Home / Browse projects / Thane, Maharashtra / PANVELKAR NISARG PHASE - II
PANVELKAR NISARG PHASE - II
By Panvelkar Realty Private Limited
RG-MH-04164 · RERA P51700021321 · Last updated on MahaRERA portal: 12 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 36 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PANVELKAR NISARG PHASE - II is a Residential / Group Housing project by Panvelkar Realty Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700021321 on 21 Jun 2019. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 36 months from the original filing. 92 of the 107 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.
At a glance
Project
- NamePANVELKAR NISARG PHASE - II
- TypeResidential / Group Housing
- Location
- JOVELI
- Badlapur (M Cl)
- Ambarnath
- Thane
- 421503
- Pincode421503
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700021321
- ReraGenie IDRG-MH-04164
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on21 Jun 2019
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2023)
- Buildings1 building record
- Documents filed149 files
Current status
Figures as on 12 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A - 1 | NA | 9 | 9 | 90 | 17 | 107 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 80%.
A - 1: 71% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 12 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 70% |
| Aggregate area of recreational Open Space | Yes | 70% |
| Open Parking | Yes | 0% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A - 1 | NA | Rs 11.32 cr | Rs 11.10 cr |
| - | NA | Rs 62.90 lakh | Rs 37.74 lakh |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAMARTHYA ENGINEERS |
| Engineer | Atul Kudtarkar |
| Chartered Accountant | ASKA & CO |
| Chartered Accountant | Narhari Rahalkar |
| Chartered Accountant | Kirtane & Pandit LLP |
| Chartered Accountant | Ashvin Thumar & Co |
| Chartered Accountant | Joshi Kale & Associates |
| Chartered Accountant | Vyankatesh Girish Joshi |
| Partner | Role in project |
|---|---|
| Panvelkar Realty Private Limited | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have obtained revised sanction for the said project and correction for the same has been already updated on the site.
Reason as filed by the promoterDear Sir, We have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700021321.The date of completion of project Panvelkar Nisarg Phase 2- Building A1 developed by M/s Panvelkar Realty Private Limited currently is 31st December 2025. The project has been delayed due to general market slowdowns and disruptions in material availability, which have affected the pace of construction. We are in the final stages of completion and require additional time to complete the remaining work. We request the Authority to kindly grant a 6-month extension up to 30th June 2026.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Jun 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Aug 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed149
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 149 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Nisarg A1 Jan26 to Mar26.pdf | 12 May 2026 |
| Withdrawal Update Form 2File: Form 2 Nisarg A1 as on March 2026.pdf | 12 May 2026 |
| Withdrawal Update Form 3File: Form 3 Nisarg A1 as on March 2026.pdf | 12 May 2026 |
| Withdrawal Update Form 1File: Form 1 Nisarg A1 Oct25 to Dec25.pdf | 2 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Nisarg A1 Q3 2025.pdf | 2 Apr 2026 |
| Withdrawal Update Form 3File: Signed Form 3 of Panvelkar Nisarg A1 as on Dec 2025.pdf | 2 Apr 2026 |
| Withdrawal Update Form 1File: 16 Certificates of Architect (Form 1) Sept 2025.pdf | 22 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 - A1 Sep25 signed.pdf | 22 Dec 2025 |
| Withdrawal Update Form 3File: Form 3_Panvelkar Nisarg A1 SEPT 25.pdf | 22 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) March 2023.pdf | 18 Dec 2025 |
| Form 2File: Certificates of Engineer (Form 2) March 2023.pdf | 18 Dec 2025 |
| Form 3File: Form 3_Panvelkar Nisarg A1_March 2023.pdf | 18 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: PRPL Nisarg Phase II A1 sold-Unsold Invt Mar 23.pdf | 18 Dec 2025 |
| Withdrawal Update Form 1File: Certificates of Architect (Form 1) June 2025.pdf | 17 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 - A1 June25.pdf | 17 Dec 2025 |
| Withdrawal Update Form 3File: Form 3_Panvelkar Nisarg A1 JUNE 25.pdf | 17 Dec 2025 |
| Form 5 (FY 2019-2020)File: Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf | 17 Dec 2025 |
| Form 5 (FY 2020-2021)File: Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf | 17 Dec 2025 |
| Form 5 (FY 2021-2022)File: Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf | 17 Dec 2025 |
| Form 5 (FY 2022-2023)File: Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf | 17 Dec 2025 |
| Form 5 (FY 2023-2024)File: Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf | 17 Dec 2025 |
| Form 5 (FY 2024-2025)File: Annual Audit Report of Statutory CA (Form 5) (FY 2024-25).pdf | 17 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) Sept 2022.pdf | 16 Dec 2025 |
| Form 2File: Certificates of Engineer (Form 2) Sept 2022.pdf | 16 Dec 2025 |
| Form 3File: Form 3_Panvelkar Nisarg A1_Sept 2022.pdf | 16 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Sep22.pdf | 16 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) Dec 2022.pdf | 16 Dec 2025 |
| Form 2File: Certificates of Engineer (Form 2) Dec 2022.pdf | 16 Dec 2025 |
| Form 3File: Form 3_Panvelkar Nisarg A1_Dec 2022.pdf | 16 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Dec 2022.pdf | 16 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) June 2023.pdf | 16 Dec 2025 |
