ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / ORIENT LEGACY

Registration lapsed No litigation declared Others project

ORIENT LEGACY

By JEWEL ORIENT

RG-MH-04148 · RERA P51700021264 · Last updated on MahaRERA portal: 5 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
27 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 95%
73 of 219Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 102 documents Report an error

ORIENT LEGACY is a Others project by JEWEL ORIENT in Thane, Maharashtra, registered with MahaRERA as P51700021264 on 14 Jun 2019. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 36 months from the original filing. 146 of the 219 units on this registration are recorded sold or booked, and 27 of 33 construction stages are filed complete.

At a glance

Project

  • NameORIENT LEGACY
  • TypeOthers
  • Location
    • Kalyan - Badlapur Road
    • BELAVALI
    • BADLAPUR (W)
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700021264
  • ReraGenie IDRG-MH-04148

Builder

  • NameJEWEL ORIENT
  • Entity typePartnership
  • PartnersRAMESH SHAMJI PATEL, DILIP DEVJI UKANI, DEVJIBHAI VISHRAM PATEL, BHUPENDRA SHAMJIBHAI PATEL

Key dates

16 months past promisethis monthRegisteredJun 2019First promiseJun 2022Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Jun 2019
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Jun 2022)
  • Buildings3 building records
  • Documents filed102 files

Current status

67%146 of 219 units booked

Figures as on 5 May 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA16166162123
WING BNA11050656
WING CNA75301040

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 5 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 95%.

WING A78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
WING B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 5 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes70%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes31%

Parking filed41

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots41
Closed/Covered10
Open Space31
BuildingClosed/CoveredOpen SpaceTotal
WING A82735
WING B033
WING C213

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,980 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityKBMC
Permissible FSI13394.41
Proposed, not sanctioned13,394 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 12 TO 19, BLDG NO 2, TILAKNAGAR SHARMIK CHSL, CHEMBUR, MUMBAI 400089

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSM ARCHITECTS
Chartered AccountantP C Parvadiya and Associates
PartnerRole in project
JEWEL ORIENT-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700012272Jun 2022 → Dec 2024

Reason as filed by the promoterRevision in plans due to changes in UDCR

EXT51700009422Jun 2022 → Jun 2023

Reason as filed by the promoterRevision in plans due to changes in UDCR

EXT51700027327Jun 2022 → Jun 2025

Reason as filed by the promoterWe would like to provide the following clarification for delay: 1. Project Structure and Status: The project "Orient Legacy" is registered as a single project under MahaRERA and comprises three wings: A, B, and C. o Wings B and C have already been completed, and the Occupancy Certificates (OCs) for these wings were received earlier, dated 19-04-2022. o Additionally, societies for Wings B and C have already been formed. o Wing A is the only ongoing component of the project. 2. Consent for Extension: Given that Wings B and C are complete and only Wing A remains under development, we have taken t

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jun 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Aug 2022

