ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / PADMAVATI AVIGHNA

Registered No litigation declared Others project

PADMAVATI AVIGHNA

By PADMAVATI DEVELOPERS

RG-MH-48950 · RERA P51700051684 · Last updated on MahaRERA portal: 16 Jun 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 13 other registrations.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedno revision filed
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 88%
0Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

PADMAVATI AVIGHNA is a Others project by PADMAVATI DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700051684 on 27 Jun 2023. Possession is promised by 31 Mar 2028.

At a glance

Project

  • NamePADMAVATI AVIGHNA
  • TypeOthers
  • Location
    • Titwala
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • RERA no.P51700051684
  • ReraGenie IDRG-MH-48950

Builder

  • NamePADMAVATI DEVELOPERS
  • Entity typePartnership
  • PartnersBHARAT JETHMAL JAIN, RESHMA JITENDRA JAIN, VIMAL KEWALCHAND SHANKLESHA
  • Other registrations13 more →
  • Completed3 of 14
  • No longer live6 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredJun 2023PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jun 2023
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1NA160000
BUILDING NO 2NA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 88%.

BUILDING NO 143%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 243%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Open Space40
BuildingOpen SpaceTotal
BUILDING NO 188
BUILDING NO 23232

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,930 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9433.42
Proposed, not sanctioned9,433 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKALYAN WEST TALUKA KALYAN DIST THANE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCREATIONS ARCHITECTS AND INTERIOR DESIGNERS
EngineerAssociated Structural Engineers LLP
Chartered AccountantC V BHOIR & CO
PartnerRole in project
PADMAVATI DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Developers Form B.pdf16 Jun 2023
Building plan approvalFile: Sheet No 01.pdf6 Jun 2023
Building plan approvalFile: Sheet No 02.pdf6 Jun 2023
Building plan approvalFile: Sheet No 03.pdf6 Jun 2023
Building plan approvalFile: Sheet No 04.pdf6 Jun 2023
Building plan approvalFile: Sheet No 05.pdf6 Jun 2023
Details of encumbrances concerned to FinanceFile: EC - Finance.pdf6 Jun 2023
Details of encumbrances concerned to FinanceFile: EC - Legal.pdf6 Jun 2023
Details of encumbrances concerned to LegalFile: EC - Finance.pdf6 Jun 2023
Details of encumbrances concerned to LegalFile: EC - Legal.pdf6 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Sheet No 01.pdf6 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Sheet No 02.pdf6 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Sheet No 03.pdf6 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Sheet No 04.pdf6 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: Sheet No 05.pdf6 Jun 2023
Proforma of Agreement for saleFile: AFS.pdf6 Jun 2023
Deviation Report with respect to model copy of AgreementFile: Deviation for AFS.pdf6 Jun 2023
Other - LegalFile: Allotment Letter.pdf6 Jun 2023
Other - LegalFile: Developers Form B.pdf6 Jun 2023
Other - TechnicalFile: Letter of chnage s_no_ (2 files merged).pdf6 Jun 2023
Other - TechnicalFile: CERSAI details.pdf6 Jun 2023
Other - TechnicalFile: Disclosure of Interest in Other Real Estate Organizations.pdf6 Jun 2023
Other - TechnicalFile: Form D.pdf6 Jun 2023
Other - TechnicalFile: Separate Bank Account Declaration.pdf6 Jun 2023
Declaration about Commencement CertificateFile: RERA FORM D.pdf22 Apr 2023
Layout approvalFile: LAYOUT PLAN.pdf5 Apr 2023
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf5 Apr 2023
Details of encumbrances concerned to FinanceFile: encumbrances concerned to Finance.pdf21 Mar 2023
Details of encumbrances concerned to FinanceFile: encumbrances concerned to Legal.pdf21 Mar 2023
Details of encumbrances concerned to LegalFile: encumbrances concerned to Finance.pdf21 Mar 2023
Details of encumbrances concerned to LegalFile: encumbrances concerned to Legal.pdf21 Mar 2023
CERSAI detailsFile: CERSAI details.pdf21 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf21 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account details.pdf21 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.pdf21 Mar 2023
Other - LegalFile: Certificates.pdf21 Mar 2023
Copy of the legal title reportFile: Copy of the legal title report.pdf14 Mar 2023
Proforma of Allotment letterFile: Rera Allotment Letter.pdf14 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PAGE FINAL .pdf9 Feb 2023
PAN CardFile: pan card padmavati.pdf31 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: PLAN APPROVAL CERTIFICATE.pdf31 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf31 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf31 Jan 2023
CERSAI detailsFile: Membership of BAI.pdf31 Jan 2023

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PADMAVATI AVIGHNA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Titwala7,600+ in Thane

Builder: PADMAVATI DEVELOPERS

PADMAVATI DEVELOPERS has 14 registrations on MahaRERA, including VRUSHAB RESIDENCY and PADMAVATI VILLA. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if PADMAVATI AVIGHNA is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PADMAVATI AVIGHNA?

The registered promoter entity is PADMAVATI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PADMAVATI AVIGHNA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PADMAVATI AVIGHNA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PADMAVATI AVIGHNA?

The professionals named in the filing: Architect: CREATIONS ARCHITECTS AND INTERIOR DESIGNERS; Engineer: Associated Structural Engineers LLP; Chartered Accountant: C V BHOIR & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PADMAVATI AVIGHNA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PADMAVATI AVIGHNA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PADMAVATI AVIGHNA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.