Home / Browse projects / Mumbai Suburban, Maharashtra / OM PALACE

Registration lapsed No litigation declared Residential / Group Housing project

OM PALACE

By P. G. ENTERPRISES

RG-MH-11171 · RERA P51800002838 · Last updated on MahaRERA portal: 5 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 39 months past the filed date
  • 8 complaints at MahaRERA
  • Completion date moved by 49 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2023Possession promised39 months past this date
12 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 98%
8Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

OM PALACE is a Residential / Group Housing project by P. G. ENTERPRISES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002838 on 4 Aug 2017. Possession was promised by 31 Jul 2023 and is now 39 months past that date. The completion date has moved by 49 months from the original filing. 8 complaints are on record with the regulator.

At a glance

Project

  • NameOM PALACE
  • TypeResidential / Group Housing
  • Location
    • MITTAL COLLEGE ROAD
    • MALAD WEST
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002838
  • ReraGenie IDRG-MH-11171

Builder

  • NameP. G. ENTERPRISES
  • Entity typePartnership
  • PartnerBHAVESH NAVNITLAL SHAH
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

39 months past promisethis monthRegisteredAug 2017First promiseJun 2019Revised toJul 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Aug 2017
  • Promised completion31 Jul 2023
  • Revised completionRevised to 31 Jul 2023 (originally 30 Jun 2019)
  • Buildings2 building records
  • Documents filed86 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OM PALACENA230000
SNEHAL SADAN SRA CHSLNA280000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 5 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 98%.

OM PALACE68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SNEHAL SADAN SRA CHSL89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 5 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes40%
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable

Parking filed29

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots29
Open Space29
BuildingOpen SpaceTotal
OM PALACE2121
SNEHAL SADAN SRA CHSL88

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,584 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4678.82
Proposed, not sanctioned4,679 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchB N AGRAWAL MARKET SHYAMKAMAL TRADE CENTER VILE PARLE EAST MUMBAI 400057

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKAHAANPROJECTCONSULTANTS
PartnerRole in project
P. G. ENTERPRISES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012325Jun 2019 → Jul 2023

Reason as filed by the promoterWe are hereby explaining the delay in completion the project on time. The primary reasons of delay was non availability of the Staff due to COVID-19 pandemic and delay in obtaining approvals on-time for the Rehab Building and Sale Building. As well as we obtained Part OC for Rehab Building & handover the possession to Rehab Tenants. Now we are trying to Full OC of Rehab Building & Sale Building so we are seeking an extended date of completion of the project.

EXT51800001973Jun 2019 → Jun 2020

Reason as filed by the promoterDeclaration We are hereby explaining the delay in completion of the project on time. The primary reason of delay was obtaining approvals ontime for the Rehab Building and Sale Building. Enormous numbers of compliances, lengthy procedures for required permissions, unfavourable market conditions and non availability of the Staff due to National general elections attributed to this delay which was beyond our control.Hence we are seeking an extended date of completion of the project.

