Home / Browse projects / Pune, Maharashtra / ONE BOAT CLUB
ONE BOAT CLUB
By GOEL GANGA CONSTRUCTIONS AND REAL ESTATE PVT LTD
RG-MH-94389 · RERA P52100019356 · Last updated on MahaRERA portal: 12 Feb 2023
Source: official MahaRERA filing
Red flags
- De-registered
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ONE BOAT CLUB is a Residential / Group Housing project by GOEL GANGA CONSTRUCTIONS AND REAL ESTATE PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100019356 on 23 Jan 2019. Possession is promised by 31 Dec 2030. 1 complaint is on record with the regulator.
At a glance
Project
- NameONE BOAT CLUB
- TypeResidential / Group Housing
- Location
- BOAT CLUB ROAD
- SANGAMWADI PUNE
- Pune (M Corp.)
- Pune City
- Pune
- 411001
- Pincode411001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100019356
- ReraGenie IDRG-MH-94389
Builder
- NameGOEL GANGA CONSTRUCTIONS AND REAL ESTATE PVT LTD
- Entity typeCompany
- DirectorATUL JAIPRAKASH GOEL
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on23 Jan 2019
- Promised completion31 Dec 2030
- Revised completionNone
- Buildings3 building records
- Documents filed48 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| LGF TO FIFTEENTH FLOOR | NA | 24 | 0 | 0 | 0 | 0 |
| 16-26 TH FLOOR | NA | 11 | 0 | 0 | 0 | 0 |
| 27-36TH FLOOR | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 12 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 82%.
LGF TO FIFTEENTH FLOOR11%
| Activity | Progress |
|---|---|
| Excavation | 82% |
| Basement (if any) | 20% |
| Podiums (if any) | 0% |
| Plinth | 20% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
16-26 TH FLOOR0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
27-36TH FLOOR0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 12 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed468
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| LGF TO FIFTEENTH FLOOR | 75 | 120 | 195 |
| 16-26 TH FLOOR | 55 | 88 | 143 |
| 27-36TH FLOOR | 50 | 80 | 130 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Malwadkar Architects |
| Architect | ABA ARCHITECTS |
| Engineer | SIDDHESHWAR KULKARNI |
| Chartered Accountant | SSAP & ASSOCIATES LLP |
| Partner | Role in project |
|---|---|
| GOEL GANGA CONSTRUCTIONS AND REAL ESTATE PVT LTD | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000167566 | Marvel Asta Constructions LLP Through its Partner Mr. Vishwajeet Subhash Jhavar | One Boat Club Construction and Real Estate Pvt Ltd Through its Director Mr. Atul Jaiprakash Goel | 23/09/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Jan 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2030
Documents filed48
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| OtherFile: One boat new letter WITHDRAWAL.pdf | 12 Feb 2023 |
| OtherFile: One Boat Club Constructions DEREGESTRATION.pdf | 7 Feb 2023 |
| OtherFile: 16012023 Rera Withdrawal letter.pdf | 18 Jan 2023 |
| OtherFile: 16012023 Rera withdrawal applocation.pdf | 18 Jan 2023 |
| OtherFile: UNDERTAKING - ONE BOAT CLUB.pdf | 18 Jan 2023 |
| OtherFile: BOAT CLUB RERA WITHDRAWAL.pdf | 26 Oct 2022 |
| CERSAI detailsFile: CERSAI REPORT BOAT CLUB 2022.pdf | 2 Mar 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: THE HQ NEW FORMAT ENGINEER CERTIFICATE FORM 2.pdf | 20 Feb 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: THE HQ NEW FORMAT FORM 2 A.pdf | 20 Feb 2022 |
| Layout approvalFile: BOAT CLUB DRG 1 MB.pdf | 19 Feb 2022 |
| Building plan approvalFile: BOAT CLUB DRG 1 MB.pdf | 19 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: BOAT CLUB DRG 1 MB.pdf | 19 Feb 2022 |
| Building Plan Approval (IOD)File: BOAT CLUB DRG 1 MB.pdf | 19 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 19 Feb 2022 |
| Declaration about Commencement CertificateFile: One Boat Club Format D CC.pdf | 19 Feb 2022 |
| Declaration in FORM BFile: FORM B One Boat Club 1MB.pdf | 19 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE ONE BOAT CLUB_compressed.pdf | 19 Feb 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: THE HQ FORM 2 A QUALITY.pdf | 19 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: One Boat Club Disclosure of sold inventory_compressed.pdf | 19 Feb 2022 |
