Home / Browse projects / Nashik, Maharashtra / PARKSYDE NEST PHASE - 3

Completed No litigation declared Residential / Group Housing project

PARKSYDE NEST PHASE - 3

By JAIKUMAR CONSTRUCTIONS LTD

RG-MH-13508 · RERA P51600025687 · Last updated on MahaRERA portal: 27 Mar 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 6 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
29 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 80%
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

PARKSYDE NEST PHASE - 3 is a Residential / Group Housing project by JAIKUMAR CONSTRUCTIONS LTD in Nashik, Maharashtra, registered with MahaRERA as P51600025687 on 1 Jul 2020. The registration is recorded completed; possession was promised by 30 Jun 2026.

At a glance

Project

  • NamePARKSYDE NEST PHASE - 3
  • TypeResidential / Group Housing
  • Location
    • HANUMAN NAGAR
    • [ANCHAVATI ANNEX
    • Nashik (M Corp.)
    • Nashik
    • 422003
  • Pincode422003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600025687
  • ReraGenie IDRG-MH-13508

Builder

  • NameJAIKUMAR CONSTRUCTIONS LTD
  • Entity typeCompany
  • DirectorsMERZYAN HOSI PATEL, HITEN HARIDAS RAJKOTIA
  • Other registrations8 more →
  • Completed4 of 9
  • Declared earlier projects21 →

Key dates

this monthRegisteredJul 2020PromisedJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Jul 2020
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed92 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA180000
BNA180000
CNA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 27 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 80%.

A92%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed384

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots384
Closed/Covered346
Open Space38
BuildingClosed/CoveredOpen SpaceTotal
A1244128
B10919128
C11315128

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,688 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
ABHISHEK MOHANLAL CHAUHANNashik (M Corp.)Nashik
SUMANGAL BUILDCONNashik (M Corp.)Nashik

Approvals and building plan

Permissible FSI22181.03
Proposed, not sanctioned22,181 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHATTHE NAGAR , GANGAPUR ROAD, NASHIK-422005

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUMESH BAGUL
EngineerPUNIT DINESH CHANDRA RAI
Chartered AccountantKRISHNA JAJOO
Chartered Accountantsharp Aarth and co
PartnerRole in project
JAIKUMAR CONSTRUCTIONS LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jun 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jun 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jun 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jun 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Nov 2024

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CA NEST PHASE 3 JUNE 24.pdf27 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER NEST PHASE 3 JUNE 24.pdf27 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy-Certificate- A-WING.pdf5 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 NEST PHASE 3 AND 3A.pdf28 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT NEST PHASE-3 JUNE-24.pdf25 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Parksyde Nest B wing occupancy certificate.pdf15 Jul 2024
Disclosure of sold/ booked inventoryFile: CA NEST PHASE 3 MARCH-24.pdf9 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER NEST PHASE 3 MARCH-24.pdf29 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA NEST PHASE 3 MARCH-24.pdf29 Jun 2024
Home Buyer /Allottee Grievance Redressal CellFile: Grievance Redressal Cell- Parksyde Nest.pdf28 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QUALITY NEST PHASE 3.pdf20 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT NEST PHASE-3 MARCH-24.pdf30 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 20240430180930.pdf30 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 NEST PHASE 3 2024.pdf7 Mar 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE NEST PHASE 3 DEC-23.pdf6 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER NEST PHASE 3 DEC-23.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA NEST PHASE 3 DEC-23.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT NEST PHASE 3-DEC-23.pdf12 Jan 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE NEST PHASE-3.pdf28 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER NEST PHASE-3 SEP23.pdf16 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA NEST PHASE-3 SEP-23.pdf16 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER NEST PHASE-3 SEP-23.pdf14 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT NEST PHASE 3 SEPT-23.pdf13 Oct 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE NEST PHASE 3.pdf12 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA NEST PHASE-3 JUNE-23.pdf2 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT NEST PHASE 3 JUNE-23.pdf7 Aug 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE NEST P-3 MARCH-23.pdf5 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER MAR-23 NEST P3.pdf17 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA NEST PHASE-3 MAR-23.pdf17 Jul 2023
Details of encumbrancesFile: Mortgage Deed Parksyde Nest Phase 3 HDFC Ltd-66.pdf21 Jun 2023
CERSAI detailsFile: CERSAI parskyde nEST pH 3 nashik.pdf21 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA CERTIFICATE NEST PHASE 3 MARCH-22.pdf25 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT NEST PHASE 3 MARCH-23.pdf18 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY NEST PHASE-3.pdf11 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: STATEMENT OF ACCOUNT NEST PHASE 3.pdf27 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER DEC-22 NEST PHASE 3.pdf18 Mar 2023
Disclosure of sold/ booked inventoryFile: DISCLOSER NEST PHASE -3 DEC-22.pdf18 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA NEST PHASE-3 DEC-22.pdf18 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NEST PHASE 3 Q1 CA.pdf1 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NEST PHASE 3 CA Q2.pdf1 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: STATEMENT OF ACCOUNT NEST PHASE 3.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA CERTIFICATE NEST PHASE 3 MARCH-22.pdf17 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Nest Phase-3 June 22.pdf21 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Nest Phase-3 Sept 22.pdf21 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE NEST PHASE 3.pdf14 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE NEST PHASE 3 Q3.pdf13 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Nest Phase 3 Sept 22.pdf13 Oct 2022
Disclosure of sold/ booked inventoryFile: 20220823170356.pdf23 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Nest Phase 3 June 22.pdf19 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 20220719153411.pdf19 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Nest Phase3 June 22.pdf19 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20220819212408.pdf19 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 20220611155207.pdf11 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Nest Phase 3 Dec21.pdf2 Jun 2022
Disclosure of sold/ booked inventoryFile: 20220409213636.pdf12 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Nest Phase-3 MAr 22.pdf9 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 20220409193257.pdf9 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Nest Phase-3 Mar22.pdf9 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality certificate Phase 3 nest.pdf7 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PHASE-3 CERTIFICATE.pdf6 Jan 2022
Disclosure of sold/ booked inventoryFile: Disclosure of inventory dec21 phase 3 nest.pdf6 Jan 2022
Details of encumbrancesFile: 20211102155213.pdf2 Nov 2021
Details of encumbrancesFile: Mortgage Deed details Parksyde Nest.pdf2 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect nest ph3 sept21.pdf9 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate Nest Phase 3.pdf9 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nest - Phase 3_compressed.pdf9 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: phase 3 NEST (1).pdf7 Oct 2021
Disclosure of sold/ booked inventoryFile: 20211007215835_compressed.pdf7 Oct 2021
Details of encumbrancesFile: NO Encumbrance Nest.pdf12 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate Nest Phase-3.pdf12 Aug 2021
Disclosure of sold/ booked inventoryFile: Inventory Phase3 Nest JUNE21.pdf12 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate NEst Phase3 June21.pdf12 Aug 2021
OtherFile: 20210723195147.pdf23 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Nest PHASE-3 June21.pdf13 Jul 2021
OtherFile: Clarification Letter revised Phase 3.pdf23 Feb 2021
OtherFile: Clarification of Changes Phase-3.pdf9 Feb 2021
Declaration in FORM BFile: Form B Parksyde Nest Phase-3 .pdf23 Jun 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archtect Certificate Phase-3.pdf23 Jun 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate Parksyde NEst Phase 3.pdf23 Jun 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Phase 3.pdf23 Jun 2020

