ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / PADMAVATI DARSHAN BUILDING NO. 1

Completed No litigation declared Others project

PADMAVATI DARSHAN BUILDING NO. 1

By PADMAVATI CONSTRUCTION

RG-MH-07111 · RERA P52000053864 · Last updated on MahaRERA portal: 8 Nov 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Internal walls, 98%
30 of 53Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

PADMAVATI DARSHAN BUILDING NO. 1 is a Others project by PADMAVATI CONSTRUCTION in Raigarh, Maharashtra, registered with MahaRERA as P52000053864 on 5 Dec 2023. The registration is recorded completed; possession was promised by 31 Dec 2025. 23 of the 53 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NamePADMAVATI DARSHAN BUILDING NO. 1
  • TypeOthers
  • Location
    • NA
    • Pen (M Cl)
    • Pen
    • Raigarh
    • 402107
  • Pincode402107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000053864
  • ReraGenie IDRG-MH-07111

Builder

  • NamePADMAVATI CONSTRUCTION
  • Entity typePartnership
  • PartnersRANJIT VAKTAVARMAL JAIN, DHARMENDRA MITHALAL JAIN
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2023PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Dec 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed60 files

Current status

43%23 of 53 units booked
95.0%Work done, per cost certificate

Figures as on 8 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PADMAVATI DARSHAN BUILDING NO 1NA7748553

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

PADMAVATI DARSHAN BUILDING NO 1: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 8 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered28
Open Space4

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,400 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Oct 2025

