Home / Browse projects / Pune, Maharashtra / PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C
PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C
RG-MH-11563 · RERA P52100001995 · Last updated on MahaRERA portal: 19 Jul 2021
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 22 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C is a Residential / Group Housing project by OM BALAJI PLAZA in Pune, Maharashtra, registered with MahaRERA as P52100001995 on 31 Jul 2017. The registration is recorded completed; possession was promised by 30 Oct 2020. The completion date has moved by 22 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NamePADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C
- TypeResidential / Group Housing
- Location
- SINHGAD ROAD
- DHAYARI
- Dhayari (Part)
- Haveli
- Pune
- 411041
- Pincode411041
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100001995
- ReraGenie IDRG-MH-11563
Builder
- NameOM BALAJI PLAZA
- Entity typePartnership
- PartnersMOTILAL NARAYAN HARIHAR, SANGRAM NARAYAN HARIHAR, SAVITA PRATAP MANKAR, MADHURI KISHOR CHAVAN, TEJPAL NAVALMAL JAIN, OMKAR SOMNATH SATTE, DEEPAK NATHAJI MANE, HIRALAL NARAYAN HARIHAR
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on31 Jul 2017
- Promised completion30 Oct 2020
- Revised completionRevised to 30 Oct 2020 (originally 31 Dec 2018)
- Buildings2 building records
- Documents filed28 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING B | NA | 14 | 0 | 0 | 0 | 0 |
| BUILDING C | NA | 14 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 19 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 90%.
BUILDING B49%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING C40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 19 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 50% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed41
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| BUILDING B | 21 | 21 |
| BUILDING C | 20 | 20 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| GURUPRASAD VASTU YOJANA | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PANKAJ SANGHVI |
| Engineer | G A BHILARE CONSULTANTS PRIVATE LIMITED |
| Partner | Role in project |
|---|---|
| OM BALAJI PLAZA | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. We have applied for the Site Elevation NOC (project requirement) as on 18/09/2019(copy of the application attached), we will receive this NOC up to March-April 2020. 2. As soon as we will receive the above said NOC, applying for the Completion Certificate to the Corporation Authority & the same procedure will take further 1-2 months.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 712/2015/2015 | V S MALKALPATTE REDDY FIFTH JT CIVIL JUDGE SENIOR DIVISION PUNE | MATTER IS DISPOSED OFF AND IN FAVOUR OF OM BALAJI PLAZA |
| 1044/2015/2015 | V S MALKALPATTE REDDY FIFTH JT CIVIL JUDGE SENIOR DIVISION PUNE | ORDER PASSED BY HONOURABLE COURT THAT SAID DISPUTE IS NOT IN RESPECT OF JOINT VENTURE AGREEMENT BETW |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000023272 | HEMCHANDRA RAJARAM BHONSALE | VISHNU NARAYAN HARIHAR THROUGH OM BLALJI PLAZA | 25/07/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 24 May 2021
Documents filed28
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Certificate FY 2019-20.pdf | 19 Jul 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION_CERTIFICATE_B___C_BUILDING_PART.pdf | 24 May 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_ARCHITECT_CERTIFICATE_B_BUILDING.pdf | 24 May 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_ARCHITECT_CERTIFICATE_C_BUILDING.pdf | 24 May 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETIONCERTIFICATEBCBUILDING.pdf | 27 Apr 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: CA's Certificate - Form 5 - FY 2017-18.pdf | 22 Jun 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA's Certificate - Form 5 - FY 2018-19.pdf | 22 Jun 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1) ENGINEER FORM 2A JUNE 2019.pdf | 14 Jan 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2) ENGINEER FORM 2A SEPTEMBER 2019.pdf | 14 Jan 2020 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 3) ENGINEER FORM 2A DECEMBER 2019.pdf | 14 Jan 2020 |
| Certificates of CA (Form 3)File: CA Certificate 1 to 2.pdf | 27 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate 3.pdf | 27 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate 4 to 6.pdf | 27 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate 7 to 10.pdf | 27 Jul 2017 |
| Building plan approvalFile: Project Layout.pdf | 26 Jul 2017 |
| Layout approvalFile: Project Layout.pdf | 26 Jul 2017 |
| PAN CardFile: PAN CARD.pdf | 26 Jul 2017 |
| Copy of the legal title reportFile: Legal Title Report 1.pdf | 26 Jul 2017 |
| Copy of the legal title reportFile: Legal Title Report 2.pdf | 26 Jul 2017 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 26 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Project Layout.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Project Layout.pdf | 26 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 26 Jul 2017 |
| Declaration in FORM BFile: Affidavit cum Declaration Form B.pdf | 26 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 26 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 26 Jul 2017 |
| Proforma of Allotment letterFile: Proforma Letter of Allotment.pdf | 26 Jul 2017 |
| Proforma of Allotment letterFile: Proforma of Agreement for Sale.pdf | 26 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 28 filed documents as one ZIP, foldered, with a manifest
Keep PADMANABH GOLDEN VALLEY PHASE-I BUILDING B A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DHAYARI13,700+ in Pune
Filed coordinates, straight-line distance. 141 registered projects within 2 km.
VYANA PHASE-I -T5, T6, T7
KOLTE-PATIL DEVELOPERS LIMITED
Pratham Vihar Phase I
LJR Constructions LLP
VYANA PHASE-I-T2,T3 AT THE RESERVE
KOLTE-PATIL DEVELOPERS LIMITED
MAITREE MEGA CITY
MAITREE INFRA
RAMANA MYRA
SAI AND SHANTISHOBHA VENTURE
Apple Regency
Sri Sidhievinayak associetes
Builder: OM BALAJI PLAZA
OM BALAJI PLAZA has 1 registration on MahaRERA, including PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C is delayed beyond 30 Oct 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C?
The registered promoter entity is OM BALAJI PLAZA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C?
The professionals named in the filing: Architect: PANKAJ SANGHVI; Engineer: G A BHILARE CONSULTANTS PRIVATE LIMITED. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PADMANABH GOLDEN VALLEY PHASE-I BUILDING B AND C?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback