Home / Browse projects / Thane, Maharashtra / Ornate Kallisto Phase I

Completed No litigation declared Others project

Ornate Kallisto Phase I

By Ornate Buildcon Developers

RG-MH-25292 · RERA P51700011610 · Last updated on MahaRERA portal: 15 Nov 2021

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

Ornate Kallisto Phase I is a Others project by Ornate Buildcon Developers in Thane, Maharashtra, registered with MahaRERA as P51700011610 on 31 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameOrnate Kallisto Phase I
  • TypeOthers
  • Location
    • Kalyan Bhiwandi Road
    • Temghar Bhiwandi
    • Bhiwandi (M Corp.)
    • Bhiwandi
    • Thane
    • 421302
  • Pincode421302
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700011610
  • ReraGenie IDRG-MH-25292

Builder

  • NameOrnate Buildcon Developers
  • Entity typePartnership
  • PartnerSunil Sedhmal Gupta
  • Other registrations3 more →
  • Completed3 of 4
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ornate KallistoNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Nov 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Ornate Kallisto: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Nov 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Closed/Covered26

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area630 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Archana G TawareBhiwandi (M Corp.)Thane
Ritesh G TawareBhiwandi (M Corp.)Thane
Vijay P PatilBhiwandi (M Corp.)Thane

Approvals and building plan

Permissible FSI6000.03
Proposed, not sanctioned4,609 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBORIVALI WEST

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectK K & Associates
PartnerRole in project
Ornate Buildcon Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700003686Dec 2019 → Dec 2020

Reason as filed by the promoterdue to delay in obtaining permission from the competent authority the project was not been able to be completed on time however we shall complete the project in a span of 1 year from now onwards. the project is almost on the verge of completion. we request you to grant us the certificate at the earliest.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000198269Mr. Amrit Bijendra GuherOrnate Buildcon Developers07/09/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Dec 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Nov 2021

