orsam angan

By GOLD PLAZA DEVELOPERS PVT LTD

RG-MH-10578 · RERA P51900007788 · Last updated on MahaRERA portal: 20 Jun 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 58 months past the filed date
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2021Possession promised58 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 95%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

orsam angan is a Others project by GOLD PLAZA DEVELOPERS PVT LTD in Mumbai City, Maharashtra, registered with MahaRERA as P51900007788 on 18 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • Nameorsam angan
  • TypeOthers
  • Location
    • Mumbai City
    • 400009
  • Pincode400009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900007788
  • ReraGenie IDRG-MH-10578

Builder

  • NameGOLD PLAZA DEVELOPERS PVT LTD
  • Entity typeOthers
  • PartnerBHARAT CHHAGANLAL JAIN
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

58 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ORSAM ANGAMNA270000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

ORSAM ANGAM: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor0%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 20 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Closed/Covered33

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area426 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3897.89
Proposed, not sanctioned3,898 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch19/21 VITHALWADI,ZAVERIBAZER,MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANSARI ISHRAT MOHAMMED YUNUS
EngineerV J JOSHI & ASSOCIATES
PartnerRole in project
GOLD PLAZA DEVELOPERS PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900005740Dec 2019 → Dec 2020

Reason as filed by the promoterOur building work/development been delay due to permission been delay from Estate Dpt & MCGM(Building Proposal Dept),so we request your good office to please extend our project to one year from today(31/3/2021)

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jun 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31032021.pdf20 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31032022.pdf20 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31032023.pdf20 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31032024.pdf20 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A 31032021.pdf20 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A 31032022.pdf20 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A 31032023.pdf20 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A 31032024.pdf20 Jun 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Disclosure.pdf20 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Form A Bank account.pdf20 Jun 2024
Certificates of CA (Form 5)File: FORM 5 TILL 31 MARCH 2019.pdf19 Feb 2020
Building plan approvalFile: BHAILAL AMEMDET PLAN 1.pdf27 Jun 2019
Building plan approvalFile: BHAILAL AMEMDET PLAN 2.pdf27 Jun 2019
Building plan approvalFile: BHAILAL AMEMDET PLAN 3.pdf27 Jun 2019
Building plan approvalFile: BHAILAL AMEMDET PLAN 4.pdf27 Jun 2019
Building Plan Approval (IOD)File: BHAILAL AMEMDET PLAN 1.pdf27 Jun 2019
Building Plan Approval (IOD)File: BHAILAL AMEMDET PLAN 2.pdf27 Jun 2019
Building Plan Approval (IOD)File: BHAILAL AMEMDET PLAN 3.pdf27 Jun 2019
Building Plan Approval (IOD)File: BHAILAL AMEMDET PLAN 4.pdf27 Jun 2019
Certificates of CA (Form 5)File: orsam angan form 5.pdf13 Jun 2019
Layout approvalFile: ORSOM 1.pdf30 Jul 2017
Layout approvalFile: ORSOM 1.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: ORSOM 1.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: ORSOM 1.pdf30 Jul 2017
Certificates of CA (Form 3)File: bhailal ca certificate.pdf30 Jul 2017
Proforma of Allotment letterFile: AGREEMENT O.pdf30 Jul 2017
Building plan approvalFile: ORSOM 2.pdf29 Jul 2017
Building plan approvalFile: ORSOM 1.pdf29 Jul 2017
Building Plan Approval (IOD)File: ORSOM 1.pdf29 Jul 2017
Building Plan Approval (IOD)File: ORSOM 2.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: orsom enginneer certificate.pdf29 Jul 2017
Declaration in FORM BFile: BHAILAL AFFIDAVIT.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Orsam Arch Certificate.pdf27 Jul 2017
Details of encumbrancesFile: Orsam angan.pdf21 Jul 2017
PAN CardFile: GOLD PLAZA PAN CARD.pdf17 Jul 2017
Copy of the legal title reportFile: orsam angan title.pdf17 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Bhailal Bhavan 7 10 15.pdf17 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationRegisteredStatusPromisedDelivered
RUDRA HEIGHTSP51900005874PLOT NO 209, CS NO. 197/74, , , , Ward FSouth, Mumbai City, 400033, MAHARASHTRAAug 2017OngoingDec 2021Registered original: Dec 2019Not delivered

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 24 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep orsam angan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mumbai City780+ in Mumbai City

2 kmorsam anganCompleted 13Lapsed / revoked 19Other 60Dot size: filed unitsN

Filed coordinates, straight-line distance. 92 registered projects within 2 km.

Builder: GOLD PLAZA DEVELOPERS PVT LTD

GOLD PLAZA DEVELOPERS PVT LTD has 3 registrations on MahaRERA, including RUDRA HEIGHTS and orsam angan. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that orsam angan shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if orsam angan is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of orsam angan?

The registered promoter entity is GOLD PLAZA DEVELOPERS PVT LTD, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in orsam angan?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for orsam angan?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at orsam angan?

The professionals named in the filing: Architect: ANSARI ISHRAT MOHAMMED YUNUS; Engineer: V J JOSHI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in orsam angan?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About orsam angan. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save orsam angan to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.