| Form 2File: Certificates of Engineer (Form 2) June 2023.pdf | 16 Dec 2025 |
| Form 3File: Form 3_Panvelkar Nisarg A1_June 2023.pdf | 16 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory June 2023.pdf | 16 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) Dec 2023.pdf | 16 Dec 2025 |
| Form 2File: Form 2 A1 -Dec23.pdf | 16 Dec 2025 |
| Form 3File: Form 3_Panvelkar Nisarg A1_Dec 2023.pdf | 16 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Dec 2023.pdf | 16 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) March 2024.pdf | 16 Dec 2025 |
| Form 2File: Certificates of Engineer (Form 2) March 2024.pdf | 16 Dec 2025 |
| Form 3File: Form 3_Panvelkar Nisarg A1_March 2024.pdf | 16 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory March 2024.pdf | 16 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) June 2024.pdf | 16 Dec 2025 |
| Form 2File: Form 2 A1 -Jun24.pdf | 16 Dec 2025 |
| Form 3File: Form 3_Panvelkar Nisarg A1_June 2024.pdf | 16 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory June 2024.pdf | 16 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) Sept 2024.pdf | 16 Dec 2025 |
| Form 2File: Certificates of Engineer (Form 2) Sept 2024.pdf | 16 Dec 2025 |
| Form 3File: Form 3_Panvelkar Nisarg A1_Sept 2024.pdf | 16 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Sept 2024.pdf | 16 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) Dec 2024.pdf | 16 Dec 2025 |
| Form 2File: Form 2 A1 -Dec24.pdf | 16 Dec 2025 |
| Form 3File: Form 3_Panvelkar Nisarg A1_Dec 2024.pdf | 16 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Dec 2024.pdf | 16 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) June 2022.pdf | 11 Dec 2025 |
| Form 2File: Certificates of Engineer (Form 2) June 2022.pdf | 11 Dec 2025 |
| Form 3File: Certificates of CA (Form 3)_June 2022.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory June 2022.pdf | 11 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) Sept 2023.pdf | 11 Dec 2025 |
| Form 2File: Certificates of Engineer (Form 2) Sept 2023.pdf | 11 Dec 2025 |
| Form 3File: Form 3_Panvelkar Nisarg Phase II_Sept 2023.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Sept 2023.pdf | 11 Dec 2025 |
| Form 1File: Certificates of Architect (Form 1) March 2025.pdf | 11 Dec 2025 |
| Form 2File: Certificates of Engineer (Form 2) March 2025.pdf | 11 Dec 2025 |
| Form 3File: Signed Form 3 PRPL Nisarg Phase II A1_ March 2025.pdf | 11 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory March 2025.pdf | 11 Dec 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nisarg Bldg A1 Form 2 Jan To March 25.pdf | 22 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Nisarg Building A1 Form 1 Jan To March 25.pdf | 13 May 2025 |
| Proforma of Agreement for saleFile: Flat Sale Agreement draft.pdf | 28 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Nisarg Building A1 23-24.pdf | 28 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Nisarg A1 Bldg Form 5 23-24.pdf | 28 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Nisarg Building A1 Form 1 Oct To Dec 24.pdf | 22 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Nisarg A1 Bldg Sold Unsold (31 12 24).pdf | 21 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nisarg A1 Form 2 July To Sept 24.pdf | 16 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nisarg A1 Form 2 July To Sept 24.pdf | 16 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Nisarg A1 Sold Unsold July To Sept 24.pdf | 19 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Nisarg Building A1 Form 1 July To Sept 24.pdf | 18 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Nisarg Building A1 Form 1 Apr To June 24.pdf | 22 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Nisarg A1 Bldg Sold Unsold Apr To June 24.pdf | 9 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nisarg Bldg A1 Form 2 (Jan To March 24).pdf | 21 May 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Panvelkar Daffodil - R2P51700033104 | Morivali, Thane | 47 | Feb 2022 | Certificate Signed | Dec 2025 | Sep 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 149 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PANVELKAR NISARG PHASE - II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near JOVELI7,600+ in Thane
Filed coordinates, straight-line distance. 118 registered projects within 2 km.
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Thane project, with the district possession charts
Builder: Panvelkar Realty Private Limited
Panvelkar Realty Private Limited has 2 registrations on MahaRERA, including Panvelkar Nisarg Phase-I and PANVELKAR NISARG PHASE - II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that PANVELKAR NISARG PHASE - II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PANVELKAR NISARG PHASE - II is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PANVELKAR NISARG PHASE - II?
The registered promoter entity is Panvelkar Realty Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PANVELKAR NISARG PHASE - II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PANVELKAR NISARG PHASE - II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PANVELKAR NISARG PHASE - II?
The professionals named in the filing: Architect: SAMARTHYA ENGINEERS; Engineer: Atul Kudtarkar; Chartered Accountant: ASKA & CO; Chartered Accountant: Narhari Rahalkar; Chartered Accountant: Kirtane & Pandit LLP; Chartered Accountant: Ashvin Thumar & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PANVELKAR NISARG PHASE - II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.