Home / Browse projects / Pune, Maharashtra / One Place - Wakad

Completed Litigation declared Commercial project

One Place - Wakad

By Sai Mittal Associates

RG-MH-95540 · RERA P52100019579 · Last updated on MahaRERA portal: 4 Oct 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 6 complaints at MahaRERA

Clear

  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Internal walls, 90%
2 of 49Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

One Place - Wakad is a Commercial project by Sai Mittal Associates in Pune, Maharashtra, registered with MahaRERA as P52100019579 on 8 Feb 2019. The registration is recorded completed; possession was promised by 30 Dec 2024. 47 of the 49 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameOne Place - Wakad
  • TypeCommercial
  • Location
    • Wakad Thergaon Road
    • Wakad
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411057
  • Pincode411057
  • RERA no.P52100019579
  • ReraGenie IDRG-MH-95540

Builder

  • NameSai Mittal Associates
  • Entity typePartnership
  • PartnerDilip Mittal
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2019PromisedDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 Feb 2019
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed74 files

Current status

96%47 of 49 units booked

Figures as on 4 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
One PlaceNA7604949

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

One Place: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,220 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Oct 2025

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI1502.15
Proposed, not sanctioned1,102 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJ M ROAD, PUNE

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSolespace
EngineerManjri Desai
Chartered AccountantSAC & Co LLP
Chartered AccountantPriyanka Chordiya and Associates
PartnerRole in project
Sai Mittal Associates-

Litigation declared2

CaseCourtStatus
690/2020Shivajinagar District CourtPending
690/2020JOINT CJSD AND ADDL CJM PUNEOngoing

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC005000000258982Harshad DeshpandeMittal Builders10/06/2023
CC12502431Govind Tukaram GhadlingeSai Mittal Associates17/07/2025
CC12502840Sai Mittal AssociatesMr Kapil Babasaheb Jadhav13/08/2025
CC12502841Sai Mittal AssociatesMr Kapil Babasaheb Jadhav13/08/2025
CC12502842Sai Mittal AssociatesMr Kapil Babasaheb Jadhav13/08/2025
CC12502843Sai Mittal AssociatesMr Kapil Babasaheb Jadhav13/08/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Feb 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 May 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 May 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Jan 2025