| Certificates of CA (Form 3)File: ONE BOAT CLUB RERA FORM 3 31122021.pdf | 19 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: The HQForm 5 31032019.pdf | 19 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: The HQ Form 531032020.pdf | 19 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: The HQ Form 5 31032021.pdf | 19 Feb 2022 |
| Proforma of Allotment letterFile: Boat Club Agreement RESIDENTIAL R0_compressed.pdf | 19 Feb 2022 |
| Proforma of Allotment letterFile: THE HQ - AGR DRAFT updated on rera on 4-1-2020.pdf | 4 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BOAT CLUB ARCHITECT CERTIFICATE.pdf | 22 Aug 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BOAT CLUB.pdf | 16 Aug 2019 |
| Form 2AFile: THE HQ FORM 2 A -.pdf | 11 Jul 2019 |
| Proforma of Allotment letterFile: BOAT CLUB Agreement- Commercial 10062009.pdf | 11 Jun 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: boat club architect certificate COMMERCIAL.pdf | 18 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE BOAT CLUB COMMERCIAL UPTO 31-3-2019.pdf | 18 Apr 2019 |
| Proforma of Allotment letterFile: BOAT CLUB agreement- Commercial- 17-4-2019.pdf | 18 Apr 2019 |
| Layout approvalFile: MD DRAWING.pdf | 5 Apr 2019 |
| Copy of Layout Approval (in case of layout)File: MD DRAWING.pdf | 5 Apr 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE BOAT CLUB.pdf | 5 Apr 2019 |
| Certificates of CA (Form 3)File: CA CERTIFICATE BOAT CLUB_Compressed.pdf | 18 Jan 2019 |
| Building plan approvalFile: IOD DECLARATION.pdf | 7 Jan 2019 |
| Building Plan Approval (IOD)File: IOD DECLARATION.pdf | 7 Jan 2019 |
| Certificates of CA (Form 5)File: FORM 5.pdf | 7 Jan 2019 |
| Proforma of Allotment letterFile: AGREEMENT BOAT CLUB.pdf | 7 Jan 2019 |
| OtherFile: SELF DECLARATION.pdf | 7 Jan 2019 |
| Layout approvalFile: Boat Club Road LAYOUT.pdf | 5 Jan 2019 |
| PAN CardFile: GG CONSTRUCTIONS AND REAL ESTATE PAN.pdf | 5 Jan 2019 |
| Copy of the legal title reportFile: TITLE REPORT.pdf | 5 Jan 2019 |
| Details of encumbrancesFile: Encumbrance certificate-28-12-2018.pdf | 5 Jan 2019 |
| Copy of Layout Approval (in case of layout)File: Boat Club Road LAYOUT.pdf | 5 Jan 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: COMENCEMENT CERTIFICATE 1.pdf | 5 Jan 2019 |
| Declaration in FORM BFile: FORM B BOAT CLUB.pdf | 5 Jan 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 48 filed documents as one ZIP, foldered, with a manifest
Keep ONE BOAT CLUB on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SANGAMWADI PUNE13,700+ in Pune
Filed coordinates, straight-line distance. 93 registered projects within 2 km.
HUES OF SKY
Bramhacorp Limited
Birla Punya Phase II
Birla Estates Private Limited
Birla Punya Phase 1
Birla Estates Private Limited
BOULEVARD TOWER A2
Bramhacorp Limited
One Place-Bund Garden Road
TOPSPACE LANDMARKS LLP
Eternia Phase 2
VENTURESPRO PROJECTS LLP
Builder: GOEL GANGA CONSTRUCTIONS AND REAL ESTATE PVT LTD
GOEL GANGA CONSTRUCTIONS AND REAL ESTATE PVT LTD has 1 registration on MahaRERA, including ONE BOAT CLUB. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that ONE BOAT CLUB shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ONE BOAT CLUB is delayed beyond 31 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ONE BOAT CLUB?
The registered promoter entity is GOEL GANGA CONSTRUCTIONS AND REAL ESTATE PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ONE BOAT CLUB?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ONE BOAT CLUB?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ONE BOAT CLUB?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ONE BOAT CLUB?
The professionals named in the filing: Architect: Malwadkar Architects; Architect: ABA ARCHITECTS; Engineer: SIDDHESHWAR KULKARNI; Chartered Accountant: SSAP & ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ONE BOAT CLUB?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback