Completed No litigation declared Residential / Group Housing project

Panache

By Cedrus Assets

RG-MH-02637 · RERA P52100010652 · Last updated on MahaRERA portal: 21 Apr 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Staircases, 99%
0Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

Panache is a Residential / Group Housing project by Cedrus Assets in Pune, Maharashtra, registered with MahaRERA as P52100010652 on 31 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2026. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NamePanache
  • TypeResidential / Group Housing
  • Location
    • Ghorpadi
    • Haveli
    • Pune
    • 411001
  • Pincode411001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100010652
  • ReraGenie IDRG-MH-02637

Builder

  • NameCedrus Assets
  • Entity typeOthers
  • Named personsNilesh Bajaj, Atharva Consortium, Umesh Pillay, Mohit Shah, Kalpita Shah, Bharat Vijaykumar Mittal, Nitin Muthiyan, Anand Sabu, Rita Sabu, Sonali Bilawar, Santosh S, Shamsundar Mohanlal Dodiya and 15 more

Key dates

this monthRegisteredAug 2017First promiseDec 2024Revised toJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed81 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PanacheNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 99%.

Panache: 76% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises53%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 21 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes95%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed78

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots78
Closed/Covered64
Open Space14

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,752 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3736.19
Proposed, not sanctioned2,615 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchIndra Pushti, Opposite FC College Gate -2,Pune 411004

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Anil Saykar
EngineerVastech Consultant
PartnerRole in project
Cedrus Assets-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025972Dec 2024 → Jun 2026

Reason as filed by the promoterWe are unable to commence construction due to Our financial strain is primarily due to slow market demand, caused by a combination of factors. The broader economic downturn and global uncertainties have reduced consumer confidence and spending. Additionally, shifts in consumer behavior, increased competition, and market saturation have slowed sales. Delayed payments from clients and longer sales cycles have further compounded the issue, creating cash flow challenges. Operational disruptions and the need to adjust our strategy to current market conditions have also contributed to the financial

Litigation declared1

CaseCourtStatus
976/2008/2008Civil Judge Senior Division PunePending

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Dec 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: 5 (2).pdf21 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form A____Architect Certi__31 03 25_0001.pdf21 Apr 2025
Certificates of CA (Form 3)File: FORM 3 C A Certificate 31 03 25___F.pdf21 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENG Certificate 31 03 25__F (1).pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: Cedrus Assets Disclosure of Sold__31 03 25_0001 (1).pdf21 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2 A____ENG CERT 2024 2025___F_0001 (1).pdf21 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2 A____ENG CERT 2024 2025___F_0001 (1).pdf21 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch Certificate.pdf15 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (21).pdf15 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch Certificate (3).pdf15 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 march 2024.pdf15 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 June 2024.pdf15 Mar 2025
Certificates of CA (Form 3)File: Form 3-30-09-2023_Signed (1) (1).pdf15 Mar 2025
Certificates of CA (Form 3)File: Form 3-31-12-2023_Signed (1) (1).pdf15 Mar 2025
Certificates of CA (Form 3)File: Form 3-31-03-2024_Signed (1) (1).pdf15 Mar 2025
Certificates of CA (Form 3)File: Form 3-30-06-2024_Signed (1) (1).pdf15 Mar 2025
Certificates of CA (Form 3)File: Form 3-31-09-2024_Signed (1) (1).pdf15 Mar 2025
Certificates of CA (Form 3)File: Form 3-31-12-2024_Signed (1) (1).pdf15 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: june 2024 panache (1) (2).pdf15 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sep 2024 Panache (1) (1).pdf15 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: lDec 24 panache (1) (1).pdf15 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: june 2023 Panache (1).pdf11 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sep 2023 panache (1).pdf11 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sep 2023 panache (1) (1).pdf11 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dec 2023 Panache (1) (1).pdf11 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: march 2024 Panache (1) (1).pdf11 Mar 2025
Layout approvalFile: 20241231_140457_11zon.pdf31 Dec 2024
Building plan approvalFile: 20241231_140548_11zon.pdf31 Dec 2024
Building plan approvalFile: 20241231_140701_11zon.pdf31 Dec 2024
Building plan approvalFile: 20241231_140701_11zon (1).pdf31 Dec 2024
Building plan approvalFile: 20241231_140756_11zon.pdf31 Dec 2024
Copy of Layout Approval (in case of layout)File: 20241231_140457_11zon.pdf31 Dec 2024
Declaration in FORM BFile: Form B Notary.pdf31 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: pmc.pdf31 Dec 2024
Building Plan Approval (IOD)File: 20241231_140548_11zon.pdf31 Dec 2024
Building Plan Approval (IOD)File: 20241231_140701_11zon.pdf31 Dec 2024
Building Plan Approval (IOD)File: 20241231_140701_11zon (1).pdf31 Dec 2024
Building Plan Approval (IOD)File: 20241231_140756_11zon.pdf31 Dec 2024
Declaration about Commencement CertificateFile: Format D.pdf31 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf28 Nov 2023
Certificates of CA (Form 3)File: FORM 3 C A Certificate 31 03 23 Panache_11zon.pdf7 Oct 2023
Certificates of CA (Form 3)File: FORM 3 C A Certificate 30 06 23 Panache_11zon.pdf7 Oct 2023
Certificates of CA (Form 5)File: FORM 3 C A Certificate 30 06 23 Panache_11zon.pdf7 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Panache F1.pdf19 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Panache f2.pdf19 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 MAY 23.pdf13 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 23.pdf24 Feb 2023
Disclosure of sold/ booked inventoryFile: Sold unsold.pdf24 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf24 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch Certificate.pdf14 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Panache .pdf14 Jan 2023
Certificates of CA (Form 3)File: Form 3 (1).pdf14 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf14 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf5 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf5 Nov 2022
Declaration about Commencement CertificateFile: Format D (4).pdf17 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf17 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 21-22.pdf17 Aug 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold.pdf3 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1Architect Certificate _compressed.pdf23 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Panache.pdf23 Jun 2022
Certificates of CA (Form 3)File: Form 3_compressed (2).pdf23 Jun 2022
Certificates of CA (Form 5)File: Form 5 - 21-22.pdf23 Jun 2022
Certificates of CA (Form 5)File: FORM 5.pdf6 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Table A.pdf3 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 07 08 18.pdf3 Sep 2018
Certificates of CA (Form 3)File: CA Certificate.pdf12 Aug 2017
Proforma of Allotment letterFile: RERA COMPLIANT DRAFT AGREEMENT.pdf12 Aug 2017
Layout approvalFile: layout.pdf11 Aug 2017
Copy of Layout Approval (in case of layout)File: layout.pdf11 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2 - Panache.pdf9 Aug 2017
Proforma of Allotment letterFile: Agreement to Sale (1).pdf9 Aug 2017
Building plan approvalFile: Application for Reg of project Panache.pdf5 Aug 2017
Copy of the legal title reportFile: title report.pdf5 Aug 2017
Details of encumbrancesFile: Declaration of Encumbrances.pdf5 Aug 2017
Building Plan Approval (IOD)File: Application for Reg of project Panache.pdf5 Aug 2017
Declaration in FORM BFile: FORM B-ilovepdf-compressed.pdf5 Aug 2017
PAN CardFile: Pan Card Cedrus Assets.pdf3 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 0204.pdf3 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: compressed_FORM 1.pdf3 Aug 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Panache on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ghorpadi13,700+ in Pune

2 kmPanacheCompleted 14Lapsed / revoked 30Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 83 registered projects within 2 km.

Builder: Cedrus Assets

Cedrus Assets has 1 registration on MahaRERA, including Panache. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Panache is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Panache?

The registered promoter entity is Cedrus Assets, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Panache?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Panache?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Panache?

The professionals named in the filing: Architect: Ar Anil Saykar; Engineer: Vastech Consultant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Panache?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Panache. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Panache to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.