ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / PARIJATAK PHASE I A AND B WING

Registration lapsed No litigation declared Residential / Group Housing project

PARIJATAK PHASE I A AND B WING

By VARAD BUILDERS

RG-MH-28864 · RERA P51700027293 · Last updated on MahaRERA portal: 29 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
11 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 95%
74 of 128Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 203 documents Report an error

PARIJATAK PHASE I A AND B WING is a Residential / Group Housing project by VARAD BUILDERS in Thane, Maharashtra, registered with MahaRERA as P51700027293 on 1 Dec 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 12 months from the original filing. 54 of the 128 units on this registration are recorded sold or booked, and 11 of 22 construction stages are filed complete.

At a glance

Project

  • NamePARIJATAK PHASE I A AND B WING
  • TypeResidential / Group Housing
  • Location
    • Shirgaon
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700027293
  • ReraGenie IDRG-MH-28864

Builder

  • NameVARAD BUILDERS
  • Entity typePartnership
  • PartnersCHETAN SHARAD APTE, AJIT BHALCHANDRA APTE, Tushar Sharad Apte, Amol Bhalchandra Apte

Key dates

4 months past promisethis monthRegisteredDec 2020First promiseJun 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Dec 2020
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
  • Buildings2 building records
  • Documents filed203 files

Current status

42%54 of 128 units booked
89.1%Work done, per cost certificate

Figures as on 29 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Parijatak Phase I A WingNA8863063
PARIJATAK PHASE I B WINGNA121265065

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.

Parijatak Phase I A Wing64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PARIJATAK PHASE I B WING57%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%

Progress on shared amenities15

As on 29 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,317 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityKulgaon Badlapur Nagarparishad
Permissible FSI3424.42
Proposed, not sanctioned3,424 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1 tO 4 jINESHWAR aPARTMENT MIDC ROAD GANDHI CHOWK BADLAPUR EAST 421503
Estimated costRs 15.68 cr
Cost incurredRs 13.97 cr
Work done89.09%
BuildingWingEstimatedIncurred
PARIJATAK PHASE I B WINGNARs 9.00 crRs 7.87 cr
Parijatak Phase I A WingNARs 6.10 crRs 6.10 cr
-NARs 58.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchitects Inc
EngineerSUDHIR M OAK AMAR AGASHE
Chartered AccountantDSJAIN & CO
Chartered AccountantAjitha Thampan
PartnerRole in project
VARAD BUILDERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA07082502333Jun 2025 → Jun 2026

Reason as filed by the promoterThe Project Consists of 2 wings 1 wing, Wing A is completed Fully and OC has also been received and Uploaded. However, due to some Financial Constraints 2nd wing work is completed to the extent of 70% and 30% is remaining . Hence, the extension is required and we sought for Project extension

