PANVELKAR BHOOMI BUILDING NO 5,6,7,8,9
RG-MH-74314 · RERA P51700050061 · Last updated on MahaRERA portal: 1 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PANVELKAR BHOOMI BUILDING NO 5,6,7,8,9 is a Residential / Group Housing project by PANVELKAR BHOOMI in Thane, Maharashtra, registered with MahaRERA as P51700050061 on 13 Mar 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 27 of the 160 units on this registration are recorded sold or booked, and 11 of 55 construction stages are filed complete.
At a glance
Project
- NamePANVELKAR BHOOMI BUILDING NO 5,6,7,8,9
- TypeResidential / Group Housing
- Location
- MAUJE KHARWAI
- TALUKA AMBERNATH
- Badlapur (M Cl)
- Ambarnath
- Thane
- 421503
- Pincode421503
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700050061
- ReraGenie IDRG-MH-74314
Builder
- NamePANVELKAR BHOOMI
- Entity typePartnership
- PartnersJAYANTILAL TULSHI PARMAR, DHIREN JAYANTILAL PARMAR, AMIT VINAYAK PANVELKAR, ASLAM ZAHIR DON, TAHA ASLAM DON, VISHWANATH RAMCHANDRA PANVELKAR, HEMLATA BACHU HINGU, MAHENDRA JETHALAL DANANI, ASHA MAHENDRA DANANI, JINESH MAHENDRA HINGU, VAISHALI AMIT PANVELKAR, RAHUL VIJAY PANVELKAR and 1 more
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on13 Mar 2023
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
- Buildings5 building records
- Documents filed126 files
Current status
Figures as on 1 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 5 BLOSSOM | NA | 7 | 7 | 32 | 0 | 32 |
| BUILDING NO 6 CLOVER | NA | 7 | 7 | 32 | 0 | 32 |
| BUILDING NO 7 DAFFODIL | NA | 7 | 7 | 32 | 0 | 32 |
| BUILDING NO 8 FLORA | NA | 7 | 7 | 32 | 0 | 32 |
| BUILDING NO 9 LOTUS | NA | 7 | 7 | 32 | 0 | 32 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 1 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Slabs of Super Structure, at 12%.
BUILDING NO 5 BLOSSOM19%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 12% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 6 CLOVER0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 7 DAFFODIL0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 8 FLORA0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 9 LOTUS82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 1 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING NO 9 LOTUS | NA | Rs 4.24 cr | Rs 4.20 cr |
| BUILDING NO 5 BLOSSOM | NA | Rs 3.59 cr | Rs 1.29 cr |
| BUILDING NO 6 CLOVER | NA | Rs 3.59 cr | - |
| BUILDING NO 7 DAFFODIL | NA | Rs 3.59 cr | - |
| BUILDING NO 8 FLORA | NA | Rs 3.59 cr | - |
| - | NA | Rs 1.62 cr | Rs 36.13 lakh |
Certifying professionals and partners10
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pramod Patil |
| Engineer | Atul Kudtarkar & Associates |
| Engineer | Atul Kudtarkar and Associates Pvt Ltd |
| Engineer | Kunal Punyarthi |
| Chartered Accountant | CA Ashvin Thumar & Co |
| Chartered Accountant | A S K A & CO. |
| Chartered Accountant | Monisha Kuperkar |
| Chartered Accountant | Kirtane & Pandit LLP |
| Chartered Accountant | JOSHI CHHADVA & CO LLP |
| Chartered Accountant | JOSHI KALE & ASSOCIATES |
| Partner | Role in project |
|---|---|
| PANVELKAR BHOOMI | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have registered under Real Estate Regulatory Act, 2016 bearing registration number P51700050061.The date of completion of project Panvelkar Bhoomi (Building No. 5,6,7,8,9)" developed by M/s Panvelkar Bhooml currently is 31st December, 2025. We would like to bring to your notice that the project comprises of five buildings namely Building No. 5,6, 7,8 & 9. Out of these buildings, only two buildings work has been started due to sluggish market demand and bookings were also taken in those two buildings only. For other buildings i.e. Building No. 6, 7, and 8, no work has been started & no booki
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Dec 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Dec 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Dec 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed126
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Signed Form 1 as on March 2026__Panvelkar Bhoomi.pdf | 1 Jun 2026 |
| Withdrawal Update Form 2File: Signed Form 2 as on March 2026__Panvelkar Bhoomi.pdf | 1 Jun 2026 |
| Withdrawal Update Form 3File: Signed Form 3 of Panvelkar Bhoomi as on March 2026 .pdf | 1 Jun 2026 |
| Withdrawal Update Form 1File: Signed Form 1 as on December 2025.pdf | 23 Mar 2026 |
| Withdrawal Update Form 2File: Signed Form 2 as on December 2025.pdf | 23 Mar 2026 |
| Withdrawal Update Form 3File: Signed Form 3__Panvelkar Bhoomi as on December 25.pdf | 23 Mar 2026 |
| Form 5 (FY 2022-2023)File: Form 5 FY 22-23 Panvelkar Bhoomi.pdf | 27 Dec 2025 |
| Form 2A (FY 2022-2023)File: Form 2A_2022-23.pdf | 26 Dec 2025 |
| Form 2A (FY 2023-2024)File: Form 2A_2023-24.pdf | 26 Dec 2025 |
| Form 2A (FY 2024-2025)File: Form 2A_2024-25.pdf | 26 Dec 2025 |
| Form 5 (FY 2023-2024)File: CA certificate for Rera (Form 5).pdf | 1 Dec 2025 |
| Form 5 (FY 2024-2025)File: Signed Copy Form 5 Panvelkar Bhoomi FY 24-25.pdf | 1 Dec 2025 |
| Form 1File: Bhoomi Form1 march 23 signed.pdf | 25 Nov 2025 |
| Form 2File: Bhoomi Form 2 March 2023 Signed.pdf | 25 Nov 2025 |
| Form 3File: Form 3 march 2023 signed.pdf | 25 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold March 23.pdf | 25 Nov 2025 |
| Withdrawal Update Form 1File: Bhoomi Form 1 Sept’25 signed.pdf | 25 Nov 2025 |
| Withdrawal Update Form 2File: Bhoomi Form 2 July - Sept 2025 signed.pdf | 25 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 Bhoomi Sept 2025 signed_compressed (1).pdf | 25 Nov 2025 |
| Form 1File: Panvelkar Bhoomi Form 1 June 2023_compressed.pdf | 19 Aug 2025 |
| Form 2File: Panvelkar Bhoomi Form 2 June 2023_compressed.pdf | 19 Aug 2025 |
| Form 3File: Panvelkar Bhoomi Form 3 June 2023_compressed.pdf | 19 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory_compressed.pdf | 19 Aug 2025 |
| Form 1File: Panvelkar Bhoomi Form 1 Sept 2023_compressed.pdf | 19 Aug 2025 |
| Form 2File: Panvelkar Bhoomi Form 2 Sept 23 Final.pdf | 19 Aug 2025 |
| Form 3File: Panvelkar Bhoomi Form 3 Sept 23.pdf | 19 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory_compressed.pdf | 19 Aug 2025 |
| Form 1File: form 1 Dec 2023.pdf | 19 Aug 2025 |
| Form 2File: Form 2 Dec 2023.pdf | 19 Aug 2025 |
| Form 3File: form 3 dec 2023.pdf | 19 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventory.pdf | 19 Aug 2025 |
| Form 1File: Form 1 March 24.pdf | 19 Aug 2025 |
| Form 2File: Form 2 March 24.pdf | 19 Aug 2025 |
| Form 3File: Form 3 March 24.pdf | 19 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventory.pdf | 19 Aug 2025 |
| Form 1File: form 1 Q1 2025.pdf | 19 Aug 2025 |
| Form 2File: Form 2 Q1 2025.pdf | 19 Aug 2025 |
| Form 3File: Form 3 Q1 2025.pdf | 19 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Q1 2024-25 Sales.pdf | 19 Aug 2025 |
| Form 1File: Form 1 Q2 2025.pdf | 19 Aug 2025 |
| Form 2File: Form 2 Q2 2025.pdf | 19 Aug 2025 |
| Form 3File: Form 3 Q2 2025.pdf | 19 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Q2 2024-25 Sales .pdf | 19 Aug 2025 |
| Form 1File: Form 1 Q3 2025.pdf | 19 Aug 2025 |
| Form 2File: Form 2 Q3 2025.pdf | 19 Aug 2025 |
| Form 3File: Form 3 Q3 2025.pdf | 19 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf | 19 Aug 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 18 Aug 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 18 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 of Panvelkar Bhoomi June 2025.pdf | 18 Aug 2025 |
| Form 1File: Form 1 signed Q4__Compressed.pdf | 8 Jul 2025 |
| Form 2File: Signed Form 2 Q4__Compressed.pdf | 8 Jul 2025 |
| Form 3File: Signed Form 3 Jan 25-Mar 25.pdf | 8 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory sheet revised .pdf | 8 Jul 2025 |
| Self-declaration of Quarterly ProgressFile: SELF declaration RERA.pdf | 8 Jul 2025 |
| Withdrawal Update Form 1File: Form 1 signed Q4__Compressed.pdf | 8 Jul 2025 |
| Withdrawal Update Form 2File: Signed Form 2 Q4__Compressed.pdf | 8 Jul 2025 |
| Withdrawal Update Form 3File: Signed Form 3 Jan 25-Mar 25.pdf | 8 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Q1 2025.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2 2025.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 2025.pdf | 22 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 2 Q3 2025.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1 2025.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 2025.pdf | 22 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 2025.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q1 2025.pdf | 22 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2 2025.pdf | 22 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Q2 2024-25 Sales .pdf | 22 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Q3 2024-25 Sales.pdf | 22 Feb 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: Q1 2024-25 Sales.pdf | 22 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA certificate for Rera (Form 5).pdf | 2 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 24.pdf | 10 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 24.pdf | 10 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 24.pdf | 10 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Dec 2023.pdf | 28 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2023.pdf | 28 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory.pdf | 28 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 dec 2023.pdf | 28 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Panvelkar Bhoomi Form 2 Sept 23 Final.pdf | 16 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Panvelkar Bhoomi Sept 2023.pdf | 16 Nov 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 126 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PANVELKAR BHOOMI BUILDING NO 5,6,7,8,9 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near TALUKA AMBERNATH7,600+ in Thane
Filed coordinates, straight-line distance. 175 registered projects within 2 km.
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Thane project, with the district possession charts
Builder: PANVELKAR BHOOMI
PANVELKAR BHOOMI has 1 registration on MahaRERA, including PANVELKAR BHOOMI BUILDING NO 5,6,7,8,9. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if PANVELKAR BHOOMI BUILDING NO 5,6,7,8,9 is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PANVELKAR BHOOMI BUILDING NO 5,6,7,8,9?
The registered promoter entity is PANVELKAR BHOOMI, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PANVELKAR BHOOMI BUILDING NO 5,6,7,8,9?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PANVELKAR BHOOMI BUILDING NO 5,6,7,8,9?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PANVELKAR BHOOMI BUILDING NO 5,6,7,8,9?
The professionals named in the filing: Architect: Pramod Patil; Engineer: Atul Kudtarkar & Associates; Engineer: Atul Kudtarkar and Associates Pvt Ltd; Engineer: Kunal Punyarthi; Chartered Accountant: CA Ashvin Thumar & Co; Chartered Accountant: A S K A & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PANVELKAR BHOOMI BUILDING NO 5,6,7,8,9?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback