ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / OM VRUNDAVAN

Completed No litigation declared Residential / Group Housing project

OM VRUNDAVAN

By RANVEER BUILDERS AND DEVLOPERS

RG-MH-00707 · RERA P51500003613 · Last updated on MahaRERA portal: 15 Apr 2021

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
16 of 33Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 90%
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

OM VRUNDAVAN is a Residential / Group Housing project by RANVEER BUILDERS AND DEVLOPERS in Aurangabad, Maharashtra, registered with MahaRERA as P51500003613 on 6 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameOM VRUNDAVAN
  • TypeResidential / Group Housing
  • Location
    • Tisgaon
    • Aurangabad
    • 431102
  • Pincode431102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500003613
  • ReraGenie IDRG-MH-00707

Builder

  • NameRANVEER BUILDERS AND DEVLOPERS
  • Entity typePartnership
  • PartnersPUNJAB SHIVAJIRAO TAUR, GORAKHNATH PARSHURAM SOLANKE

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings3 building records
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING D ENA50000
BUILDING B CNA20000
BUILDING ANA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 15 Apr 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

BUILDING D E75%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises69%
Sanitary Fittings within the flats / premises58%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks72%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
BUILDING B C82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING A68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 15 Apr 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered32
BuildingClosed/CoveredTotal
BUILDING D E1717
BUILDING B C1111
BUILDING A44

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
KISHOR BALARAM BEDEKARAurangabad (M Corp.)Aurangabad

Approvals and building plan

Permissible FSI2821.96
Proposed, not sanctioned2,822 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAMARPREET CHOWK,AURANGABAD

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRADEEP MOTE
EngineerABHAY PATIL
PartnerRole in project
RANVEER BUILDERS AND DEVLOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500005283Dec 2019 → Dec 2020

Reason as filed by the promoterThe Registered project is having Building and Row House structures and some Row House, out of which the promoter have completed all work except some finishing work is under process. Presently partial development work of open space is only pending.The promoter have already taken part completion of the project vide Part Occupancy Certificate No. CIDCO/ATPO/AUR(WLJ)/2017(OC)/30 dated 23/08/2017 from CIDCO and handed over possession to the buyers of the units. Balance work of the project is proposed to be completed within applied extension.We undertake to complete the project within applied extens

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 31 Dec 2019

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: DEC 19 FORM 3 - Om Vrundavan Ranveer Builders Developers.pdf15 Apr 2021
Certificates of CA (Form 3)File: JUN 20 FORM 3 - Om Vrundavan Ranveer Builders Developers - Copy.pdf15 Apr 2021
Certificates of CA (Form 3)File: SEP 20 FORM 3 - Om Vrundavan Ranveer Builders Developers - Copy - Copy.pdf15 Apr 2021
Certificates of CA (Form 3)File: SEP 20 FORM 3 - Om Vrundavan Ranveer Builders Developers - Copy - Copy.pdf15 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Ranveer Builders Developers 2017-18 FORM 5.pdf7 Oct 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ranveer-builders 2018-19.pdf7 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RBD ACR 06-07-2018.pdf31 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RBD ARC 04-10-2018.pdf31 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RBD ACR 08-01-2019.pdf31 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RBD ACR 05-04-2019.pdf31 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RBD ACR 02-07-2019.pdf31 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RBD ACR 01-10-2019.pdf31 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RBD ENG 05-04-2018.pdf31 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RBD ENG 01-10-2018.pdf31 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RBD ENG 01-01-2019.pdf31 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RBD ENG 05-04-2019.pdf31 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RBD ENG 04-07-2019.pdf31 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RBD ENG 07-10-2019.pdf31 Dec 2019
Certificates of CA (Form 3)File: om Vrundavan CA certificate 31-03-18.pdf31 Dec 2019
Certificates of CA (Form 3)File: om vrundavan CA cerificate 30-06-18.pdf31 Dec 2019
Certificates of CA (Form 3)File: om vrundavan CA certificate 30-09-18.pdf31 Dec 2019
Certificates of CA (Form 3)File: om vrunadanvan CA certificate 31-12-18.pdf31 Dec 2019
Certificates of CA (Form 3)File: om vrundanvan CA certificate 31-03-19.pdf31 Dec 2019
Certificates of CA (Form 3)File: om vrundanvan CA certificate 30-6-19.pdf31 Dec 2019
Certificates of CA (Form 3)File: Om Vrundavan As on 30-09-2019.pdf31 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: RBD OC.pdf31 Dec 2019
Architect’s Certificate on Completion of Project (Form 4)File: RBD FORM 4.pdf31 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: OM VRUNDAVAN - ARCHITECT CERTIFICATE.pdf21 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ranveer Architect Letter.pdf21 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ranveer Architect Letter 2.pdf21 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: OM VRUNDAVAN - ENG CERTIFIFCATE.pdf21 Dec 2018
Certificates of CA (Form 3)File: Om Vrundavan.pdf30 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: OM VRUNDAVAN- ARCHI CERTIF - SEP 2017.pdf12 Dec 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 03 PAGES.pdf12 Dec 2017
Certificates of CA (Form 3)File: OM VRUNDAVAN- CA CERTIF - SEP 2017.pdf12 Dec 2017
Details of encumbrancesFile: encumbrance Ranveer.pdf30 Jul 2017
Declaration in FORM BFile: RANVEER FORM B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECH CERTIFICATE RANVEER.pdf30 Jul 2017
Certificates of CA (Form 3)File: rd1.pdf30 Jul 2017
Layout approvalFile: 29072017130849.pdf29 Jul 2017
Building plan approvalFile: 29072017130849.pdf29 Jul 2017
PAN CardFile: PAN.pdf29 Jul 2017
Copy of the legal title reportFile: New Doc 17.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 29072017130849.pdf29 Jul 2017
Building Plan Approval (IOD)File: 29072017130849.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 29072017130829.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: ATS-Ranveer-Om Vrundawan.pdf29 Jul 2017

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 24 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is completed

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep OM VRUNDAVAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tisgaon1,400+ in Aurangabad

2 kmOM VRUNDAVANCompleted 22Lapsed / revoked 9Other 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 46 registered projects within 2 km.

Builder: RANVEER BUILDERS AND DEVLOPERS

RANVEER BUILDERS AND DEVLOPERS has 1 registration on MahaRERA, including OM VRUNDAVAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if OM VRUNDAVAN is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OM VRUNDAVAN?

The registered promoter entity is RANVEER BUILDERS AND DEVLOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OM VRUNDAVAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for OM VRUNDAVAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OM VRUNDAVAN?

The professionals named in the filing: Architect: PRADEEP MOTE; Engineer: ABHAY PATIL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OM VRUNDAVAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OM VRUNDAVAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OM VRUNDAVAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.