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

6 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Parksyde Homes Phase 5AP51600004799Hanuman Nagar, Nashik-Aug 2017CompletedJun 2025Sep 2023
PARKSYDE HOMES PHASE 2BPARKSYDE HOMES S NO 256 PART 257 PART PANCHAVATI ANNEX NASHIK3-CompletedApr 2020Nov 2018
PARKSYDE HOMES PHASE -2AS NO. 256 257 PART HANUMAN NAGAR PANCHAVATI ANNEX NASHIK 4220033-CompletedApr 2020Apr 2019
PARKSYDE HOMES PHASE 4BPARKSYDE HOMES S NO 256 PART 257 PART HANUMAN NAGAR PANCHAVATI NASHIK-4220032-CompletedOct 2019Jul 2019
PARKSYDE HOMES PHASE 4APARKSYDE HOMES S NO. 256 PART 257 PART HANUMAN NAGAR PANCHAVATI ANNEX NASHIK4-CompletedMar 2019Nov 2018
PARKSYDE HOMES PHASE- 1PARKSYDE HOMES S NO 256 257 PART HANUMAN NAGAR NASHIK 4220035-CompletedJun 2018Oct 2017

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARKSYDE NEST PHASE - 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near [ANCHAVATI ANNEX4,100+ in Nashik

2 kmPARKSYDE NEST PHASE - 3Completed 49Lapsed / revoked 16Other 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: JAIKUMAR CONSTRUCTIONS LTD

JAIKUMAR CONSTRUCTIONS LTD has 9 registrations on MahaRERA, including PARKSYDE NEST PHASE - 1 and PARKSYDE NEST PHASE - 2. Its filings disclose 21 earlier MahaRERA projects: declares 17 of 17 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if PARKSYDE NEST PHASE - 3 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARKSYDE NEST PHASE - 3?

The registered promoter entity is JAIKUMAR CONSTRUCTIONS LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARKSYDE NEST PHASE - 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARKSYDE NEST PHASE - 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARKSYDE NEST PHASE - 3?

The professionals named in the filing: Architect: UMESH BAGUL; Engineer: PUNIT DINESH CHANDRA RAI; Chartered Accountant: KRISHNA JAJOO; Chartered Accountant: sharp Aarth and co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARKSYDE NEST PHASE - 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARKSYDE NEST PHASE - 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARKSYDE NEST PHASE - 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.