession in the market, this is to bring to your notice that our project is near to the completion and we have received and uploaded part occupation certificate for above mentioned project. we have some unsold inventory in this project which needs to be sell but due to the expiry of the project we are not able to sell. Hence we applied for further extension of this project.

EXT51800011598Mar 2022 → Mar 2023

Reason as filed by the promoterThe construction work for the units in the project is completed and the units are ready for fit out possession. Further elevators for the projects are procured from Kone Elevators India Pvt. Ltd. for which we are in contract with them. In the same light the company promised us to complete the installation of the elevator along with PWD license and handover the elevator to us by 30th November 2021. However, they failed to comply with the same and repeatedly failed for all the consecutive months till march 2022 and as the lift is still not completed till date by them, for the same reasons we wer

Litigation declared2

CaseCourtStatus
25/2015BOMBAY SMALL CAUSES COURTCROSS EXAMINATION OF EVIDENCE
114/2016BOMBAY SMALL CAUSES COURTDISPOSED OF

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Feb 2025

Documents filed106

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: ME FORM3.pdf10 Mar 2025
Certificates of CA (Form 3)File: ME FORM 3.pdf10 Mar 2025
Certificates of CA (Form 3)File: ME FORM 3 .pdf10 Mar 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf10 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.PDF3 Mar 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation Memorandum.pdf3 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC COPY.pdf3 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A March 2022.pdf10 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A March 2021.pdf10 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March 2022.pdf10 Jun 2023
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate (4).pdf9 Jun 2023
Declaration in FORM BFile: Form B Rera.pdf5 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory dotom.pdf5 Jun 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory dotom.pdf5 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 for AY 2021 2022.pdf28 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration.pdf11 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certifcate 1Q.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certifcate 1Q (2).pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 1Q II.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certifcate 2Q.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2Q II.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2Q III.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2Q III.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 3Q.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 3Q II.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 4Q.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 4Q II.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 1Q.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 1Q I.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 2Q.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 2Q.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 2Q.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 2Q II.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 3Q.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 3Q II.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 4Q.pdf26 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate 4Q II.pdf26 Oct 2021
Certificates of CA (Form 3)File: RERA 1Q.pdf26 Oct 2021
Certificates of CA (Form 3)File: RERA 1Q I.pdf26 Oct 2021
Certificates of CA (Form 3)File: RERA 2Q.pdf26 Oct 2021
Certificates of CA (Form 3)File: RERA 2Q I.pdf26 Oct 2021
Certificates of CA (Form 3)File: RERA 2Q.pdf26 Oct 2021
Certificates of CA (Form 3)File: RERA 2Q I.pdf26 Oct 2021
Certificates of CA (Form 3)File: RERA 3Q.pdf26 Oct 2021
Certificates of CA (Form 3)File: RERA 3Q I.pdf26 Oct 2021
Certificates of CA (Form 3)File: RERA 4Q II.pdf26 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Form 5 for the year 2019-2020.pdf26 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA form 5 for the year 2020-2021.pdf26 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: 2249121_FurtherCC_signed.pdf3 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF14 Nov 2019
Certificates of CA (Form 3)File: Form3.PDF13 Nov 2019
Certificates of CA (Form 3)File: Form 3.PDF13 Nov 2019
Certificates of CA (Form 3)File: Form 3.PDF13 Nov 2019
Certificates of CA (Form 3)File: Form 3.PDF13 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF10 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF10 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF10 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 (2).PDF10 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form2.PDF10 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.PDF26 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificiate Form 1.PDF26 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.PDF26 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.PDF26 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF1 Oct 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCC.pdf20 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF28 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf28 May 2018
Certificates of CA (Form 3)File: Form 3.pdf28 May 2018
Building plan approvalFile: LETTER 1.pdf31 Aug 2017
Building plan approvalFile: LETTER 2.pdf31 Aug 2017
Building plan approvalFile: LETTER 3.pdf31 Aug 2017
Building plan approvalFile: LETTER 4.pdf31 Aug 2017
Building plan approvalFile: IOD PLAN.pdf31 Aug 2017
Layout approvalFile: layout- sub division plan.pdf31 Aug 2017
Layout approvalFile: IOD PLAN.pdf31 Aug 2017
PAN CardFile: pan card.pdf31 Aug 2017
Copy of the legal title reportFile: Title Search Report.pdf31 Aug 2017
Details of encumbrancesFile: encumbrance certificate_1 (1).pdf31 Aug 2017
Copy of Layout Approval (in case of layout)File: layout- sub division plan.pdf31 Aug 2017
Copy of Layout Approval (in case of layout)File: IOD PLAN.pdf31 Aug 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 45 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmPATIL PRASAD AND SHANTI Completed 85Lapsed / revoked 75Other 109Dot size: filed unitsN

Filed coordinates, straight-line distance. 269 registered projects within 2 km.

Builder: MEERA ENTERPRISES

Meera Enterprises has 2 registrations on MahaRERA, including ASIAN GALAXY B WING and PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT?

The registered promoter entity is MEERA ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT?

The professionals named in the filing: Architect: ASHISH BHATT; Architect: RAMESH TAMBAT; Engineer: VINAYAK CHOPDEKAR AND ASSOCIATES; Chartered Accountant: Y S Muzumdar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT PROJECT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PATIL PRASAD AND SHANTI SADAN REDEVELOPMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.