Home / Browse projects / Mumbai Suburban, Maharashtra / Pant Nagar Ganadhiraj CHSL

Registered No litigation declared Others project

Pant Nagar Ganadhiraj CHSL

By Mishal Construction Private Limited

RG-MH-24341 · RERA P51900007103 · Last updated on MahaRERA portal: 28 May 2026

Source: official MahaRERA filing

Red flags

  • 7 complaints at MahaRERA
  • Completion date moved by 72 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 72 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 70%
46 of 87Units unsoldnot recorded sold or booked
7Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

Pant Nagar Ganadhiraj CHSL is a Others project by Mishal Construction Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51900007103 on 17 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 72 months from the original filing. 41 of the 87 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 7 complaints are on record with the regulator.

At a glance

Project

  • NamePant Nagar Ganadhiraj CHSL
  • TypeOthers
  • Location
    • PantNagar
    • Kurla
    • Mumbai Suburban
    • 400075
  • Pincode400075
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900007103
  • ReraGenie IDRG-MH-24341

Builder

  • NameMishal Construction Private Limited
  • Entity typeCompany
  • ChairpersonNaveenkumar Mishrimal Jain
  • Other registrations10 more →
  • No longer live9 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseDec 2021Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2021)
  • Buildings1 building record
  • Documents filed75 files

Current status

47%41 of 87 units booked
31.0%Work done, per cost certificate

Figures as on 28 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Pant Nagar Ganadhiraj CHSLNA1716771087

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.

Pant Nagar Ganadhiraj CHSL: 52% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises33%
Sanitary Fittings within the flats / premises7%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks64%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed31

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots31
Closed/Covered31

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area842 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Sep 2024

Approvals and building plan

Sanctioning authorityMhada
Permissible FSI5098.17
Proposed, not sanctioned2,141 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRatnadeep, Bhaveshwar Lane, MG Road, Mumbai-400077
Estimated costRs 10.10 cr
Cost incurredRs 3.13 cr
Work done30.96%
BuildingWingEstimatedIncurred
Pant Nagar Ganadhiraj CHSLNARs 9.55 crRs 2.98 cr
-NARs 55.00 lakhRs 15.00 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV.S.Vaidya & Associates
ArchitectAssociated Structural Engineers LLP
ArchitectArcvishan Infratech Ltd
EngineerAssociated Consultants
EngineerV.S.Vaidya & Associates
Chartered AccountantR B Ashar & Co.
PartnerRole in project
Mishal Construction Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011770Dec 2021 → Dec 2023