Documents filed102

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form-3_Jewel Orient.pdf5 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_Jewel Orient_15-04-2025.pdf5 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Orient A-wing_RERA FORM_20250331.pdf2 May 2025
Disclosure of sold/ booked inventoryFile: 2025-03-31_Dis of Sold Units_Jewel Orient.pdf2 May 2025
Declaration in FORM BFile: 2025-02-28_Form B_Affidavit.pdf28 Feb 2025
Certificates of CA (Form 3)File: 2025-02-28_RERA_Form 3_CA Cert.pdf28 Feb 2025
Disclosure of sold/ booked inventoryFile: 2025-02-28_Dis of Sold Units_Jewel Orient.pdf28 Feb 2025
Certificates of CA (Form 3)File: Form-3_Jewel Orient.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1_Orient Legacy.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_Orient Legacy.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: 2024-12-31_Dis of Sold Units_Jewel Orient.pdf18 Jan 2025
Certificates of CA (Form 3)File: 2024-10-20_RERA_Form 3_CA Cert.pdf15 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2024-10-11_Form-2_Eng Certficate.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: 2024-09-30_Dis of Sold Units_Jewel Orient.pdf6 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A_23-24 Eng Quality Assu Cert.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1_Architect Certificate_2024-10-10.pdf10 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 2023-24_CA Form_5 Anual Report_RERA.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2024-07-12_Form-2_Eng Certficate.pdf17 Jul 2024
Disclosure of sold/ booked inventoryFile: 2024-06-30_Dis of Sold Units_Jewel Orient.pdf17 Jul 2024
Certificates of CA (Form 3)File: 2024-07-15_RERA_Form 3_CA Cert.pdf17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: S M Architect_Form-1 _11-07-24.pdf13 Jul 2024
Certificates of CA (Form 3)File: FORM3_Orient Legacy.pdf1 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1_Architect Certificate.pdf27 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_Eng Certficate.pdf27 Apr 2024
Disclosure of sold/ booked inventoryFile: Dis of Sold Units_Jewel Orient_compressed.pdf27 Apr 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: B Wing_Society Formation_Certificate.pdf27 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng Certficate_compressed.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: Jewel Orient_Disclosure of Sold -Booked Inventory_compressed.pdf19 Jan 2024
Certificates of CA (Form 3)File: Form 3 CA Cert_compressed.pdf19 Jan 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: C Wing Soc Formation.pdf18 Dec 2023
Certificates of CA (Form 3)File: 2023-11-22_RERA_Form 3_CA Cert.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1_Architect Certificate_2023-10-05.pdf20 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2023-09-30_Form-2_Eng Certficate.pdf20 Nov 2023
Disclosure of sold/ booked inventoryFile: 2023-09-30_Jewel Orient_Sold Unit.pdf20 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1_Architect Cert_2023-03-30.pdf4 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A_22-23 Eng Quality Assu Cert.pdf4 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2022-23_CA Form-5 Annual Report_Rera_(Revised)_compressed.pdf30 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf15 Sep 2023
Certificates of CA (Form 3)File: Form 3_compressed.pdf8 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_Eng Certficate.pdf7 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Dis of Int in other Project_RSP.pdf30 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Dis of Int in other Project_DDU.pdf30 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Jewel_RERA Bank AC.pdf30 Mar 2023
Details of encumbrances concerned to FinanceFile: 2023-03-29_Jewel-Encumbrances Legal.pdf29 Mar 2023
Details of encumbrances concerned to LegalFile: 2023-03-29_Jewel-Encumbrances Legal.pdf29 Mar 2023
CERSAI detailsFile: 2023-03-29_Cersai_Declaration.pdf29 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A_21-22 Eng Quality Assu Cert.pdf28 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2021-22_CA Form-5 Annual Report_Rera.pdf27 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-20.pdf18 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A_2020-21.pdf18 Aug 2022
Declaration about Commencement CertificateFile: Format-D.pdf16 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1-Architects certificate_2019-06-18.pdf16 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1-Architects certificate_2021-03-15.pdf16 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM- 1- Architect Certificate_2022-05-06.pdf16 Aug 2022
Disclosure of sold/ booked inventoryFile: B wing as on 31-07-22.pdf5 Aug 2022
Disclosure of sold/ booked inventoryFile: C wing as on 31-07-22.pdf5 Aug 2022
Building plan approvalFile: Approval Letter 07-10-2021.pdf1 Aug 2022
PAN CardFile: PAN.pdf1 Aug 2022
Building Plan Approval (IOD)File: Approval Letter 07-10-2021.pdf1 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-21_CA Form-5 Annual Report_Rera.pdf1 Aug 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC B and C Wing.pdf1 Aug 2022
Building plan approvalFile: 1.pdf28 Feb 2022
Building plan approvalFile: 2.pdf28 Feb 2022
Building plan approvalFile: 3.pdf28 Feb 2022
Building plan approvalFile: 4.pdf28 Feb 2022
Building plan approvalFile: 5.pdf28 Feb 2022
Building Plan Approval (IOD)File: 1.pdf28 Feb 2022
Building Plan Approval (IOD)File: 2.pdf28 Feb 2022
Building Plan Approval (IOD)File: 3.pdf28 Feb 2022
Building Plan Approval (IOD)File: 4.pdf28 Feb 2022
Building Plan Approval (IOD)File: 5.pdf28 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: Approval 07-10-2021.pdf28 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: Approval Letter_2021-03-01.pdf25 Mar 2021
Layout approvalFile: 1.pdf19 Mar 2021
Building plan approvalFile: 2-compressed.pdf19 Mar 2021
Building plan approvalFile: 3-compressed.pdf19 Mar 2021
Building plan approvalFile: 4-compressed.pdf19 Mar 2021
Building plan approvalFile: 5.pdf19 Mar 2021
Copy of Layout Approval (in case of layout)File: 1.pdf19 Mar 2021

How this compares with Thane

67%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 36 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ORIENT LEGACY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BELAVALI, BADLAPUR (W)7,600+ in Thane

2 kmORIENT LEGACYCompleted 182Lapsed / revoked 67Other 92Dot size: filed unitsN

Filed coordinates, straight-line distance. 341 registered projects within 2 km.

Builder: JEWEL ORIENT

JEWEL ORIENT has 1 registration on MahaRERA, including ORIENT LEGACY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that ORIENT LEGACY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ORIENT LEGACY is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ORIENT LEGACY?

The registered promoter entity is JEWEL ORIENT, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ORIENT LEGACY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ORIENT LEGACY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ORIENT LEGACY?

The professionals named in the filing: Architect: SM ARCHITECTS; Chartered Accountant: P C Parvadiya and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ORIENT LEGACY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ORIENT LEGACY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ORIENT LEGACY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.