Completed No litigation declared Residential / Group Housing project

Palazzio

By Spenta Builders Private Limited

RG-MH-08105 · RERA P51800002414 · Last updated on MahaRERA portal: 18 Nov 2024

Source: official MahaRERA filing

Red flags

  • 10 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2018Possession promisedregistration recorded completed
40 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 0%
10Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

Palazzio is a Residential / Group Housing project by Spenta Builders Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002414 on 31 Jul 2017. The registration is recorded completed; possession was promised by 31 Dec 2018. The completion date has moved by 12 months from the original filing. 10 complaints are on record with the regulator.

At a glance

Project

  • NamePalazzio
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400072
  • Pincode400072
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002414
  • ReraGenie IDRG-MH-08105

Builder

  • NameSpenta Builders Private Limited
  • Entity typeCompany

Key dates

this monthRegisteredJul 2017First promiseDec 2017Revised toDec 2018Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Jul 2017
  • Promised completion31 Dec 2018
  • Revised completionRevised to 31 Dec 2018 (originally 31 Dec 2017)
  • Buildings4 building records
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA150000
Wing BNA150000
Wing CNA150000
Wing DNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 18 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.

Wing A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes95%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed256

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots256
Closed/Covered210
Open Space46
BuildingClosed/CoveredOpen SpaceTotal
Wing A512273
Wing B46652
Wing C381452
Wing D75479

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,482 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Future Communications LtdAndheriMumbai Suburban

Approvals and building plan

Permissible FSI13366.0
Proposed, not sanctioned13,366 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTulsiani Chambers, Free Press Journal Marg, Nariman Point, Mumbai - 400021

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShashikant Jadhav Spaceage Consultants
PartnerRole in project
Spenta Builders Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000016Dec 2017 → Dec 2018

Reason as filed by the promoterWe have made the application for OC on 26/05/2017 as our buildings ready for occupation. Subsequent to our application, as per new norms instated by the MCGM, a letter was written by MCGM to M/s GVK Mumbai International Airport (P) Ltd. to verify the height of the four wings built at site. The representatives of GVK subsequently visited the site and conducted the requisite survey. Despite several follow-ups with representatives of GVK after their visit, we did not receive any formal communication from them. Subsequently, on the verbal suggestion of one of the representatives, we made a revised

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000000180Sagar Sarjerao NikamSpenta Builders Private Limited25/08/2017
CC006000000012618Mr Pradeep Sharma & Mrs Sangeeta SharmaSpenta Builders Pvt Ltd31/12/2017
CC006000000057230Sagar Sarjerao NikamSpenta Builders Private Limited09/12/2018
CC006000000057334NUPURA CHANDRAKANT NAIKSpenta Builders Private Limited25/12/2018
CC006000000057561Ashlesh GosainSpenta Builders Pvt Ltd06/01/2019
CC006000000079514ASHLESH GOSAINM/s Spenta Builders Pvt. Ltd08/06/2019
CC006000000079213RISHI BHASINSpenta Builders Private Limited31/05/2019
CC006000000193879Ravibhushan Kumar Prasad, Jawahar Prasad, Suchitra Jawahar PrasadSpenta Builders Pvt. Ltd.31/08/2020
CC006000000397559Palazzio Co-operative Housing Society Ltd.Spenta Builders Pvt. Ltd.23/09/2023
CC006000000429284Spenta Builders Pvt. Ltd.Ravibhushan Kumar Prasad16/02/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: OCC 2022 JULY FINAL PULLAZIO KURLA.pdf18 Nov 2024
OtherFile: Occupation Certificate Palazzio wing A and D_July2020.pdf18 Nov 2024
OtherFile: OCC 2022 JULY FINAL PULLAZIO KURLA.pdf18 Nov 2024
OtherFile: Occupation Certificate Palazzio wing A and D_July2020.pdf18 Nov 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Palazzio Society Registration Certificate.pdf30 Jun 2021
Architect’s Certificate on Completion of Project (Form 4)File: Compelition certificate.pdf5 Dec 2019
Architect’s Certificate on Completion of Project (Form 4)File: LS Complition Certificate 25052017.pdf5 Dec 2019
Architect’s Certificate on Completion of Project (Form 4)File: Application Letter for A and D.pdf5 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Spenta Builders Pvt Ltd 30th June 2019.pdf25 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Spenta Builders Pvt Ltd 25th October 2019.pdf25 Nov 2019
Certificates of CA (Form 3)File: Form3 CA Cert Palazzio Sep 2019.pdf25 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sep 2019 RERA Palazzio.pdf8 Nov 2019
Certificates of CA (Form 5)File: Spenta Builder Form 5.pdf30 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30 sept 2018.pdf1 Mar 2019
Certificates of CA (Form 3)File: Certificate june18.pdf1 Mar 2019
Certificates of CA (Form 3)File: Form 3 DEC 18.pdf1 Mar 2019
OtherFile: Occupation Certificate Palazzio wing B and C.pdf28 Feb 2019
Certificates of CA (Form 5)File: Spenta Builders Pvt Ltd- RERA Annual Return.pdf30 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: builder Eng -1 mb.pdf2 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BUILDER ARTITECH 3009-1mb.pdf31 Oct 2017
Certificates of CA (Form 3)File: 30 Sep 2017.pdf27 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (Palazzio).pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (Palazzio).pdf27 Jul 2017
Certificates of CA (Form 3)File: Form 3.pdf27 Jul 2017
Proforma of Allotment letterFile: AFS Palazzio Final.pdf21 Jul 2017
Layout approvalFile: Layout Certification.pdf20 Jul 2017
Copy of the legal title reportFile: Title Certificate Final.pdf20 Jul 2017
Details of encumbrancesFile: Letter of Encumberance.pdf20 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Certification.pdf20 Jul 2017
Declaration in FORM BFile: Form B (Spenta).pdf20 Jul 2017
Building plan approvalFile: IOD.pdf18 Jul 2017
PAN CardFile: SPENTA BUILDERS PAN.pdf18 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf18 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf18 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Palazzio on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmPalazzioCompleted 49Lapsed / revoked 25Other 43Dot size: filed unitsN

Filed coordinates, straight-line distance. 117 registered projects within 2 km.

Builder: Spenta Builders Private Limited

Spenta Builders Private Limited has 1 registration on MahaRERA, including Palazzio. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Palazzio is delayed beyond 31 Dec 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Palazzio?

The registered promoter entity is Spenta Builders Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Palazzio?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Palazzio?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Palazzio?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Palazzio?

The professionals named in the filing: Architect: Shashikant Jadhav Spaceage Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Palazzio?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Palazzio. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Palazzio to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.