Home / Browse projects / Thane, Maharashtra / PATASKAR ECLAT BUILDING NO 3

Registration lapsed No litigation declared Commercial project

PATASKAR ECLAT BUILDING NO 3

By PATASKAR DEVELOPERS PVT. LTD

RG-MH-25229 · RERA P51700004805 · Last updated on MahaRERA portal: 3 Feb 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 81 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 80%
0Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

PATASKAR ECLAT BUILDING NO 3 is a Commercial project by PATASKAR DEVELOPERS PVT. LTD in Thane, Maharashtra, registered with MahaRERA as P51700004805 on 9 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 81 months from the original filing.

At a glance

Project

  • NamePATASKAR ECLAT BUILDING NO 3
  • TypeCommercial
  • Location
    • Ghodbunder road
    • Kavesar
    • Thane (M Corp.)
    • Thane
    • 400602
  • Pincode400602
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700004805
  • ReraGenie IDRG-MH-25229

Builder

  • NamePATASKAR DEVELOPERS PVT. LTD
  • Entity typeCompany
  • Managing DirectorRAJANINATH GOVIND PATASKAR
  • ChairpersonAMIT RAJANINATH PATASKAR
  • Declared earlier projects2 →

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PATASKAR ECLAT BUILDING NO 3NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

PATASKAR ECLAT BUILDING NO 3: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 3 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes85%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes85%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed129

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots129
Open Space129

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,900 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4471.0
Proposed, not sanctioned2,586 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchA WING RAJYOG RESIDENCY, DR RP ROAD, MULUND WEST MUMBAI 400080

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSUBHASH GUPTE OF SCAPES
Chartered AccountantHIREN K GORADIYA
PartnerRole in project
PATASKAR DEVELOPERS PVT. LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700001724Mar 2019 → Mar 2021

Reason as filed by the promoterThe revised plans are not sanctioned by the Thane Municipal Corporation. Loading of TDR on the project was subject to a Govt. Directive for the issue of immediate road front width and not the Dp road width. Decision took considerable time. Moreover while amalgamating the adjacent plot, the TMC has ordered some legal paper work like TILR and updation in revenue records which also took considerable amount of time. The plans are likely to pass in couple of months. Then we can commence the construction work. Also please take a note that WE HAVE NOT SOLD/TAKEN MONEY./ENTERED INTO AGREEMENT WITH ANY

EXT51700009823Mar 2019 → Mar 2023

Reason as filed by the promoterIn view of the recent;y passed Unified DCR rules & regulations of 2020, the plans needs amendment, however some clarity issues from the Municipal Corporation of Thane on the implementation of new unified DCR rules and also by the recent second wave of the Corona pandemic, we will try to complete the work by 31-3-2023 as soon as the amendment is sanction.

EXT51700013762Mar 2019 → Dec 2025

Reason as filed by the promoterBig commercial building, very less demand for big floor plate, offers of rent or sale does not match the expectations. we are holding the project to go on one shot single point sale instead of giving it in parts.

Litigation declared2

CaseCourtStatus
SPL CS NO 45/2008/2008HON CIVIL JUDGE SD THANEAPPEAL PENDING IN HIGH COURT
SPL CS NO 395/2010/2010HON CIVIL JUDGE SD THANEAPPEAL PENDING IN HIGH COURT

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Scapes.pdf3 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 2019 Architech Certificate.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 Enginee certificate.pdf3 Feb 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold Inventory.pdf3 Feb 2023
Certificates of CA (Form 3)File: Form 3 Prashant Kadam.pdf3 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf3 Feb 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf23 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEER CERTIFICATE FY 2019 20.pdf23 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER CERTIFICATE FY 2020 21.pdf23 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 RERA 2018-19.pdf23 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form-5 2019-20 (1).pdf23 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5 2020-21 (1).pdf23 Sep 2021
Certificates of CA (Form 3)File: FORM 3 Prashant Kadam CA 2021.pdf11 Aug 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold inventory.pdf9 Jun 2021
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 RERA 2019.pdf9 Aug 2019
Commencement Certificates / NA Order for plotted developmentFile: BLDG 3 CC Self Certified.pdf26 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: BLDG 3 Plinth Self Certified.pdf26 Mar 2018
Building plan approvalFile: BLDG PLAN 4.PDF27 Jul 2017
Building plan approvalFile: BLDG PLAN 5.PDF27 Jul 2017
Building plan approvalFile: BLDG PLAN 6.PDF27 Jul 2017
Layout approvalFile: BLDG PLAN 1.PDF27 Jul 2017
PAN CardFile: COMPANY PAN CARD.pdf27 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf27 Jul 2017
Details of encumbrancesFile: LITIGATION CASES RERA UPLOAN FILE.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: BLDG PLAN 1.PDF27 Jul 2017
Building Plan Approval (IOD)File: BLDG PLAN 4.PDF27 Jul 2017
Building Plan Approval (IOD)File: BLDG PLAN 5.PDF27 Jul 2017
Building Plan Approval (IOD)File: BLDG PLAN 6.PDF27 Jul 2017
Declaration in FORM BFile: FORM B.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE.pdf27 Jul 2017
Certificates of CA (Form 3)File: C A CERTIFICATE.pdf27 Jul 2017
Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf27 Jul 2017
Proforma of Allotment letterFile: ALLOTTMENT LETTER.pdf27 Jul 2017
OtherFile: DEV AGR 1.pdf27 Jul 2017
OtherFile: DEV AGR OF OWNER.pdf27 Jul 2017
OtherFile: SUB DEV AGR OF PDPL.pdf27 Jul 2017
OtherFile: BLDG NO 3 PLINTH.pdf27 Jul 2017
OtherFile: PDPL INCORPORATION CERTIFICATE.pdf27 Jul 2017
OtherFile: ARTICLE OF ASSOCIATION.pdf27 Jul 2017
OtherFile: MOA PDPL.pdf27 Jul 2017
OtherFile: PDPL letterhead.pdf27 Jul 2017
OtherFile: PDPL RECEIPT.pdf27 Jul 2017
OtherFile: MTNL BILL PDPL.pdf27 Jul 2017

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
PATASKAR ECLATGB ROAD THANE W92CompletedOct 2015Late, Dec 2017
PATASKAR AVENUETHANE19CompletedSep 2014Late, Oct 2014
PATASKAR ECLATGB ROAD THANE W8CompletedMar 2009Late, Mar 2010

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 81 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PATASKAR ECLAT BUILDING NO 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kavesar7,600+ in Thane

2 kmPATASKAR ECLAT BUILDING Completed 100Lapsed / revoked 24Other 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 185 registered projects within 2 km.

Builder: PATASKAR DEVELOPERS PVT. LTD

PATASKAR DEVELOPERS PVT. LTD has 1 registration on MahaRERA, including PATASKAR ECLAT BUILDING NO 3. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that PATASKAR ECLAT BUILDING NO 3 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PATASKAR ECLAT BUILDING NO 3 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PATASKAR ECLAT BUILDING NO 3?

The registered promoter entity is PATASKAR DEVELOPERS PVT. LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PATASKAR ECLAT BUILDING NO 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PATASKAR ECLAT BUILDING NO 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PATASKAR ECLAT BUILDING NO 3?

The professionals named in the filing: Architect: SUBHASH GUPTE OF SCAPES; Chartered Accountant: HIREN K GORADIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PATASKAR ECLAT BUILDING NO 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PATASKAR ECLAT BUILDING NO 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PATASKAR ECLAT BUILDING NO 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.