Registration lapsed No litigation declared Residential / Group Housing project

PARK ASTRA

By PRIDE PURPLE INFRASTRUCTURE

RG-MH-48159 · RERA P52100024449 · Last updated on MahaRERA portal: 21 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
19 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 80%
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

PARK ASTRA is a Residential / Group Housing project by PRIDE PURPLE INFRASTRUCTURE in Pune, Maharashtra, registered with MahaRERA as P52100024449 on 13 Feb 2020. Possession was promised by 30 Dec 2025 and is now 10 months past that date.

At a glance

Project

  • NamePARK ASTRA
  • TypeResidential / Group Housing
  • Location
    • MARUNJI GAON
    • MARUNJI
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • RERA no.P52100024449
  • ReraGenie IDRG-MH-48159

Builder

  • NamePRIDE PURPLE INFRASTRUCTURE
  • Entity typePartnership
  • GSTIN27AAMFP1587H1ZT
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerSHRAVAN DEVAKINANDAN AGARWAL
  • Other registrations9 more →
  • Completed3 of 10
  • No longer live3 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredFeb 2020PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on13 Feb 2020
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E FNA200000
G HNA200000
I JNA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 21 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 80%.

E F69%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G H69%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
I J76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterYes60%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes30%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed408

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots408
Closed/Covered408
BuildingClosed/CoveredTotal
E F136136
G H136136
I J136136

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,113 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI50550.54
Proposed, not sanctioned40,440 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHE CITY JEWEL MALL NEAR MENS AVENUE 709 NARAYAN PETH LAXMI ROAD

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCRYSTAL ARCH
Chartered AccountantParth v Jain & Associates
PartnerRole in project
PRIDE PURPLE INFRASTRUCTURE-

Litigation declared1

CaseCourtStatus
2187/2019CIVIL JUDGE SENIOR DIVISION PUNEFILING OF SAY

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Feb 2025

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - LegalFile: FORM 4 ASTRA.pdf21 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FORM 4 ASTRA.pdf21 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Astra form 4 completion _ 4-7-2024.pdf24 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-Park Astra.pdf12 Dec 2024
Details of encumbrances concerned to FinanceFile: Release Deed _ Kotak_19187-2024- Index.pdf30 Nov 2024
Details of encumbrances concerned to LegalFile: Release Deed _ Kotak_19187-2024- Index.pdf30 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Park Astra Completion.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Astra phase - Engg March 24.pdf24 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Rera_Quality _Astra March 24.pdf24 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park Astra -Form 3 Sign copy_.pdf24 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PARK ASTRA-Form 3_C.pdf6 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PARK ASTRA-Form 3_C.pdf6 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Astra Ph I_Form 5_FY 22-23_compressed.pdf5 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch_Astra I.pdf7 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Astra Ph 1_3009_DSC_compressed.pdf7 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera_Engg_Astra I Sep 23.pdf11 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Rera_Quality _Astra I Sep 23.pdf11 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pi7_00Astra_Ph_I_Form_3_June_23_compressed_1_1.pdf31 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Astra Ph I_Form 3_March 23_compressed.pdf6 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERT PARK ASTRA 31012023.pdf2 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: PPIRera Audit Report.pdf20 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: PPIRera ReportForm 5 FinalPark Astra.pdf20 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT PARK ASTRA PLOT 6 31122022.pdf10 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QTY ASSURANCE CERT PARK ASTRA PH II 31122022.pdf10 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QTY ASSURANCE CERT PARK ASTRA 31122022.pdf10 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 PARK ASTRA 21112022.pdf24 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RERA PARK ASTRA QUALITY SEPT22.pdf14 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Rera Quality Park Astra June 22.pdf22 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Rera Quality park Astra.pdf12 Apr 2022
Details of encumbrancesFile: MORTGAGE DEED PARK ASTRA MARUNJI 31122021.pdf28 Feb 2022
CERSAI detailsFile: CERSAI Park Astra.pdf25 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Rera Quality Certificate Park Astra Dec 21.pdf6 Jan 2022
CERSAI detailsFile: UNDERTAKING PARK CONNECT PH II.pdf6 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Rera Quality Park Astra Sept 21.pdf9 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PARK ASTRA SIGNED FORM 3.pdf6 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Rera Quality Park Astra June 21.pdf17 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Rera Quality Park Connect March 21.pdf8 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Rera Quality Park Astra Dec 20.pdf14 Jan 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Certificate Park Astra Sept 20.pdf10 Oct 2020
Layout approvalFile: LAYOUT.pdf3 Aug 2020
Building plan approvalFile: IJ BUILDING 3,5,6,9,15,16 FLOOR PLAN.pdf3 Aug 2020
Building plan approvalFile: IJ BUILDING 7,8,11,17 FLOOR PLAN.pdf3 Aug 2020
Building plan approvalFile: IJ BUILDING 12, 13 FLOOR PLAN.pdf3 Aug 2020
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf3 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: IJ BUILDING 3,5,6,9,15,16 FLOOR PLAN.pdf3 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: IJ BUILDING 7,8,11,17 FLOOR PLAN.pdf3 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: IJ BUILDING 12, 13 FLOOR PLAN.pdf3 Aug 2020
Layout approvalFile: LAYOUT.pdf7 Feb 2020
Building plan approvalFile: FLOOR PLAN.pdf7 Feb 2020
PAN CardFile: PAN CARD.pdf7 Feb 2020
Copy of the legal title reportFile: TITLE REPORT S NO 40.pdf7 Feb 2020
Copy of the legal title reportFile: TITLE REPORT S NO 41.pdf7 Feb 2020
Details of encumbrancesFile: SELF DECLARATION PARK ASTRA.pdf7 Feb 2020
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf7 Feb 2020
Building Plan Approval / NA Order for plotted developmentFile: FLOOR PLAN.pdf7 Feb 2020
Commencement Certificates / NA Order for plotted developmentFile: NA ORDER.pdf7 Feb 2020
Declaration in FORM BFile: B FORM AFFIDAVIT PARK ASTRA.pdf7 Feb 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 Park Astra.pdf7 Feb 2020
Proforma of Allotment letterFile: DRAFT AGREEMENT.pdf7 Feb 2020

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARK ASTRA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MARUNJI13,700+ in Pune

Builder: PRIDE PURPLE INFRASTRUCTURE

PRIDE PURPLE INFRASTRUCTURE has 10 registrations on MahaRERA, including PARK CONNECT and PARK ASTRA. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that PARK ASTRA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARK ASTRA is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARK ASTRA?

The registered promoter entity is PRIDE PURPLE INFRASTRUCTURE, a partnership as per the filing. Its GSTIN 27AAMFP1587H1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARK ASTRA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARK ASTRA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARK ASTRA?

The professionals named in the filing: Architect: CRYSTAL ARCH; Chartered Accountant: Parth v Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARK ASTRA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARK ASTRA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARK ASTRA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.