Home / Browse projects / Pune, Maharashtra / PADMA MADHAV

Completed No litigation declared Residential / Group Housing project

PADMA MADHAV

By Vriddhi Realty Parvati LLP

RG-MH-64843 · RERA P52100052040 · Last updated on MahaRERA portal: 21 Feb 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Staircases, 90%
7 of 18Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 83 documents Report an error

PADMA MADHAV is a Residential / Group Housing project by Vriddhi Realty Parvati LLP in Pune, Maharashtra, registered with MahaRERA as P52100052040 on 19 Jul 2023. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 6 months from the original filing. 11 of the 18 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NamePADMA MADHAV
  • TypeResidential / Group Housing
  • Location
    • DAHANUKAR COLONY ROAD
    • KOTHRUD
    • Haveli
    • Pune
    • 411038
  • Pincode411038
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052040
  • ReraGenie IDRG-MH-64843

Builder

  • NameVriddhi Realty Parvati LLP
  • Entity typeOthers
  • Named personsAmit Anupan Shah, AMOL SHAILENDRA SHAH
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2023First promiseJun 2025Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Jul 2023
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed83 files

Current status

61%11 of 18 units booked

Figures as on 21 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PADMA MADHAVNA7718018

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

PADMA MADHAV: 67% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed23

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots23
Closed/Covered23

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area569 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Feb 2026
LandownerVillageDistrict
Padma Madhav ApartmentKothrudPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI1866.65
Proposed, not sanctioned1,867 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKanya School, Ground Floor A Wing, 1, NC Kelkar Road, Narayan Peth, Pune 411030

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAVIRAJ GOSAVI
EngineerARHAM CONSTRUCTIONS
Chartered AccountantMUTTHA AND LAHOTI
Chartered AccountantM.K Chhajed & Co
PartnerRole in project
Vriddhi Realty Parvati LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018450Jun 2025 → Dec 2025

Reason as filed by the promoter.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed83

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Q3.pdf21 Feb 2026
Form 2File: Form 2 Q3.pdf21 Feb 2026
Form 3File: Form 3 Q3.pdf21 Feb 2026
Disclosure of Sold and Booked InventoryFile: Promoters Disclosure.pdf21 Feb 2026
Occupational CertificateFile: Occupancy Certificate - Full.pdf21 Feb 2026
Form 1File: Form 1 Padma Madhav.pdf19 Oct 2025
Form 2File: Form 2 Padma Madhav.pdf19 Oct 2025
Form 3File: Form 3.pdf19 Oct 2025
Disclosure of Sold and Booked InventoryFile: Promoters Disclosure 30092025.pdf19 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5 Padma Madhav.pdf19 Oct 2025
Form 1File: Form 1.pdf20 Jul 2025
Form 2File: Form 2.pdf20 Jul 2025
Form 3File: Form 3_compressed.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Padma Madhav 11-07-2025.pdf20 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PM - Form 1.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PM - Form 3_compressed.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PM - Form 2.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Promoters Disclosure.pdf20 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 VRPL - Padma Madhav.PDF4 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-PM.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-PM_compressed.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-PM.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Promoters Dis-PM.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VRPL Form 2.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: VRPL - Form 3_compressed.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclouser Of Sold Booked Inventory-As per Form 3.pdf7 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engg Certificate.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Promoters Disclosure.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate_compressed.pdf20 Apr 2024
Layout approvalFile: Sanctioned 1.pdf6 Apr 2024
Building plan approvalFile: Sanctioned 2.pdf6 Apr 2024
Building plan approvalFile: Sanctioned 3.pdf6 Apr 2024
Copy of Layout Approval (in case of layout)File: Sanctioned 1.pdf6 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned 2.pdf6 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned 3.pdf6 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert CC-0032-24.pdf6 Apr 2024
Declaration about Commencement CertificateFile: Declaration About Commencement.pdf6 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Cer.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Cer.pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: Promoter's Disclosure-PM.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA Cer.pdf20 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Decl-Form 2A.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Decl-Form 5.pdf10 Jan 2024
Declaration in FORM BFile: Form B.pdf5 Jan 2024
Disclosure of sold/ booked inventoryFile: Promoter's Disclosure-PM.pdf5 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 - VRPL.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Oct 2023
Layout approvalFile: Sanctioned dwg Sheet 1_compressed.pdf18 Oct 2023
Building plan approvalFile: Sanctioned dwg Sheet 2_compressed.pdf18 Oct 2023
Building plan approvalFile: Sanctioned dwg Sheet 3.pdf18 Oct 2023
Copy of Layout Approval (in case of layout)File: Sanctioned dwg Sheet 1_compressed.pdf18 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned dwg Sheet 2_compressed.pdf18 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned dwg Sheet 3.pdf18 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert CC-1328-23.pdf18 Oct 2023
Declaration about Commencement CertificateFile: Declaration of CC.pdf18 Oct 2023
Other - LegalFile: LAYOUT.pdf23 May 2023
Other - TechnicalFile: LAYOUT.pdf23 May 2023
Copy of the legal title reportFile: FINAL UPLOAD.pdf16 May 2023
Proforma of Agreement for saleFile: Draft Agreement NEW.pdf16 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf18 Apr 2023
Deviation Report with respect to Allotment letterFile: DEVIATION FOR ALLOTMENT LETTER.pdf18 Apr 2023
Declaration in FORM BFile: Form B.pdf17 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST.pdf17 Apr 2023
Proforma of Allotment letterFile: DRAFT ALLOTMENT LETTER.pdf17 Apr 2023
Layout approvalFile: LAYOUT.pdf14 Apr 2023
Building plan approvalFile: BUILDING PLAN.pdf14 Apr 2023
Building plan approvalFile: BUILDING PLAN 1.pdf14 Apr 2023
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf14 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN.pdf14 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN 1.pdf14 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf14 Apr 2023
Declaration about Commencement CertificateFile: FORMAT D.pdf14 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DISCLOSURE FOR SEPERATE BANK ACCOUNT.pdf14 Apr 2023
PAN CardFile: VRPL Pan Card.pdf13 Apr 2023
Details of encumbrances concerned to FinanceFile: FINANCE ENCUMBRANCE.pdf13 Apr 2023
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMBRANCE.pdf13 Apr 2023
Details of encumbrances concerned to LegalFile: FINANCE ENCUMBRANCE.pdf13 Apr 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SUKHAKARTACTS NO 168 6 PUNE15CompletedOct 2021Jan 2021

How this compares with Pune

61%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PADMA MADHAV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KOTHRUD13,700+ in Pune

2 kmPADMA MADHAVCompleted 87Lapsed / revoked 44Other 160Dot size: filed unitsN

Filed coordinates, straight-line distance. 291 registered projects within 2 km.

Builder: Vriddhi Realty Parvati LLP

Vriddhi Realty Parvati LLP has 2 registrations on MahaRERA, including SUKHAKARTA and PADMA MADHAV. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PADMA MADHAV is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PADMA MADHAV?

The registered promoter entity is Vriddhi Realty Parvati LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PADMA MADHAV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PADMA MADHAV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PADMA MADHAV?

The professionals named in the filing: Architect: RAVIRAJ GOSAVI; Engineer: ARHAM CONSTRUCTIONS; Chartered Accountant: MUTTHA AND LAHOTI; Chartered Accountant: M.K Chhajed & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PADMA MADHAV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PADMA MADHAV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PADMA MADHAV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.