Reason as filed by the promoterCovid

EA25022619997Dec 2021 → Dec 2027

Reason as filed by the promoterDue to change in plan

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000292334Bharat Ramji GalaMishal Construction Pvt td24/08/2022
CC006000000292335Bharat Ramji GalaMishal Construction Pvt Ltd24/08/2022
CC006000000292336Chaganlal Kalyanji HariaMishal Construction Pvt Ltd24/08/2022
CC006000000292473NILESH RATANSHI GADAMishal Construction Pvt Ltd27/08/2022
CC006000000397714Suryakant Gopal TekadeMishal Construction Pvt Ltd31/10/2023
CC12605376NARAYAN LALJI KATARMALMishal Construction Private Limited21/08/2026
CC12605377Kalpesh MehtaMishal Construction Private Limited21/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: GN - FORM 1 (December 2025).pdf28 May 2026
Withdrawal Update Form 1File: GN - FORM 1 (March 2026).pdf28 May 2026
Withdrawal Update Form 2File: GN - FORM 2 - December 2025.pdf28 May 2026
Withdrawal Update Form 2File: GN - FORM 2 - March 2026.pdf28 May 2026
Withdrawal Update Form 3File: GN - Form 3- Dec 2025.pdf28 May 2026
Withdrawal Update Form 3File: GN - Form 3 - March 2026.pdf28 May 2026
Form 5 (FY 2025-2026)File: Ganadhiraj - Form 5 - 2026.pdf28 May 2026
Form 1File: GN - Form 1 (March 2024).pdf24 Apr 2026
Form 2File: GN - Form 2 - March 2024.pdf24 Apr 2026
Form 3File: GN - Form 3- March 2024.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory - 18-03-2026.pdf24 Apr 2026
Form 1File: GN - Form 1 (June 2024).pdf24 Apr 2026
Form 2File: GN - Form 2 - June 2024.pdf24 Apr 2026
Form 3File: GN - Form 3- June 2024.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory - 18-03-2026.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory - 18-03-2026.pdf24 Apr 2026
Form 1File: GN - Form 1 (September 2024).pdf24 Apr 2026
Form 2File: GN - Form 2 - September 2024.pdf24 Apr 2026
Form 3File: GN - Form 3- Sept 2024.pdf24 Apr 2026
Form 3File: GN - Form 3- Dec 2024.pdf24 Apr 2026
Form 2File: GN - Form 2 - December 2024.pdf24 Apr 2026
Form 1File: GN - Form 1 (December 2024).pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory - 18-03-2026.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold inventory - 18-03-2026.pdf24 Apr 2026
Form 1File: GN - Form 1 (March 2025).pdf24 Apr 2026
Form 2File: GN - Form 2 - March 2025.pdf24 Apr 2026
Form 3File: GN - Form 3- March 2025.pdf24 Apr 2026
Withdrawal Update Form 1File: GN - Form 1 (June 2025).pdf24 Apr 2026
Withdrawal Update Form 1File: GN - Form 1 (June 2025).pdf24 Apr 2026
Withdrawal Update Form 1File: GN - Form 1 (September 2025).pdf24 Apr 2026
Withdrawal Update Form 2File: GN - Form 2 - June 2025.pdf24 Apr 2026
Withdrawal Update Form 2File: GN - Form 2 - June 2025.pdf24 Apr 2026
Withdrawal Update Form 2File: GN - Form 2 - September 2025.pdf24 Apr 2026
Withdrawal Update Form 3File: GN - Form 3- June 2025.pdf24 Apr 2026
Withdrawal Update Form 3File: GN - Form 3- June 2025.pdf24 Apr 2026
Withdrawal Update Form 3File: GN - Form 3- Sept 2025.pdf24 Apr 2026
Form 1File: GN - Form 1 (Upto March 2023).pdf21 Jan 2026
Form 2File: GN-Form-2-March 2023.pdf21 Jan 2026
Form 3File: GN - Form 3- March 2023.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: GN-Disclosure of Sold booked inventory.pdf21 Jan 2026
Form 1File: GN - Form 1 (June 2023).pdf21 Jan 2026
Form 2File: GN-Form-2-June 2023.pdf21 Jan 2026
Form 3File: GN - Form 3- June 2023.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: GN-Disclosure of Sold booked inventory.pdf21 Jan 2026
Form 1File: GN - Form 1 (September 2023).pdf21 Jan 2026
Form 2File: GN-Form-2-Sept 2023.pdf21 Jan 2026
Form 3File: GN - Form 3- Sept 2023.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: GN-Disclosure of Sold booked inventory.pdf21 Jan 2026
Form 1File: GN - Form 1 (December 2023).pdf21 Jan 2026
Form 2File: GN-Form-2- Dec 2023.pdf21 Jan 2026
Form 3File: GN - Form 3- Dec 2023.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: GN-Disclosure of Sold booked inventory.pdf21 Jan 2026
Declaration about Commencement CertificateFile: GN Format D.pdf21 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: GN EC.pdf21 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: GN EC.pdf21 Apr 2022
Disclosure of sold/ booked inventoryFile: GN Sold Unsold.pdf21 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_Ganadhiraj.pdf7 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Ganadhiraj.pdf7 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: GN 19-20.pdf7 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: GN 20-21.pdf7 Apr 2022
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 GANADHIRAJ CHS.pdf11 Sep 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_Ganadhiraj.pdf29 Jul 2017
Certificates of CA (Form 3)File: Form 3_Ganadhiraj.pdf29 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Draft Ganadhiraj.pdf29 Jul 2017
Proforma of Allotment letterFile: AGREEMENTFORSALE - GANADHIRAJ CHS.pdf29 Jul 2017
Details of encumbrancesFile: Ganadhiraj_Encumbrance certificate.pdf28 Jul 2017
Declaration in FORM BFile: Form B Ganadhiraj .pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ganadhiraj_Architect Certificate.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ganadhiraj_Engg Certificate.pdf28 Jul 2017
Building plan approvalFile: IOD to be uploaded.pdf27 Jul 2017
Layout approvalFile: Layout Plan.pdf27 Jul 2017
Copy of the legal title reportFile: Title Certificate Ganadhiraj to be uploaded.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf27 Jul 2017
Building Plan Approval (IOD)File: IOD to be uploaded.pdf27 Jul 2017
PAN CardFile: Mishal Construction Private Limited PAN card.pdf26 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Mahesh Villa Ghatkopar Cooperative Housing Society LtdPlot No 12 Vallabhaug Lane Garodia Nagar Ghatkopar East Mumbai - 40007716CompletedDec 2015Late, Jun 2017
Mohan Sadan Co-Operative Housing Society LtdPlot No 2A of TPS III CTS No 5991 MG Road Ghatkopar East Mumbai 40007726CompletedJun 2015Late, Sep 2015

How this compares with Mumbai Suburban

47%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 72 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Pant Nagar Ganadhiraj CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmPant Nagar Ganadhiraj CHCompleted 118Lapsed / revoked 64Other 104Dot size: filed unitsN

Filed coordinates, straight-line distance. 286 registered projects within 2 km.

Builder: Mishal Construction Private Limited

Mishal Construction Private Limited has 11 registrations on MahaRERA, including Gagan Vihar Co-operative Housing Society Limited and Gulistan Manzil Co-operative Housing Society Limited. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Pant Nagar Ganadhiraj CHSL is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Pant Nagar Ganadhiraj CHSL?

The registered promoter entity is Mishal Construction Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Pant Nagar Ganadhiraj CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Pant Nagar Ganadhiraj CHSL?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Pant Nagar Ganadhiraj CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Pant Nagar Ganadhiraj CHSL?

The professionals named in the filing: Architect: V.S.Vaidya & Associates; Architect: Associated Structural Engineers LLP; Architect: Arcvishan Infratech Ltd; Engineer: Associated Consultants; Engineer: V.S.Vaidya & Associates; Chartered Accountant: R B Ashar & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pant Nagar Ganadhiraj CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pant Nagar Ganadhiraj CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pant Nagar Ganadhiraj CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.