ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / OMKARESHWAR CHS PROP

Completed No litigation declared Residential / Group Housing project

OMKARESHWAR CHS PROP

By NEW LAXMI ENTERPRISES

RG-MH-24034 · RERA P51800012099 · Last updated on MahaRERA portal: 7 Jul 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
2 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
0Complaints at MahaRERAon this registration
Jump to the 33 documents Report an error

OMKARESHWAR CHS PROP is a Residential / Group Housing project by NEW LAXMI ENTERPRISES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012099 on 1 Sep 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameOMKARESHWAR CHS PROP
  • TypeResidential / Group Housing
  • Location
    • Andheri
    • Mumbai Suburban
    • 400060
  • Pincode400060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012099
  • ReraGenie IDRG-MH-24034

Builder

  • NameNEW LAXMI ENTERPRISES
  • Entity typePartnership
  • PartnersRAJENDRA NARAYAN RANE, SUNIL NARAYAN RANE, VIJAY NARAYAN RANE, PRASHANT NARAYAN RANE, MAHESH NARAYAN RANE, ANIL NARAYAN RANE
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects2 →

Key dates

this monthRegisteredSep 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Sep 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed33 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OMKARESHWAR TOWERNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

OMKARESHWAR TOWER: 53% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor70%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered8
Open Space2

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area554 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1367.76
Proposed, not sanctioned1,368 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHANTA MANGESH CHS HINDU FRIENDS SOCIETY ROAD JOGESHWARI EAST MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSACHIN JADHAV
EngineerHIMANSHU M RAJE
PartnerRole in project
NEW LAXMI ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005280Dec 2019 → Dec 2020

Reason as filed by the promoterStructure standing on setback area was compensated to one of the tenant earlier as per the consent term filled in suit but there were third party rights created by the Tenant in the said structure. Due to the same the demolition of said structure was obstructed. Later on the structure was demolished by Dy Collector by following due process of law. Only after the demolition and clearance of the Structure on set back area further CC could be obtained on March 2019 which delayed the progress on site for three years.

Litigation declared5

CaseCourtStatus
2344/2014/2014CITY CIVIL COURTDisposed Off
2345/2014/2014CITY CIVIL COURTDisposed Off
2742/2014/2014CITY CIVIL COURTDisposed Off
877/2015/2015CITY CIVIL COURTDisposed Off
772/2015/2015CITY CIVIL COURTDismissed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Jul 2023

Documents filed33

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf7 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full OC.pdf3 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate_compressed.pdf8 Mar 2021
Proforma of Allotment letterFile: Agreement.pdf21 Nov 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf31 Jul 2017
Building plan approvalFile: IOD.pdf30 Jul 2017
Building plan approvalFile: IOD2.pdf30 Jul 2017
Building plan approvalFile: IOD3.pdf30 Jul 2017
Layout approvalFile: lAYOUT.pdf30 Jul 2017
Layout approvalFile: LAYOUTA.pdf30 Jul 2017
Layout approvalFile: LAYOUTB.pdf30 Jul 2017
Details of encumbrancesFile: Format-Encumbrances.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: lAYOUT.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUTA.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUTB.pdf30 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf30 Jul 2017
Building Plan Approval (IOD)File: IOD2.pdf30 Jul 2017
Building Plan Approval (IOD)File: IOD3.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf30 Jul 2017
Certificates of CA (Form 3)File: Format- Form 3 under Compilation.pdf30 Jul 2017
Proforma of Allotment letterFile: Format- Draft Agreement for Sale.pdf30 Jul 2017
PAN CardFile: pan1.pdf29 Jul 2017
Copy of the legal title reportFile: t1.pdf29 Jul 2017
Copy of the legal title reportFile: t2.pdf29 Jul 2017
Copy of the legal title reportFile: t3.pdf29 Jul 2017
Copy of the legal title reportFile: t4.pdf29 Jul 2017
Copy of the legal title reportFile: t5.pdf29 Jul 2017
Copy of the legal title reportFile: t6.pdf29 Jul 2017
Declaration in FORM BFile: DECLARATION.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Untitled-11.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Untitled-12.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Untitled-13.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Untitled-14.pdf29 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
N G RANE SRA CHS LTDPLOT BEARING CTS NO 279A-2 RANE COMPOUND NATWAR NAGAR ROAD NO 1 JOGESHWARI EAST MUMBAI40CompletedJan 2017Jan 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep OMKARESHWAR CHS PROP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri6,700+ in Mumbai Suburban

2 kmOMKARESHWAR CHS PROPCompleted 88Lapsed / revoked 41Abeyance 1Other 98Dot size: filed unitsN

Filed coordinates, straight-line distance. 228 registered projects within 2 km.

Builder: NEW LAXMI ENTERPRISES

NEW LAXMI ENTERPRISES has 2 registrations on MahaRERA, including OMKARESHWAR CHS PROP and Ranes Trimurti CHSL. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if OMKARESHWAR CHS PROP is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OMKARESHWAR CHS PROP?

The registered promoter entity is NEW LAXMI ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OMKARESHWAR CHS PROP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for OMKARESHWAR CHS PROP?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OMKARESHWAR CHS PROP?

The professionals named in the filing: Architect: SACHIN JADHAV; Engineer: HIMANSHU M RAJE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OMKARESHWAR CHS PROP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OMKARESHWAR CHS PROP. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OMKARESHWAR CHS PROP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.