Home / Browse projects / Thane, Maharashtra / PANCHRATNA SAPPHIRE

Registered No litigation declared Others project

PANCHRATNA SAPPHIRE

By PANCHARATNA DEVELOPERS

RG-MH-65158 · RERA P51700050689 · Last updated on MahaRERA portal: 6 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 12 months from the original
5 of 11Construction stages donefurthest along: External plumbing and external plaster, 90%
42 of 138Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

PANCHRATNA SAPPHIRE is a Others project by PANCHARATNA DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700050689 on 28 Apr 2023. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 96 of the 138 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NamePANCHRATNA SAPPHIRE
  • TypeOthers
  • Location
    • KALYAN
    • Thane
    • 421306
  • Pincode421306
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700050689
  • ReraGenie IDRG-MH-65158

Builder

  • NamePANCHARATNA DEVELOPERS
  • Entity typePartnership
  • PartnersGULAMNABI GARIBSHAH SAYYED, DAMA PARESH GOPALJI, VASANT DAYARAM KHANIA, KISHORE GIRDHARILAL KHUBCHANDANI, PANKAJKUMAR MOTICHAND GUPTA, MANISH UDHAV RUPCHANDANI
  • Other registrations5 more →
  • Completed4 of 6
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredApr 2023First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Apr 2023
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed93 files

Current status

70%96 of 138 units booked
72.7%Work done, per cost certificate

Figures as on 6 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA18181299138

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.

WING A: 64% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)30%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed167

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots167
Closed/Covered125
Open Space42

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,400 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Feb 2026

Approvals and building plan

Sanctioning authorityKALYAN DOMBIVALI MUNICIPAL CORPORATION
Permissible FSI9544.0
Proposed, not sanctioned9,544 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMumbai
Estimated costRs 32.80 cr
Cost incurredRs 23.83 cr
Work done72.66%
BuildingWingEstimatedIncurred
WING ANARs 30.17 crRs 23.83 cr
-NARs 2.64 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSPACE ENVIRO ARCHITECTS
ArchitectANKUR ARVINDSHETYE
EngineerKHASNIS & ASSOCIATES
Chartered AccountantR A HOTWANI & COMPANY
Chartered AccountantD S KARIRA & ASSOCIATES
PartnerRole in project
PANCHARATNA DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA24022619996Mar 2026 → Mar 2027

Reason as filed by the promoterThe Promoter respectfully submits that the project could not be completed within the originally declared timeline due to genuine administrative, financial and execution-related challenges encountered during the course of development. The delay is neither wilful nor intentional. During implementation, the project experienced delays in obtaining certain revised approvals, technical permissions and compliance clearances from competent authorities. The time involved in scrutiny, documentation updates and inter-departmental coordination extended beyond the anticipated schedule, which impacted the p

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCHITECTS CERTIFICATE.pdf6 May 2026
Withdrawal Update Form 2File: Engineers Certificate_31-03-2026.pdf6 May 2026
Withdrawal Update Form 3File: Panchratna_Developers_Form3.pdf6 May 2026
Form 2A (FY 2023-2024)File: Form_2A_2023-24.pdf2 Apr 2026
Form 2A (FY 2024-2025)File: Form_2A_2024-25.pdf2 Apr 2026
Form 2A (FY 2025-2026)File: Form_2A_2025-26.pdf2 Apr 2026
Form 5 (FY 2023-2024)File: form 5 Panchratna_Developers_FY23-24.pdf2 Apr 2026
Form 5 (FY 2024-2025)File: form 5Panchratna_Developers_FY24-25.pdf2 Apr 2026
Withdrawal Update Form 1File: Architect_Certificate_Q3.pdf24 Feb 2026
Withdrawal Update Form 2File: Engineer_Certificate_Q3.pdf24 Feb 2026
Withdrawal Update Form 3File: Panchranta_Developers_Form3_Q3.pdf24 Feb 2026
Building plan approvalFile: revised CC.pdf20 Feb 2026
Building plan approvalFile: Revised Plan.pdf20 Feb 2026
Withdrawal Update Form 1File: Panchratna_Certificate_Q1.pdf20 Feb 2026
Withdrawal Update Form 1File: Architect_Certificate.pdf20 Feb 2026
Withdrawal Update Form 2File: 2024-25Q1_Form2Engineers Certificate.pdf20 Feb 2026
Withdrawal Update Form 2File: Engineer_Certificate.pdf20 Feb 2026
Withdrawal Update Form 3File: Form3_RERA_Certificate.pdf20 Feb 2026
Withdrawal Update Form 3File: WingA.pdf20 Feb 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2 en certificate.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_Architechs Certificate.pdf28 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Certificate.pdf28 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2_Engineers certificate.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2024-25Q1_Form1Architectures Certificate.pdf20 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2024-25Q1_Form2Engineers Certificate.pdf20 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_RERA_Certificate.pdf20 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2024-25Q1_Form1Architectures Certificate.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2024-25Q1_Form2Engineers Certificate.pdf22 Jul 2024
CERSAI detailsFile: 1 CERSAI Report.pdf24 Apr 2024
Details of encumbrances concerned to FinanceFile: Declaration of encumbarnces-legal Q4.pdf20 Apr 2024
Details of encumbrances concerned to FinanceFile: Declaration of Encumberance -Finance Q4.pdf20 Apr 2024
Details of encumbrances concerned to LegalFile: Declaration of encumbarnces-legal Q4.pdf20 Apr 2024
Details of encumbrances concerned to LegalFile: Declaration of Encumberance -Finance Q4.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect's Certificate for prcentage of Completion of Work-Form 1.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer's Certificate on cost incurred on project- Form 2.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Engineer's Certificate on Quality Assurance- Form 2A.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on Project Cost and Fund Withdrawal Form3.pdf20 Apr 2024
Details of encumbrances concerned to FinanceFile: 1b Details of encumbrances on legal (Q1).pdf16 Mar 2024
Details of encumbrances concerned to FinanceFile: 1b Details of encumbrances on legal (Q2).pdf16 Mar 2024
Details of encumbrances concerned to FinanceFile: 1b Details of encumbrances on legal (Q3).pdf16 Mar 2024
Details of encumbrances concerned to FinanceFile: 1b Details of encumbrances on legal (Q1).pdf16 Mar 2024
Details of encumbrances concerned to FinanceFile: 1b Details of encumbrances on legal (Q2).pdf16 Mar 2024
Details of encumbrances concerned to FinanceFile: 1b Details of encumbrances on legal (Q3).pdf16 Mar 2024
Details of encumbrances concerned to LegalFile: 1b Details of encumbrances on legal (Q1).pdf16 Mar 2024
Details of encumbrances concerned to LegalFile: 1b Details of encumbrances on legal (Q2).pdf16 Mar 2024
Details of encumbrances concerned to LegalFile: 1b Details of encumbrances on legal (Q3).pdf16 Mar 2024
Details of encumbrances concerned to LegalFile: 1b Details of encumbrances on legal (Q1).pdf16 Mar 2024
Details of encumbrances concerned to LegalFile: 1b Details of encumbrances on legal (Q2).pdf16 Mar 2024
Details of encumbrances concerned to LegalFile: 1b Details of encumbrances on legal (Q3).pdf16 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate Q1(April-June).pdf16 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate Q2(July-September).pdf16 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate Q3(October-December).pdf16 Mar 2024
Details of encumbrances concerned to FinanceFile: 1a Declaration of encumbrances on finance (Q1).pdf14 Mar 2024
Details of encumbrances concerned to FinanceFile: 1a Details of encumbrances on finance (Q2).pdf14 Mar 2024
Details of encumbrances concerned to FinanceFile: 1a Details of encumbrances on finance (Q3).pdf14 Mar 2024
Details of encumbrances concerned to LegalFile: 1a Declaration of encumbrances on finance (Q1).pdf14 Mar 2024
Details of encumbrances concerned to LegalFile: 1a Details of encumbrances on finance (Q2).pdf14 Mar 2024
Details of encumbrances concerned to LegalFile: 1a Details of encumbrances on finance (Q3).pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect's Certififcate of Percentage of Completion on Work Q1 (April-June).pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect's Certificate of Percentage of Completion on Work Q2 (July-Sept).pdf14 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect's Certificate of Percentage of Completion on Work Q3 (Oct-Dec).pdf14 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate on Cost incurred on Project cost Q1 (April-June).pdf14 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate on Cost incurred on Project cost Q2 (July-Sept).pdf14 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer;s Certificate on Cost incurred on Project cost Q3 (Oct- Dec).pdf14 Mar 2024
CERSAI detailsFile: 1 CERSAI details.pdf14 Mar 2024
Other - FinanceFile: Declaration.pdf10 Apr 2023
CERSAI detailsFile: Cersai Declaration.pdf22 Mar 2023
Proforma of Agreement for saleFile: organized (3).pdf22 Mar 2023
Details of encumbrances concerned to FinanceFile: Encumberance.pdf9 Mar 2023
Details of encumbrances concerned to LegalFile: Encumberance.pdf9 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report_200261339764_For_Asset_Based_Search_25_02_2023_13_57_29_269.pdf9 Mar 2023
Declaration in FORM BFile: Form B.pdf21 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate 2.pdf21 Feb 2023
Layout approvalFile: Layout.pdf20 Feb 2023
Building plan approvalFile: Layout.pdf20 Feb 2023
PAN CardFile: pan Firm.pdf20 Feb 2023
Copy of the legal title reportFile: Title_Certiricate.pdf20 Feb 2023
Copy of the legal title reportFile: search report 2.pdf20 Feb 2023

How this compares with Thane

70%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PANCHRATNA SAPPHIRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALYAN7,600+ in Thane

2 kmPANCHRATNA SAPPHIRECompleted 39Lapsed / revoked 35Other 101Dot size: filed unitsN

Filed coordinates, straight-line distance. 175 registered projects within 2 km.

Builder: PANCHARATNA DEVELOPERS

PANCHARATNA DEVELOPERS has 6 registrations on MahaRERA, including JEEVAN SHILP and PANCHARATNA COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if PANCHRATNA SAPPHIRE is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PANCHRATNA SAPPHIRE?

The registered promoter entity is PANCHARATNA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PANCHRATNA SAPPHIRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PANCHRATNA SAPPHIRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PANCHRATNA SAPPHIRE?

The professionals named in the filing: Architect: SPACE ENVIRO ARCHITECTS; Architect: ANKUR ARVINDSHETYE; Engineer: KHASNIS & ASSOCIATES; Chartered Accountant: R A HOTWANI & COMPANY; Chartered Accountant: D S KARIRA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PANCHRATNA SAPPHIRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PANCHRATNA SAPPHIRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PANCHRATNA SAPPHIRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.