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Occupancy Certificate.pdf4 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sai Mittal - Form 1 Dec 2024.pdf29 Jan 2025
Certificates of CA (Form 3)File: form 3 One Place - Wakad 31-12-2024_compressed.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 One Place Wakad.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: Wakad.pdf29 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate Full.pdf7 Jan 2025
Declaration in FORM BFile: Form B SAI MITTAL ASSOCIATES.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Wakad Sai Mittal.pdf6 Nov 2024
Certificates of CA (Form 3)File: Form 3 SEPT Sai Mittal Associates_compressed.pdf6 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_One Place Wakad.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: Inventory_One Place Wakad.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: Inventory_One Place Wakad for Sep 2024.pdf6 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 One Place Wakad 31-03-2024.pdf8 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM_2A_One Place Wakad.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_One Place Wakad.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_One Place Wakad.pdf20 Jul 2024
Certificates of CA (Form 3)File: form 3 One plase - Wakad 30-06-2024_compressed.pdf20 Jul 2024
Certificates of CA (Form 3)File: form 3 one place - wakad 31-03-2024_compressed.pdf30 May 2024
Other - LegalFile: One Place Wakad Court order.pdf18 May 2024
Disclosure of sold/ booked inventoryFile: wakad q1.pdf8 May 2024
Disclosure of sold/ booked inventoryFile: wakad q2.pdf8 May 2024
Disclosure of sold/ booked inventoryFile: wakad q3.pdf8 May 2024
Disclosure of sold/ booked inventoryFile: wakad q4.pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 One Place wakad.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 One Place Wakda.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sai mittal Form 1 sign copy March 2023.pdf20 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_ONE PLACE Wakad.pdf20 Mar 2024
Certificates of CA (Form 3)File: form 3 One Place -Wakad 31-12-2023 both sign_compressed.pdf20 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 One Place Wakad.pdf25 Jan 2024
Certificates of CA (Form 3)File: from 3 one place Wakad 30-06-2023 BOTH SIGN_compressed.pdf25 Jan 2024
Certificates of CA (Form 3)File: from 3 one place - Wakad 30-09-2023-BOTH SIGN_compressed.pdf25 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A Sai mittal Associates.pdf7 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 PC FY 22-23 One Place Wakad_both sign_compressed.pdf7 Sep 2023
Certificates of CA (Form 3)File: Form 3 31122022 Sai Mittal Associates - both sign_compressed.pdf28 Aug 2023
Certificates of CA (Form 3)File: Form 3 30032023 Sai Mittal Associates both sign_compressed.pdf28 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 for One Place Wakad.pdf31 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sai Mittal Form 1 Dec 2022.pdf31 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SAI MITTAL ASSOCIATES Form 2.pdf31 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 WAKAD ENGINEERING CERTIFICATE.pdf31 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-WAKAD-ONE PLACE.pdf27 May 2023
Certificates of CA (Form 3)File: from 3_30092022_one place -wakad_compressed.pdf27 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SAI MITTAL ASSOCIATES - FORM 2.pdf20 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 one place wakad.pdf20 Feb 2023
Certificates of CA (Form 3)File: Form 3 30062022 Sai Mittal Associates Both sign_compressed.pdf20 Feb 2023
Certificates of CA (Form 3)File: Form 3 31032022 Sai Mittal Associates_Sign.pdf20 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Wakad Form2A march 2022 signed.pdf13 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 One Place wakad 31-3 Sign_compressed.pdf17 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Wakad CC No30 26 03 2021.pdf26 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-WAKAD-ONE PLACE.pdf26 Nov 2022
Certificates of CA (Form 3)File: Sai Mittal Associates Form 3 March 20.pdf16 Mar 2022
Certificates of CA (Form 3)File: Sai Mittal Associates Form 3 March 21.pdf16 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SAI MITTAL ASSOCIATES 2019-20 Form 5.pdf16 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SAI MITTAL ASSOCIATES 2020-21 Form 5.pdf16 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch cert Wakad signed .pdf25 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A March 21 Wakad.pdf25 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual Audit Report of Statutory CA (Form 5)(2).pdf25 Aug 2021
Layout approvalFile: Plan 1 MB.pdf7 May 2021
Building plan approvalFile: Plan 1 MB.pdf7 May 2021
Copy of Layout Approval (in case of layout)File: Plan 1 MB.pdf7 May 2021
Building Plan Approval (IOD)File: Plan 1 MB.pdf7 May 2021
Annual Audit Report of Statutory CA (Form 5)File: Form 5 Sai Mittal Associates.pdf29 Sep 2019
Form 2AFile: IMG_Sai mittal.pdf8 Jun 2019
Layout approvalFile: ONE PLACE- WAKAD- RERA LAYOUT1.pdf6 Feb 2019
Copy of Layout Approval (in case of layout)File: ONE PLACE- WAKAD- RERA LAYOUT1.pdf6 Feb 2019
Certificates of CA (Form 3)File: Form 3 CA CETIFICATES.pdf6 Feb 2019
Copy of the legal title reportFile: Title Certificate Wakad.pdf5 Feb 2019
Details of encumbrancesFile: SMA Encumbrance Declaration Letter.pdf5 Feb 2019
Building plan approvalFile: Sanction Plan Page 1.pdf4 Feb 2019
Layout approvalFile: Sanction Plan Page 1.pdf4 Feb 2019
Copy of Layout Approval (in case of layout)File: Sanction Plan Page 1.pdf4 Feb 2019
Building Plan Approval (IOD)File: Sanction Plan Page 1.pdf4 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf4 Feb 2019
Declaration in FORM BFile: Form B Declaration.pdf4 Feb 2019
Proforma of Allotment letterFile: Allotment agreement declaration.pdf4 Feb 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Petals ABCDS No. 194 Petals Wakad Pune 411057164CompletedApr 2017Apr 2017

How this compares with Pune

96%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep One Place - Wakad on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wakad13,700+ in Pune

Builder: Sai Mittal Associates

Sai Mittal Associates has 1 registration on MahaRERA, including One Place - Wakad. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if One Place - Wakad is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of One Place - Wakad?

The registered promoter entity is Sai Mittal Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in One Place - Wakad?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against One Place - Wakad?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for One Place - Wakad?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at One Place - Wakad?

The professionals named in the filing: Architect: Solespace; Engineer: Manjri Desai; Chartered Accountant: SAC & Co LLP; Chartered Accountant: Priyanka Chordiya and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in One Place - Wakad?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About One Place - Wakad. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save One Place - Wakad to a free account