Home / Browse projects / Thane, Maharashtra / Panvelkar Estate - Greenford
Panvelkar Estate - Greenford
By Panvelkar Infrastructures Private Limited
RG-MH-40976 · RERA P51700017332 · Last updated on MahaRERA portal: 22 Jan 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 3 complaints at MahaRERA
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Panvelkar Estate - Greenford is a Residential / Group Housing project by Panvelkar Infrastructures Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700017332 on 7 Aug 2018. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 24 months from the original filing. 3 complaints are on record with the regulator.
At a glance
Project
- NamePanvelkar Estate - Greenford
- TypeResidential / Group Housing
- Location
- MANKIVALI
- BADLAPUR
- Badlapur (M Cl)
- Ambarnath
- Thane
- 421503
- Pincode421503
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700017332
- ReraGenie IDRG-MH-40976
Builder
- NamePanvelkar Infrastructures Private Limited
- Entity typeCompany
- CINU45208MH2010PTC199539
- GSTIN27AAFCP3290F1ZE
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- ChairpersonVijay Ramchand Panvelkar
- Other registrations6 more →
- Completed3 of 7
- No longer live4 lapsed, de-registered or revoked
- Declared earlier projects4 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Aug 2018
- Promised completion31 Dec 2024
- Revised completionRevised to 31 Dec 2024 (originally 30 Dec 2022)
- Buildings5 building records
- Documents filed101 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 7 | 0 | 0 | 0 | 0 |
| B Wing | NA | 7 | 0 | 0 | 0 | 0 |
| C Wing | NA | 10 | 0 | 0 | 0 | 0 |
| D Wing | NA | 10 | 0 | 0 | 0 | 0 |
| E Wing | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 22 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
40 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 0%.
A Wing91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B Wing91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
C Wing91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D Wing91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 22 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 100% |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Raj Associates |
| Engineer | Atul Kutdarkar |
| Partner | Role in project |
|---|---|
| Panvelkar Infrastructures Private Limited | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe plan for the said project has been revised to avail the benefit of the new UDCPR. The approval was received on 09/09/2021. In the said revision, we have received additional FSI following with additional flats and floors. We have taken appropriate consent from the existing customers as per new MahaRERA guidelines(same has been attached herewith). Please grant us the extension for the same.
Reason as filed by the promoterWork is to be completed till December but to obtain OC it will take more 3-4 month as the process of obtaining OC is Online and it has very complicated and time consuming process.
Complaints filed with MahaRERA3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000196690 | Kunal Sagwekar | Rahul Vijay Panvelkar | 11/04/2021 |
| CC006000000570816 | Mandar Sham Ghumkar | PANVELKAR INFRATRUCTURES PVT. LTD. | 08/07/2024 |
| CC006000000591248 | Arun arjun pawar | Panvelkar Infrastructures Private Limited | 20/07/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Jan 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jul 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 1 Mar 2024
Documents filed101
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| PAN CardFile: PIPL PAN.pdf | 22 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (RVP).pdf | 22 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A (VRP).pdf | 22 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Greenford Wing A To D Form 4.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greenford A To D Wing Form 1 Jan To March 24_compressed.pdf | 1 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greenford A To D Wing Form 1 Apr To June 24_compressed.pdf | 1 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greenford A To D Wing Form 1July To Sept 24_compressed.pdf | 1 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greenford A To D Wing Form 1 Jan To March 24_compressed.pdf | 28 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greenford A To D Wing Form 1 Apr To June 24_compressed.pdf | 28 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greenford A To D Wing Form 1July To Sept 24_compressed.pdf | 28 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Greenford A To E Wing 23-24.pdf | 28 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Greenford A To D Form 5 23-24.pdf | 28 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Greenford Wing A To D Form 4.pdf | 5 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Greenford Wing A To D Form 4.pdf | 23 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Greenford Wing A To D Form 4.pdf | 22 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Greenford Wing A To D Sold Unsold Jan To March 24.pdf | 15 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Greenford A To D CC Copy.pdf | 1 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greenford Wing A To D F1 Dec_compressed.pdf | 17 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Greenford A To D Sold Unsold_compressed.pdf | 12 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 PIPL Greenford A-D Wing Sept 2023.pdf | 28 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greenford Wing A To D Form 2 (July To Sept 23).pdf | 6 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Greenford A To D July To Sept 23_compressed.pdf | 17 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greenford A To D Wing Form 1_July To Sept 23_compressed.pdf | 11 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greenford A To D Form 2 (Apr To June) (2).pdf | 23 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greenford A To D Wing Form 1.pdf | 4 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Greenford A To E Form 2A (M19).pdf | 29 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Greenford A To E Form 2A (M20).pdf | 29 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Greenford A To E Form 2A (M21).pdf | 29 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Greenford A To D Form 2A (M23).pdf | 29 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Greenford A To D Wing_compressed.pdf | 18 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greenford Wing A To D_Jan To March 23_compressed.pdf | 9 May 2023 |
| Certificates of CA (Form 3)File: Form 3 Greenford Wing A-D_March 23.pdf | 9 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greenford Wing A To D Form 1_compressed.pdf | 3 May 2023 |
| Disclosure of sold/ booked inventoryFile: panvelkar greenford wing A To D_compressed.pdf | 14 Apr 2023 |
| Proforma of Agreement for saleFile: Greenford A To D Agreement for sale.pdf | 12 Apr 2023 |
| Deviation Report with respect to Allotment letterFile: No Deviation letter ( Allotment letter).pdf | 12 Apr 2023 |
| Deviation Report with respect to model copy of AgreementFile: No Deviation letter (Agreement for sale).pdf | 12 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: PIPL Panvelkar Estate Greenford Wing A to D FY 18-19.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: PIPL Panvelkar Estate Greenford Wing A to D FY 19-20.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: PIPL Panvelkar Estate Greenford Wing A to D FY 20-21.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: PIPL Panvelkar Estate Greenford Wing A to D FY 21-22.pdf | 10 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: Greenford A To D Sold Unsold Dec 22.pdf | 20 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greenford A To D Wing_Oct To Dec 22_compressed.pdf | 12 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greenford Wing A To D Form 2 (Dec Qtr)_compressed.pdf | 12 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Greenford A To D Sold Unsold.pdf | 26 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Greenford A To D Wing_compressed.pdf | 15 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Greenford A To D Wing_compressed.pdf | 15 Oct 2022 |
| Layout approvalFile: Sheet 1_compressed.pdf | 7 Jan 2022 |
| Layout approvalFile: Sheet 2_compressed.pdf | 7 Jan 2022 |
| Layout approvalFile: Sheet 3_compressed.pdf | 7 Jan 2022 |
| Layout approvalFile: Sheet 4_compressed.pdf | 7 Jan 2022 |
| Layout approvalFile: Sheet 5_compressed.pdf | 7 Jan 2022 |
| Copy of the legal title reportFile: Title Greenford.pdf | 7 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Sheet 1_compressed.pdf | 7 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Sheet 2_compressed.pdf | 7 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Sheet 3_compressed.pdf | 7 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Sheet 4_compressed.pdf | 7 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Sheet 5_compressed.pdf | 7 Jan 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised CC ( Greenford).pdf | 7 Jan 2022 |
| Declaration about Commencement CertificateFile: Declaration about CC ( Greenford revised).pdf | 7 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf | 7 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer certificate.pdf | 7 Jan 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200225812276_For_Asset_Based_Search_13_12_2021_19_21_08_509.pdf | 7 Jan 2022 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate_compressed.pdf | 7 Jan 2022 |
| OtherFile: Consent for Correction_compressed.pdf | 7 Jan 2022 |
| OtherFile: Consent for Extension_compressed.pdf | 7 Jan 2022 |
| OtherFile: Letter for correction.pdf | 7 Jan 2022 |
| OtherFile: Letter for extension.pdf | 7 Jan 2022 |
| Details of encumbrancesFile: Encumbrance.pdf | 2 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 3 May 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 25 Jan 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 23 Oct 2019 |
| Building plan approvalFile: Blueprint 1.pdf | 27 Jul 2018 |
| Building plan approvalFile: Blueprint 2.pdf | 27 Jul 2018 |
| Building plan approvalFile: Blueprint 3.pdf | 27 Jul 2018 |
| Building plan approvalFile: Blueprint 4.pdf | 27 Jul 2018 |
| Building plan approvalFile: Blueprint 5.pdf | 27 Jul 2018 |
| Layout approvalFile: Blueprint 1.pdf | 27 Jul 2018 |
| Layout approvalFile: Blueprint 2.pdf | 27 Jul 2018 |
| Layout approvalFile: Blueprint 3.pdf | 27 Jul 2018 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Panvelkar Estate-Stanford-Phase I | Mankivali Badlapur East | 285 | Completed | Dec 2018 | Late, Dec 2019 |
| Panvelkar Aquamarine | Gut No 3 Morivali Ambernath East | 262 | Completed | Oct 2016 | May 2016 |
| Panvelkar Vellozia | Survey No 79 Hissa No 2 Near Asaram Bapu Ashram Shirgaon Badlapur East | 159 | Completed | Dec 2014 | Dec 2014 |
| Panvelkar Royale Square | Survey No 64 Hissa No 12 Near Bharat College Hendre Pada Badlapur West | 122 | Completed | Dec 2013 | May 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 101 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Panvelkar Estate - Greenford on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BADLAPUR7,600+ in Thane
Filed coordinates, straight-line distance. 394 registered projects within 2 km.
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Thane project, with the district possession charts
Builder: Panvelkar Infrastructures Private Limited
Panvelkar Infrastructures Private Limited has 7 registrations on MahaRERA, including Panvelkar Estate - Stanford - Phase 1 and Panvelkar Swarajya Phase-I. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Panvelkar Estate - Greenford shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Panvelkar Estate - Greenford is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Panvelkar Estate - Greenford?
The registered promoter entity is Panvelkar Infrastructures Private Limited, a company as per the filing. Its CIN U45208MH2010PTC199539 and GSTIN 27AAFCP3290F1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Panvelkar Estate - Greenford?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Panvelkar Estate - Greenford?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Panvelkar Estate - Greenford?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Panvelkar Estate - Greenford?
The professionals named in the filing: Architect: Raj Associates; Engineer: Atul Kutdarkar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Panvelkar Estate - Greenford?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback