Home / Browse projects / Mumbai Suburban, Maharashtra / Parijat Towers

Registration lapsed No litigation declared Residential / Group Housing project

Parijat Towers

By BETTER BUILDERS AND INFRASTRUCTURE PRIVATE LTD

RG-MH-11726 · RERA P51800004762 · Last updated on MahaRERA portal: 13 Oct 2020

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date
  • 10 complaints at MahaRERA
  • Completion date moved by 51 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
1 of 11Construction stages donefurthest along: Stilt Floor, 90%
10Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

Parijat Towers is a Residential / Group Housing project by BETTER BUILDERS AND INFRASTRUCTURE PRIVATE LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004762 on 9 Aug 2017. Possession was promised by 30 Jun 2023 and is now 40 months past that date. The completion date has moved by 51 months from the original filing. 10 complaints are on record with the regulator.

At a glance

Project

  • NameParijat Towers
  • TypeResidential / Group Housing
  • Location
    • Sakivihar Road
    • Chandivali
    • Andheri
    • Mumbai Suburban
    • 400072
  • Pincode400072
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800004762
  • ReraGenie IDRG-MH-11726

Builder

  • NameBETTER BUILDERS AND INFRASTRUCTURE PRIVATE LTD
  • Entity typeCompany
  • Managing DirectorsSHYAM DEVRAJ BALI, UMESH JANSUKHLAL VYAS
  • Declared earlier projects1 →

Key dates

40 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARIJAT TOWERSNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Oct 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.

PARIJAT TOWERS: 62% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor90%
Slabs of Super Structure71%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 13 Oct 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes80%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes15%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes70%
Open ParkingYes0%

Parking filed8

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots8
Open Space8

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,338 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10705.77
Proposed, not sanctioned6,387 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 1 Milap Cinema S V Road Kandivali W Mumbai Maharashtra 400067

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHISH SOLANKI
EngineerV V JOSHI
Chartered AccountantJigar Zaveri & Associates
PartnerRole in project
BETTER BUILDERS AND INFRASTRUCTURE PRIVATE LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800006294Mar 2019 → Dec 2022

Reason as filed by the promoterWe state that due to delay in implementation of DCR 2034, there was delay in approval of plans we have put up for amendment of plans further as per the process we are compiling various procedure and as soon as on receipt of commencement Certificate we will start the construction work and complete the same within time line, also we are getting benefit of additional FSI, therefore we will utilize of the Additional FSI by way of construction of additional floors on the A, and B and constructing additional wing D in the current property layout without changing layout/plan and we may modify Ameniti

EXT51800000598Mar 2019 → Mar 2020

Reason as filed by the promoter1. Release of new D.P - this was slated for March and then June this year, but has not yet been released. As per the new DC Rules within the new DP 2034 announced, the FSI potential is to be calculated on the Gross Plot Area, thereby resulting in substantial savings in TDR costs. 2. Shortage of TDR in the open market for the past year or so. 3. The TDR costs have skyrocketed, whereas the Selling Price has either been stagnant or has reduced by 15-20 % across all areas. 4. Shortage of skilled manpower with Contractors. 5. Introduction of GST has also impacted Sales potential as buyers are on th

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000090138Mohnish SaraswatBetter Builders & Infrastructure Pvt Ltd22/07/2019
CC006000000090139Siddhi Tushar Udani & Dhwani Tushar Udani & Tushar D UdaniBetter Builders & Infrastructure Pvt Ltd22/07/2019
CC006000000090140Prashant P Kamath & Prajnya P KamathBetter Builders & Infrastructure Pvt Ltd22/07/2019
CC006000000090135Nirav Kirtikumar Salot & Shirish Laxmichand MehtaBetter Builders & Infrastructure Pvt. Ltd.22/07/2019
CC006000000090141Subhash S Suriya & Snehlata Subhsh SuriyaBetter Builders & Infrastructure Pvt Ltd22/07/2019
CC006000000193742Sagar Digwalekar & Jyoti Arun DhuhaleBetter Builders & Infrastructure Pvt Ltd18/08/2020
CC006000000193783Bharati Shah, Dharmesh Shah & Nimesh ShahBetter Builders & Infrastructure Pvt Ltd24/08/2020
CC006000000193784Kalpesh R Mehta & Vibhuti K MehtaBetter Builders & Infrastructure Pvt Ltd24/08/2020
CC006000000303719MAHESH ATMARAM MANGLANIBetter Builders& Infrastructure Pvt Ltd19/12/2022
CC006000000429310VijayKumar Manubhai VedBetter Builders and Infrastructure Private Limited19/02/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Sep 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form 3.pdf13 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 Architect Certificate.pdf14 Feb 2019
Certificates of CA (Form 3)File: FORM 3 BY CA.pdf14 Feb 2019
Certificates of CA (Form 5)File: CA Form 5 of 310318.pdf26 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Form 1.pdf18 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf18 Dec 2018
Certificates of CA (Form 3)File: CA certificate Form 3.pdf18 Dec 2018
Building plan approvalFile: IOD Parijat.pdf18 Sep 2018
Building Plan Approval (IOD)File: IOD Parijat.pdf18 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: Parijat CC.pdf18 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate-1.pdf18 Sep 2018
Building plan approvalFile: IOD Parijat.pdf22 Jan 2018
Details of encumbrancesFile: Declaration of Encumbrances 23012018.pdf22 Jan 2018
Building Plan Approval (IOD)File: IOD Parijat.pdf22 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf22 Jan 2018
OtherFile: IOD Parijat.pdf22 Jan 2018
Layout approvalFile: Layout Plan.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf29 Jul 2017
Proforma of Allotment letterFile: Self declaration.pdf29 Jul 2017
Copy of the legal title reportFile: Title Certificate of Parijat Towers Compressed.pdf27 Jul 2017
Certificates of CA (Form 3)File: CA Certificate.pdf27 Jul 2017
Details of encumbrancesFile: Details of Encumbrances.pdf26 Jul 2017
Declaration in FORM BFile: Form B Declaration.pdf26 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1.pdf26 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf26 Jul 2017
Building plan approvalFile: IOD Parijat.pdf24 Jul 2017
Building Plan Approval (IOD)File: IOD Parijat.pdf24 Jul 2017
PAN CardFile: PAN CARD BBIPL.pdf21 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Parijat CC upto 8th Floor ABC.pdf21 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SampadaDAULAT NAGAR BORIVALI EAST18CompletedAug 2010Late, Mar 2011

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 51 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Parijat Towers on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chandivali6,700+ in Mumbai Suburban

2 kmParijat TowersCompleted 70Lapsed / revoked 33Other 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 151 registered projects within 2 km.

Builder: BETTER BUILDERS AND INFRASTRUCTURE PRIVATE LTD

BETTER BUILDERS AND INFRASTRUCTURE PRIVATE LTD has 1 registration on MahaRERA, including Parijat Towers. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Parijat Towers shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Parijat Towers is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Parijat Towers?

The registered promoter entity is BETTER BUILDERS AND INFRASTRUCTURE PRIVATE LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Parijat Towers?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Parijat Towers?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Parijat Towers?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Parijat Towers?

The professionals named in the filing: Architect: ASHISH SOLANKI; Engineer: V V JOSHI; Chartered Accountant: Jigar Zaveri & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Parijat Towers?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Parijat Towers. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Parijat Towers to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.