Home / Browse projects / Pune, Maharashtra / Oriana Nest
Oriana Nest
RG-MH-60056 · RERA P52100052204 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Oriana Nest is a Residential / Group Housing project by Shrenik Nilesh Oswal in Pune, Maharashtra, registered with MahaRERA as P52100052204 on 31 Jul 2023. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 6 months from the original filing. 40 of the 42 units on this registration are recorded sold or booked, and 22 of 22 construction stages are filed complete.
At a glance
Project
- NameOriana Nest
- TypeResidential / Group Housing
- Location
- Baner Road
- Banergaon
- Baner
- Haveli
- Pune
- 411045
- Pincode411045
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100052204
- ReraGenie IDRG-MH-60056
Builder
- NameShrenik Nilesh Oswal
- Entity typeIndividual
- GSTIN27ACBPO4007G1ZX
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Jul 2023
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2025)
- Buildings2 building records
- Documents filed95 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A wing | NA | 7 | 7 | 28 | 0 | 28 |
| B Wing | NA | 7 | 7 | 14 | 0 | 14 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 22 construction stages are filed complete across 2 buildings.
A wing100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B Wing100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed71
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A wing | 44 | 44 |
| B Wing | 27 | 27 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A wing | NA | Rs 6.82 cr | Rs 6.82 cr |
| B Wing | NA | Rs 6.82 cr | Rs 6.82 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ankur Associates |
| Engineer | Ganesh Himmat Bichukale Himmat Bichukale |
| Chartered Accountant | Govind D Chevale and Associates |
| Chartered Accountant | Govind D Chevale & Associates |
| Chartered Accountant | Deshmukh Deshpande & Associates |
| Chartered Accountant | Deshmukh Deshpande and Associates |
| Chartered Accountant | Chevale Aghav & Co LLP |
| Partner | Role in project |
|---|---|
| Shrenik Nilesh Oswal | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay in revise sanction. Only 2 flats were not completed as on date, all other unit compeleted and a part occupancy certificate received on 31/12/2025
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Apr 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed95
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Q4 FY 2025-26.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 March 2026.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Balaji Realty Q4 FY 2025-26_compressed.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Q4 FY 2025-26.pdf | 4 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 March 2026.pdf | 4 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Balaji Realty Q4 FY 2025-26_compressed.pdf | 4 Jul 2026 |
| Form 2A (FY 2023-2024)File: Form 2A FY 23-24.pdf | 12 Mar 2026 |
| Form 2A (FY 2024-2025)File: Form 2A FY 24-25.pdf | 12 Mar 2026 |
| Form 2A (FY 2025-2026)File: Form 2 A Dec 2025.pdf | 12 Mar 2026 |
| Form 1File: 5 Form 1 June 2025.pdf | 9 Mar 2026 |
| Form 2File: Form 2 June 2025.pdf | 9 Mar 2026 |
| Form 3File: Form 3 June 2025_compressed.pdf | 9 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventory Details June 2025.pdf | 9 Mar 2026 |
| Form 1File: Form 1 - Sep 2025.pdf | 9 Mar 2026 |
| Form 2File: Form 2 Sep 2025.pdf | 9 Mar 2026 |
| Form 3File: Form 3 Sep 2025_compressed.pdf | 9 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventory Sep 2025.pdf | 9 Mar 2026 |
| Form 1File: Form 1 - Dec 2025.pdf | 9 Mar 2026 |
| Form 2File: Form 2 - Dec 2025.pdf | 9 Mar 2026 |
| Form 3File: Form 3 Dec 2025_compressed.pdf | 9 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventory Dec 2025.pdf | 9 Mar 2026 |
| Form 1File: 4 Form 1 March 2025.pdf | 6 Mar 2026 |
| Form 2File: Form 2 March 2025.pdf | 6 Mar 2026 |
| Form 3File: Form 3 Rera Oriana Nest_20250528_0001_compressed.pdf | 6 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold Unit March 2025.pdf | 6 Mar 2026 |
| Form 5 (FY 2023-2024)File: CA Form 5 FY 2023-24.pdf | 28 Feb 2026 |
| Form 5 (FY 2024-2025)File: CA Form 5 FY 2024-25.pdf | 28 Feb 2026 |
| Form 1File: Form 1 Sep 2023.pdf | 2 Feb 2026 |
| Form 2File: Form 2 June 2023.pdf | 2 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold Sep 2023.pdf | 2 Feb 2026 |
| Form 3File: Form 3 Sep 2023_compressed.pdf | 2 Feb 2026 |
| Form 2File: Form 2 - Engineer Certificate_Oriana Nest _Baner.pdf | 30 Jan 2026 |
| Form 3File: RERA Form -3 Oriana Nest _Baner.pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventory Details.pdf | 30 Jan 2026 |
| Form 1File: Form 1 June 2024.pdf | 30 Jan 2026 |
| Form 2File: Form 2 Engineers Certificate.pdf | 30 Jan 2026 |
| Form 1File: Architect Certificate.pdf | 30 Jan 2026 |
| Form 3File: C A Certificate (1).pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Sold Unsold Booked Inventory.pdf | 30 Jan 2026 |
| Form 1File: Architect Certificate Baner 280225.pdf | 30 Jan 2026 |
| Form 2File: FORM 2 Engineers certificate Baner 280125_20250303_0001.pdf | 30 Jan 2026 |
| Form 3File: Oriana Nest - Form 3 Q3 FY 2024-25.pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Sold Unsold Booked Inventory.pdf | 30 Jan 2026 |
| Form 1File: Form 1 March 2023.pdf | 30 Jan 2026 |
| Form 2File: Form 2 March 2023.pdf | 30 Jan 2026 |
| Form 3File: Form 3 March 2023.pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and unsold June 2023.pdf | 30 Jan 2026 |
| Form 1File: Form 1 Dec 2023.pdf | 30 Jan 2026 |
| Form 3File: Form 3 Dec 2023.pdf | 30 Jan 2026 |
| Form 2File: Form 2 Dec 2023.pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and unsold June 2023.pdf | 30 Jan 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Oriana Nest - Form 3 Q3 FY 2024-25.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Baner 280225.pdf | 3 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineers certificate Baner 280125_20250303_0001.pdf | 3 Mar 2025 |
| Other - LegalFile: Format C Application for correction under project .pdf | 1 Mar 2025 |
| Other - LegalFile: Form C Baner RERA.pdf | 12 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate (1).pdf | 29 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Sold Unsold Booked Inventory.pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 26 Nov 2024 |
| Layout approvalFile: HPSC1058_compressed.pdf | 22 Jul 2024 |
| Layout approvalFile: HPSC1059_compressed.pdf | 22 Jul 2024 |
| Layout approvalFile: HPSC1060_compressed.pdf | 22 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: HPSC1058_compressed.pdf | 22 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: HPSC1059_compressed.pdf | 22 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: HPSC1060_compressed.pdf | 22 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate_Oriana Nest _Baner.pdf | 22 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory Details.pdf | 22 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Form -3 Oriana Nest _Baner.pdf | 22 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf | 27 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Bank Declaration.pdf | 27 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance_oriana Nest Legal.pdf | 25 Jul 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance_oriana Nest Legal.pdf | 25 Jul 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report - Balaji Realty.pdf | 25 Jul 2023 |
| CERSAI detailsFile: Cersai Undertaking 27062023.pdf | 30 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CCF_000881.pdf | 30 Jun 2023 |
| Copy of the legal title reportFile: Search and Title Report.pdf | 7 Jun 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance.pdf | 7 Jun 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance.pdf | 7 Jun 2023 |
| Declaration in FORM BFile: Form B_Affidavit cum declaration.pdf | 7 Jun 2023 |
| Declaration about Commencement CertificateFile: Commencement Certificate.pdf | 4 May 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 95 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Oriana Nest on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Banergaon13,700+ in Pune
Filed coordinates, straight-line distance. 358 registered projects within 2 km.
EARTH 1 BY VTP LUXE PHASE 1
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
Godrej Meadows
Mahalunge Township Developers Private Limi
Godrej Green Vistas
Mahalunge Township Developers Private Limi
Godrej Hill Retreat
Mahalunge Township Developers Private Limi
Godrej Green Cove
Mahalunge Township Developers Private Limi
NYATI EMERALD I
NYATI BUILDERS PRIVATE LIMITED
Builder: Shrenik Nilesh Oswal
Shrenik Nilesh Oswal has 1 registration on MahaRERA, including Oriana Nest. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Oriana Nest shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Oriana Nest is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Oriana Nest?
The registered promoter entity is Shrenik Nilesh Oswal, an individual as per the filing. Its GSTIN 27ACBPO4007G1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Oriana Nest?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Oriana Nest?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Oriana Nest?
The professionals named in the filing: Architect: Ankur Associates; Engineer: Ganesh Himmat Bichukale Himmat Bichukale; Chartered Accountant: Govind D Chevale and Associates; Chartered Accountant: Govind D Chevale & Associates; Chartered Accountant: Deshmukh Deshpande & Associates; Chartered Accountant: Deshmukh Deshpande and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Oriana Nest?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback