Registration lapsed No litigation declared Commercial project

PARINEE EMINENCE PHASE 1

By Om Omega Shelters Private Limited

RG-MH-40384 · RERA P51900015555 · Last updated on MahaRERA portal: 25 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • 29 complaints at MahaRERA
  • Completion date moved by 30 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 90%
29Complaints at MahaRERAon this registration
Jump to the 112 documents Report an error

PARINEE EMINENCE PHASE 1 is a Commercial project by Om Omega Shelters Private Limited in Mumbai City, Maharashtra, registered with MahaRERA as P51900015555 on 8 Mar 2018. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 30 months from the original filing. 29 complaints are on record with the regulator.

At a glance

Project

  • NamePARINEE EMINENCE PHASE 1
  • TypeCommercial
  • Location
    • DAINIK SHIVNER MARG
    • WORLI
    • Ward GSouth
    • Mumbai City
    • 400018
  • Pincode400018
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900015555
  • ReraGenie IDRG-MH-40384

Builder

  • NameOm Omega Shelters Private Limited
  • Entity typeCompany
  • DirectorsVipul Dilip Shah, Dhaval Dilip Shah

Key dates

7 months past promisethis monthRegisteredMar 2018First promiseSep 2023Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Mar 2018
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 30 Sep 2023)
  • Buildings1 building record
  • Documents filed112 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARINEE EMINENCE PHASE 1NA400000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.

PARINEE EMINENCE PHASE 1: 25% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed901

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots901
Closed/Covered901

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,068 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI62496.0
Proposed, not sanctioned45,496 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRNA CORPORATE PARK NEXT TO COLLECTORS OFFICE BANDRA EAST MUMBAI 400018

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectConsultant Combined
EngineerJW CONSULTANTS LLP
PartnerRole in project
Om Omega Shelters Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900009712Sep 2023 → Mar 2026

Reason as filed by the promoterThe project has undergone changes due to revision in plans and increase in FSI as per New DCPR 2034. Necessary consents for the revision of plans and extension of Project Completion as per Format B (Circular No. 28 dated 8th March 2021) is obtained and attached herewith. Due to the time elapsed in getting revised approvals and time required to construct the building, we are seeking extended date of 31st March 2026.

Litigation declared2

CaseCourtStatus
1108/2011Bombay High CourtPending
1163/2011Bombay High CourtPending

Complaints filed with MahaRERA29

Case no.ComplainantRespondentFiled
CC12400606Sammaan Capital LimitedOm Omega Shelters Private Limited28/10/2024
CC12400608Sammaan Capital LimitedOm Omega Shelters Private Limited29/10/2024
CC12400610Sammaan Capital LimitedOm Omega Shelters Private Limited29/10/2024
CC12400653Sammaan Capital LimitedOm Omega Shelters Private Limited05/11/2024
CC12400654Sammaan Capital LimitedOm Omega Shelters Private Limited05/11/2024
CC12400655Sammaan Capital LimitedOm Omega Shelters Private Limited05/11/2024
CC12400657Sammaan Capital LimitedOm Omega Shelters Private Limited05/11/2024
CC12400658Sammaan Capital LimitedOm Omega Shelters Private Limited05/11/2024
CC12400659Sammaan Capital LimitedOm Omega Shelters Private Limited05/11/2024
CC12400660Sammaan Capital LimitedOm Omega Shelters Private Limited05/11/2024
CC12400678Sammaan Capital LimitedOm Omega Shelters Private Limited06/11/2024
CC12400679Sammaan Capital LimitedOm Omega Shelters Private Limited06/11/2024
CC12400680Sammaan Capital LimitedOm Omega Shelters Private Limited06/11/2024
CC12400686Sammaan Capital LimitedOm Omega Shelters Private Limited06/11/2024
CC12400687Sammaan Capital LimitedOm Omega Shelters Private Limited06/11/2024
CC12400690Sammaan Capital LimitedOm Omega Shelters Private Limited07/11/2024
CC12400691Sammaan Capital LimitedOm Omega Shelters Private Limited07/11/2024
CC12400699Sammaan Capital LimitedOm Omega Shelters Private Limited07/11/2024
CC12400700Sammaan Capital LimitedOm Omega Shelters Private Limited07/11/2024
CC12500068Behrulal JainOm Omega Shelters Private Limited08/01/2025
CC12500076Ms Geeta Behrulal JainOm Omega Shelters Private Limited08/01/2025
CC12500125B One Business House Private LimitedOm Omega Shelters Private Limited13/01/2025
CC12500296Ravindra Kumar VermaOm Omega Shelters Private Limited27/01/2025
CC12500873Roadwings Western Pvt LtdOm Omega Shelters Private Limited13/03/2025
CC12600855PRATHMESH UDAY KHHAREMahadev Realtors Worli LLp16/02/2026
CC12600857Tarunkumar Panday PandayOm Omega Shelters Private Limited16/02/2026
CC12600861Adv. Sagar Ramesh NaikOm Omega Shelters Private Limited16/02/2026
CC12600862Yogesh Rasiklal ShahOm Omega Shelters Private Limited16/02/2026
CC12604295RAMESHKUMAR BHATTOm Omega Shelters Private Limited09/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Mar 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed112

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence June 2024.pdf25 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence Sept 2024.pdf25 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence Dec 2024.pdf25 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence March 2024.pdf25 Mar 2025
Certificates of CA (Form 3)File: Form 3 Eminence December 2024.pdf25 Mar 2025
Certificates of CA (Form 3)File: Form 3 Eminence September 2024.pdf25 Mar 2025
Certificates of CA (Form 3)File: Form 3 Eminence June 2024_2.pdf25 Mar 2025
Certificates of CA (Form 3)File: Form 3 Eminence June 2024_1.pdf25 Mar 2025
Certificates of CA (Form 3)File: Form 3 Eminence March 2024_2.pdf25 Mar 2025
Certificates of CA (Form 3)File: Form 3 Eminence March 2024_1.pdf25 Mar 2025
Certificates of CA (Form 3)File: Form 3 Worli Mar 2023_1.pdf25 Mar 2025
Certificates of CA (Form 5)File: Form 5- Parinee Eminence Phase 1 - FY 2023-24.pdf25 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eminence March 2024.pdf25 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 Eminence June 2024.pdf25 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 Eminence Sept 2024.pdf25 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eminence_Form 2_Dec 2024.pdf25 Mar 2025
Disclosure of sold/ booked inventoryFile: Parinee Eminence _Sold, Unsold and booked Dec 2024.pdf25 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Eminence March 2024.pdf25 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Eminence March 2024.pdf25 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5- Parinee Eminence Phase 1 - FY 2023-24.pdf25 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Worli June 2023.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Worli Sep 2023.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Worli Dec 2023.pdf4 Jul 2024
Certificates of CA (Form 3)File: Form 3 Worli June 2023.pdf4 Jul 2024
Certificates of CA (Form 3)File: Form 3 Worli Sep 2023.pdf4 Jul 2024
Certificates of CA (Form 3)File: Form 3 Worli Dec 2023.pdf4 Jul 2024
OtherFile: SRA Order_OOSPL.pdf1 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eminence June 2023.pdf13 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eminence Sep 2023.pdf13 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eminence Dec 2023.pdf13 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Booked Inventory March 2024_1.pdf13 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Booked Inventory March 2024_2.pdf13 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence MARCH 2018.pdf5 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence MARCH 2019.pdf5 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence MARCH 2020.pdf5 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence MARCH 2021.pdf5 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence MARCH 2021.pdf5 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence MARCH 2022.pdf5 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence JUNE 2022.pdf5 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence SEPT 2022.pdf5 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence DEC 2022.pdf5 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Eminence MARCH 2023.pdf5 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Parinee Eminence March 2019.pdf5 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Parinee Eminence March 2020.pdf5 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Parinee Eminence March 2021.pdf5 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eminence Mar 2022.pdf5 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eminence June 2022.pdf5 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eminence 30 September 2022.pdf5 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 Eminence DEC 2022.pdf5 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Eminece 31st March 2023.pdf5 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Eminence March 2020.pdf5 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Eminence March 2021.pdf5 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurnace_Eminence.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli June 2023.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli Sep 2023.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli Dec 2023.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli June 2022_1.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli June 2022_2.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli June 2022_3.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli September 2022_1.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli September 2022_2.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli September 2022_3.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli Dec 2022_1.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli Dec 2022_2.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli Dec 2022_3.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli Mar 2023_1.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli Mar 2023_2.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli Mar 2023_3.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli March 2020.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli March 2018_1.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli March 2018_2.pdf5 Mar 2024
Certificates of CA (Form 3)File: Form 3 Worli March 2018_3.pdf5 Mar 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory_1.pdf21 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory_2.pdf21 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory_3.pdf21 Oct 2023
Certificates of CA (Form 5)File: Form 5- Parinee Eminence Phase 1_FY 2022-23.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- Parinee Eminence Phase 1_FY 2022-23.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 5 Certificates of CA (Form 5) (2).pdf10 Jan 2023
Certificates of CA (Form 5)File: RERA Form 5 Parinee Eminence Phase 1 FY 21 22.pdf30 Aug 2022
Certificates of CA (Form 3)File: Rera Form 3 Eminence.pdf12 Aug 2022

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 30 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARINEE EMINENCE PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WORLI780+ in Mumbai City

2 kmPARINEE EMINENCE PHASE 1Completed 15Lapsed / revoked 17Other 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 59 registered projects within 2 km.

Builder: Om Omega Shelters Private Limited

Om Omega Shelters Private Limited has 1 registration on MahaRERA, including PARINEE EMINENCE PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that PARINEE EMINENCE PHASE 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARINEE EMINENCE PHASE 1 is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARINEE EMINENCE PHASE 1?

The registered promoter entity is Om Omega Shelters Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARINEE EMINENCE PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PARINEE EMINENCE PHASE 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PARINEE EMINENCE PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARINEE EMINENCE PHASE 1?

The professionals named in the filing: Architect: Consultant Combined; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARINEE EMINENCE PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARINEE EMINENCE PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARINEE EMINENCE PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.