Approvals and building plan

Sanctioning authorityPen NAGARPARISHAD
Permissible FSI4464.52
Proposed, not sanctioned4,465 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBAZAR PETH, PEN, RAIGAD 402 107
Estimated costRs 6.02 cr
Cost incurredRs 5.72 cr
Work done95.0%
BuildingWingEstimatedIncurred
PADMAVATI DARSHAN BUILDING NO 1NARs 5.79 crRs 5.50 cr
-NARs 23.00 lakhRs 21.85 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHINAY JOGI
EngineerMAHESH V CHAVAN
Chartered AccountantCA SHRIKANT DONGRE
Chartered AccountantS.V. DEO & ASSOCIATES
PartnerRole in project
PADMAVATI CONSTRUCTION-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: FORM 2A_ MARCH 25_ PADMAVATI CONSTRUCTION.pdf8 Nov 2025
Form 5 (FY 2024-2025)File: FORM 5_ MARCH 25_ PADMAVATI CONSTRUCTION.pdf8 Nov 2025
Occupational CertificateFile: OC.pdf8 Nov 2025
Withdrawal Update Form 1File: FORM 1_ JUNE25__PADMAVATI CONSTRUCTION.pdf15 Oct 2025
Withdrawal Update Form 1File: FORM 1_ JUNE25__PADMAVATI CONSTRUCTION.pdf15 Oct 2025
Withdrawal Update Form 2File: FORM 2_JUNE25__PADMAVATI CONSTRUCTION.pdf15 Oct 2025
Withdrawal Update Form 2File: FORM 2_JUNE25__PADMAVATI CONSTRUCTION.pdf15 Oct 2025
Withdrawal Update Form 3File: FORM 3_ JUNE25_compressed_PADMAVATI CONSTRUCTION_compressed.pdf15 Oct 2025
Withdrawal Update Form 3File: FORM 3_ JUNE25_compressed_PADMAVATI CONSTRUCTION_compressed.pdf15 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_ MARCH 25.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_ MARCH 25_compressed.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_ MARCH 25.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_ MARCH 25.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: fORM 2A_ MARCH 24.pdf28 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_ MARCH 24.pdf28 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1 PADMAWATI DARSHAN DEC 2024.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 FORM 3 PADMAWATI DARSHAN DEC 2024.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2 PADMAWATI DARSHAN DEC 2024.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: sold unsold inventory.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PADAWATI.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 24 PADMAVATI.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PADMAVATI.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 1_merged.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed.pdf17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed.pdf17 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3_compressed.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-PADMAVATI BLDG 1_DEC 23.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-PADMAVATI BLDG 1_DEC 23.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-PADMAVATI BLDG 1_DEC 23.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-PADMAVATI BLDG 1_DEC 23.pdf19 Jan 2024
Layout approvalFile: 5 Copy of Layout Approval.pdf11 Nov 2023
Building plan approvalFile: 6 Building Plan Approval.pdf11 Nov 2023
PAN CardFile: 1 PAN CARD.pdf11 Nov 2023
Copy of the legal title reportFile: 2 TITLE CERTIFICATE_compressed.pdf11 Nov 2023
Details of encumbrances concerned to FinanceFile: 3 a Details of encumbrances concerned to Finance.pdf11 Nov 2023
Details of encumbrances concerned to FinanceFile: 4 b Details of encumbrances concerned to Legal.pdf11 Nov 2023
Details of encumbrances concerned to LegalFile: 3 a Details of encumbrances concerned to Finance.pdf11 Nov 2023
Details of encumbrances concerned to LegalFile: 4 b Details of encumbrances concerned to Legal.pdf11 Nov 2023
Copy of Layout Approval (in case of layout)File: 5 Copy of Layout Approval.pdf11 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: 6 Building Plan Approval.pdf11 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: 7 Commencement Certificates_compressed.pdf11 Nov 2023
Declaration about Commencement CertificateFile: 8 Declaration about Commencement Certificate.pdf11 Nov 2023
Declaration in FORM BFile: 9 Declaration in FORM B_compressed.pdf11 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1-RERA -BLDG-01-231108-mailed (1).pdf11 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA_Mr Ranjit Jain_09112023_compressed.pdf11 Nov 2023
CERSAI detailsFile: 12 CERSAI details.pdf11 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 13 CA Certificate on Project Cost and Fund withdrawal (Form 3)_compressed (2).pdf11 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 14 Disclosure of Interest in Other Real Estate Organizations.pdf11 Nov 2023
Proforma of Agreement for saleFile: 15 Proforma of Agreement for sale.pdf11 Nov 2023
Proforma of Allotment letterFile: 16 Proforma of Allotment letter.pdf11 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 18 Separate Bank Account details including no encumbrances on the Bank Account or no escro11 Nov 2023
Deviation Report with respect to Allotment letterFile: 19 Deviation Report with respect to Allotment letter.pdf11 Nov 2023
Deviation Report with respect to model copy of AgreementFile: 20 Deviation Report with respect to model copy of Agreement.pdf11 Nov 2023
Other - LegalFile: 17 Legal Other_compressed-1-20.pdf11 Nov 2023
Other - LegalFile: 17 Legal Other_compressed-21-40.pdf11 Nov 2023

How this compares with Raigarh

43%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PADMAVATI DARSHAN BUILDING NO. 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NA5,900+ in Raigarh

2 kmPADMAVATI DARSHAN BUILDICompleted 49Lapsed / revoked 21Other 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 92 registered projects within 2 km.

Builder: PADMAVATI CONSTRUCTION

PADMAVATI CONSTRUCTION has 3 registrations on MahaRERA, including PADMAVATI CORNER and PADMAVATI DARSHAN BUILDING NO 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if PADMAVATI DARSHAN BUILDING NO. 1 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PADMAVATI DARSHAN BUILDING NO. 1?

The registered promoter entity is PADMAVATI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PADMAVATI DARSHAN BUILDING NO. 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PADMAVATI DARSHAN BUILDING NO. 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PADMAVATI DARSHAN BUILDING NO. 1?

The professionals named in the filing: Architect: ABHINAY JOGI; Engineer: MAHESH V CHAVAN; Chartered Accountant: CA SHRIKANT DONGRE; Chartered Accountant: S.V. DEO & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PADMAVATI DARSHAN BUILDING NO. 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PADMAVATI DARSHAN BUILDING NO. 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PADMAVATI DARSHAN BUILDING NO. 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.