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Mar 2024

Documents filed203

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 203 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 3File: form 3.pdf29 Jul 2026
Form 1File: engineer certificate.pdf29 Jul 2026
Form 2File: engineer certificate.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf29 Jul 2026
Form 3File: form 3.pdf29 Jul 2026
Form 1File: Adobe Scan 03 Jul 2026 (1).pdf29 Jul 2026
Form 2File: engineer certificate.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf29 Jul 2026
Form 1File: FORM 1.pdf29 Jul 2026
Form 2File: FORM 2.pdf29 Jul 2026
Form 3File: Form 3.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: sold unsold inventory.pdf29 Jul 2026
Form 1File: FORM 1.pdf29 Jul 2026
Form 2File: FORM 2.pdf29 Jul 2026
Form 3File: FORM 3 SEP 21.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: sold unsold inventory.pdf29 Jul 2026
Form 1File: Form 1.pdf29 Jul 2026
Form 2File: form 2.pdf29 Jul 2026
Form 3File: Form 3_com.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: sold unsold inventory.pdf29 Jul 2026
Form 1File: FORM 1.pdf29 Jul 2026
Form 2File: FORM 2.pdf29 Jul 2026
Form 3File: Form 3.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: sold unsold inventory.pdf29 Jul 2026
Form 1File: Form-1 june-22.pdf29 Jul 2026
Form 2File: Form-2 june-22.pdf29 Jul 2026
Form 3File: Form-3 june 22_compressed.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: varad builders sold unsold.pdf29 Jul 2026
Form 1File: form 1.pdf29 Jul 2026
Form 2File: Form-2.pdf29 Jul 2026
Form 3File: FORM-3 Sept-22_compressed.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: varad builders sold unsold.pdf29 Jul 2026
Form 1File: Form 1.pdf29 Jul 2026
Form 2File: Form 2.pdf29 Jul 2026
Form 3File: Form 3.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf29 Jul 2026
Form 1File: Form 1.pdf29 Jul 2026
Form 2File: Form 2.pdf29 Jul 2026
Form 3File: Form 3.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf29 Jul 2026
Form 1File: Form 1.pdf29 Jul 2026
Form 2File: Form 2.pdf29 Jul 2026
Form 3File: Form 3.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold disclosure.pdf29 Jul 2026
Form 1File: FORM 1.pdf29 Jul 2026
Form 2File: Form 2 jun.pdf29 Jul 2026
Form 3File: form 3 new.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold quantity dated 30-06-2024.pdf29 Jul 2026
Form 1File: Form 1.pdf29 Jul 2026
Form 2File: form 2.pdf29 Jul 2026
Form 3File: Scan_Sept23 Form 3.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf29 Jul 2026
Form 1File: FORM 1.pdf29 Jul 2026
Form 2File: FORM 2.pdf29 Jul 2026
Form 3File: form 3 new.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold Qty 30th Sep 24 Varad Builders.pdf29 Jul 2026
Form 1File: Form 1.pdf29 Jul 2026
Form 2File: form 2.pdf29 Jul 2026
Form 3File: Scan_Dec23 form 3.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf29 Jul 2026
Form 1File: FORM 1.pdf29 Jul 2026
Form 2File: Form 2 Dec.pdf29 Jul 2026
Form 3File: form 3 New.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf29 Jul 2026
Form 1File: Form 2 A.pdf29 Jul 2026
Form 2File: Form 2.pdf29 Jul 2026
Form 3File: varad form 3 signed_.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold Quantity Dated 31-03-2024.pdf29 Jul 2026
Form 1File: Adobe Scan 16 May 2025.pdf29 Jul 2026
Form 2File: Form 2 mar.pdf29 Jul 2026
Form 3File: Form 3 Mar 25.pdf29 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold quantity dated 30-06-2024.pdf29 Jul 2026
Withdrawal Update Form 1File: FORM 1.pdf29 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf29 Jul 2026
Withdrawal Update Form 3File: form 3.pdf29 Jul 2026
Form 2A (FY 2020-2021)File: Form 2 A.pdf29 Jul 2026
Form 2A (FY 2021-2022)File: Form 2 A.pdf29 Jul 2026
Form 2A (FY 2022-2023)File: Form 2 A.pdf29 Jul 2026
Form 2A (FY 2024-2025)File: Form 2 A.pdf29 Jul 2026
Form 2A (FY 2023-2024)File: Form 2 A.pdf29 Jul 2026

How this compares with Thane

42%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARIJATAK PHASE I A AND B WING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shirgaon7,600+ in Thane

2 kmPARIJATAK PHASE I A AND Completed 150Lapsed / revoked 52Other 107Dot size: filed unitsN

Filed coordinates, straight-line distance. 309 registered projects within 2 km.

Builder: VARAD BUILDERS

VARAD BUILDERS has 1 registration on MahaRERA, including PARIJATAK PHASE I A AND B WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that PARIJATAK PHASE I A AND B WING shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARIJATAK PHASE I A AND B WING is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARIJATAK PHASE I A AND B WING?

The registered promoter entity is VARAD BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARIJATAK PHASE I A AND B WING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARIJATAK PHASE I A AND B WING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARIJATAK PHASE I A AND B WING?

The professionals named in the filing: Architect: Architects Inc; Engineer: SUDHIR M OAK AMAR AGASHE; Chartered Accountant: DSJAIN & CO; Chartered Accountant: Ajitha Thampan. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARIJATAK PHASE I A AND B WING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARIJATAK PHASE I A AND B WING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARIJATAK PHASE I A AND B WING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.