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 OK I.pdf15 Nov 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_1.pdf1 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ]arch ornate kallisto.pdf12 Oct 2021
Certificates of CA (Form 3)File: kallisto -1 form 3_compressed (1).pdf12 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Kallisto 1.pdf8 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Ornate Kallisto Phase I quaterly form 2A.pdf6 Oct 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: letter to rera formation of society_kallisto I.pdf6 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Ornate Kallisto Phase I quaterly.pdf13 Aug 2021
Certificates of CA (Form 3)File: Ornate Kallisto Phase 1 form 3.pdf11 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1 Kallisto A wing I.pdf14 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A PHASE 1.pdf11 Jun 2021
Certificates of CA (Form 3)File: Ornate Kalisto- Phase-1.pdf31 May 2021
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE-KALLISTO-I.pdf27 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Kallisto-Phase I_compressed.pdf23 Jan 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: OK Ph - 1 Form 2-A.pdf22 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: KALLISTO A WING_compressed.pdf17 Oct 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A Kallisto A (1).pdf17 Oct 2020
Details of Restarting of Construction work post lockdownFile: KALLISTO PHASE I.pdf30 Jun 2020
Details of encumbrancesFile: 2.pdf11 Feb 2020
Details of encumbrancesFile: 1.pdf11 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_2018 19_Financial Statements.pdf15 Nov 2019
Certificates of CA (Form 5)File: Form 5_2018 19_CA Certificate.pdf28 Sep 2019
Proforma of Allotment letterFile: Proforma Allot letter and Agree for Sale Kallisto I_40.pdf6 Jul 2019
Proforma of Allotment letterFile: Proforma Allot letter and Agree for sale Kallisto I_ 60.pdf6 Jul 2019
Details of encumbrancesFile: Encumberance letter.pdf13 May 2019
Details of encumbrancesFile: Encumberance letter.pdf13 May 2019
Layout approvalFile: new_Copy of layout proposed.pdf4 Dec 2018
Building plan approvalFile: Approved plan-1.pdf4 Dec 2018
Building plan approvalFile: Approved plan-2.pdf4 Dec 2018
Building plan approvalFile: Approved plan-3.pdf4 Dec 2018
Building plan approvalFile: Approved plan-4.pdf4 Dec 2018
Building plan approvalFile: Approved plan-5.pdf4 Dec 2018
Copy of Layout Approval (in case of layout)File: new_Copy of layout proposed.pdf4 Dec 2018
Building Plan Approval (IOD)File: Approved plan-1.pdf4 Dec 2018
Building Plan Approval (IOD)File: Approved plan-2.pdf4 Dec 2018
Building Plan Approval (IOD)File: Approved plan-3.pdf4 Dec 2018
Building Plan Approval (IOD)File: Approved plan-4.pdf4 Dec 2018
Building Plan Approval (IOD)File: Approved plan-5.pdf4 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: new_Commencement Certificate.pdf4 Dec 2018
Certificates of CA (Form 5)File: Certificate of CA_ FORM 5.pdf13 Nov 2018
Details of encumbrancesFile: Encumbrance letter.pdf6 Nov 2018
Certificates of CA (Form 5)File: Certificate of CA Form 5.pdf31 Oct 2018
Certificates of CA (Form 5)File: Certificate.pdf31 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf23 Mar 2018
Layout approvalFile: Proposed LAYOUT.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Proposed LAYOUT.pdf29 Jul 2017
Certificates of CA (Form 3)File: Certificate of CA FORM 3.pdf29 Jul 2017
Proforma of Allotment letterFile: Proforma of the Allotment letter and Agreement for sale.pdf29 Jul 2017
OtherFile: Declaration Kallisto.pdf29 Jul 2017
Layout approvalFile: BUILDING PLAN APPROVAL 1.pdf28 Jul 2017
Building plan approvalFile: BUILDING PLAN APPROVAL 1.pdf28 Jul 2017
Building plan approvalFile: BUILDING PLAN APPROVAL 2.pdf28 Jul 2017
PAN CardFile: PAN Ornate Buildcon Developers.pdf28 Jul 2017
Copy of the legal title reportFile: Copy of the legal title report.pdf28 Jul 2017
Details of encumbrancesFile: Encumberance certificate-search Report.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: BUILDING PLAN APPROVAL 1.pdf28 Jul 2017
Building Plan Approval (IOD)File: BUILDING PLAN APPROVAL 1.pdf28 Jul 2017
Building Plan Approval (IOD)File: BUILDING PLAN APPROVAL 2.pdf28 Jul 2017
Declaration in FORM BFile: FORM B Sunil Gupta.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect FORM 1.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate of Engineer FORM 2.pdf28 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 not delivered by the promised date1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
ORNATE RISEP51700032780TEMGHAR, Thane288Jan 2022OngoingDec 2026Not due yet
Ornate Kallisto Phase IIP51700018908Temghar, Thane162Dec 2018OngoingDec 2024Not delivered
Ornate Kallisto Phase IVP51700033627TEMGHAR BHIWANDI, Thane17Mar 2022OngoingDec 2023Not delivered
Ornate Kallisto Phase IKalyan Bhiwandi Road Temghar Bhiwandi Dist Thane 421302146-CompletedDec 2019Dec 2019

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ornate Kallisto Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Temghar Bhiwandi7,600+ in Thane

2 kmOrnate Kallisto Phase ICompleted 16Lapsed / revoked 14Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 55 registered projects within 2 km.

Builder: Ornate Buildcon Developers

Ornate Buildcon Developers has 4 registrations on MahaRERA, including Ornate Kallisto Phase I and Ornate Kallisto Phase II. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Ornate Kallisto Phase I is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ornate Kallisto Phase I?

The registered promoter entity is Ornate Buildcon Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ornate Kallisto Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ornate Kallisto Phase I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ornate Kallisto Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ornate Kallisto Phase I?

The professionals named in the filing: Architect: K K & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ornate Kallisto Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ornate Kallisto Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ornate Kallisto Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.