Litigation declared1

CaseCourtStatus
1266/2016CITY CIVIL COURT DINDOSHICHAMBER SUMMONS ON BEHALF OF THE SLUM SOCIETY ADMITTED

Complaints filed with MahaRERA8

Case no.ComplainantRespondentFiled
CC006000000012519girish choprap g enterprises21/12/2017
CC006000000012532umma tekchandanip g enterprises21/12/2017
CC006000000044518Nimesh PandyaMukesh Makwana16/05/2018
CC006000000056599SMT.KAILASHGOURI G PUROHIT & MR.PRAGNESH G PUROHITBHAVESH.N.SHAH16/10/2018
CC006000000079452Ms. Mekhola GangulyMakwana Group09/06/2019
CC006000000196101Mekhola GangulyP. G. Enterprises22/02/2021
CC006000000195165Snehal Sadan SaleMakwana / P G06/12/2020
CC006000000209617Mr Suresh R Shettyar and Mrs Surya S ShettyarP G Enterprises04/01/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: P G Enterprises RERA Form 5 2023-2024.pdf5 Dec 2024
Declaration about Commencement CertificateFile: CC Declaration.PDF18 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate.PDF18 Aug 2022
Disclosure of sold/ booked inventoryFile: Sold-Unsold List.PDF18 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Certificate.pdf18 Aug 2022
Certificates of CA (Form 3)File: PG Enterprises.PDF26 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: P G Engineers.PDF24 Oct 2020
Certificates of CA (Form 3)File: CA Certificate P G Enterprises.PDF24 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect From P G 30092020.PDF3 Oct 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2.PDF21 Aug 2020
Certificates of CA (Form 3)File: Certificate of CA Form 3.PDF21 Aug 2020
Certificates of CA (Form 5)File: Form 5 of RERA 2018-2019- PG.pdf12 Jul 2019
OtherFile: Part Occupation Permission.PDF26 Jun 2019
Certificates of CA (Form 3)File: CA CERTIFICATE 31032019.PDF23 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 31032019.PDF17 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31032019.PDF17 Apr 2019
Certificates of CA (Form 3)File: CA CERTIFICATE 31032019.PDF17 Apr 2019
Details of encumbrancesFile: 1.PDF2 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF1 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF1 Dec 2018
Certificates of CA (Form 3)File: CA Certificate.PDF1 Dec 2018
Certificates of CA (Form 3)File: CA Certificate.PDF1 Dec 2018
Details of encumbrancesFile: Encumberance.PDF11 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.PDF24 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.PDF24 Apr 2018
Certificates of CA (Form 3)File: CERTIFICATE OF CA.PDF24 Apr 2018
Building plan approvalFile: IOA.PDF23 Jan 2018
Building plan approvalFile: IOA.PDF23 Jan 2018
Building plan approvalFile: IOA.PDF23 Jan 2018
Building plan approvalFile: Layout Plan 1.pdf23 Jan 2018
Building plan approvalFile: Ground Floor Plan 2.pdf23 Jan 2018
Building plan approvalFile: Floor Plan 3.pdf23 Jan 2018
Building plan approvalFile: Typical Floor Plan 4.pdf23 Jan 2018
Building plan approvalFile: Refuge Floor Plan 5.pdf23 Jan 2018
Building plan approvalFile: Section Plan 6.pdf23 Jan 2018
Building Plan Approval (IOD)File: IOA.PDF23 Jan 2018
Building Plan Approval (IOD)File: IOA.PDF23 Jan 2018
Building Plan Approval (IOD)File: IOA.PDF23 Jan 2018
Building Plan Approval (IOD)File: Layout Plan 1.pdf23 Jan 2018
Building Plan Approval (IOD)File: Ground Floor Plan 2.pdf23 Jan 2018
Building Plan Approval (IOD)File: Floor Plan 3.pdf23 Jan 2018
Building Plan Approval (IOD)File: Typical Floor Plan 4.pdf23 Jan 2018
Building Plan Approval (IOD)File: Refuge Floor Plan 5.pdf23 Jan 2018
Building Plan Approval (IOD)File: Section Plan 6.pdf23 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: Rehab CC.pdf23 Jan 2018
Commencement Certificates / NA Order for plotted developmentFile: Sale CC.pdf23 Jan 2018
Building plan approvalFile: Rehab Ground Floor Plan.pdf26 Jul 2017
Building plan approvalFile: Rehab Typical Floor Plan 1.pdf26 Jul 2017
Building plan approvalFile: Sale Typical Floor Plan 2.pdf26 Jul 2017
Building plan approvalFile: Sale Typical Floor Plan 3.pdf26 Jul 2017
Building plan approvalFile: Sale Plot Area Statement.pdf26 Jul 2017
Building plan approvalFile: Sale Section Plan.pdf26 Jul 2017
Building plan approvalFile: Sale Section Plan.pdf26 Jul 2017
Building plan approvalFile: Sale Typical Floor Plan 1.pdf26 Jul 2017
Building plan approvalFile: Rehab Typical Floor Plan 2.pdf26 Jul 2017
Building plan approvalFile: Rehab Plot Area Statement.pdf26 Jul 2017
Building plan approvalFile: Rehab Typical Floor Plan 5.pdf26 Jul 2017
Building plan approvalFile: Rehab Section Plan.pdf26 Jul 2017
Building plan approvalFile: Rehab Typical Floor Plan 3.pdf26 Jul 2017
Building plan approvalFile: Rehab Typical Floor Plan 4.pdf26 Jul 2017
Building plan approvalFile: Sale Ground Floor Plan.pdf26 Jul 2017
Layout approvalFile: Copy of Layout Approval.pdf26 Jul 2017
PAN CardFile: PANCARD.pdf26 Jul 2017
Copy of the legal title reportFile: Legal Title Report.pdf26 Jul 2017
Details of encumbrancesFile: Details of encumbrances.PDF26 Jul 2017
Copy of Layout Approval (in case of layout)File: Copy of Layout Approval.pdf26 Jul 2017
Building Plan Approval (IOD)File: Rehab Ground Floor Plan.pdf26 Jul 2017
Building Plan Approval (IOD)File: Rehab Plot Area Statement.pdf26 Jul 2017
Building Plan Approval (IOD)File: Rehab Typical Floor Plan 1.pdf26 Jul 2017
Building Plan Approval (IOD)File: Rehab Typical Floor Plan 2.pdf26 Jul 2017
Building Plan Approval (IOD)File: Rehab Typical Floor Plan 5.pdf26 Jul 2017
Building Plan Approval (IOD)File: Rehab Section Plan.pdf26 Jul 2017
Building Plan Approval (IOD)File: Rehab Typical Floor Plan 3.pdf26 Jul 2017
Building Plan Approval (IOD)File: Rehab Typical Floor Plan 4.pdf26 Jul 2017
Building Plan Approval (IOD)File: Sale Ground Floor Plan.pdf26 Jul 2017
Building Plan Approval (IOD)File: Sale Plot Area Statement.pdf26 Jul 2017
Building Plan Approval (IOD)File: Sale Section Plan.pdf26 Jul 2017
Building Plan Approval (IOD)File: Sale Section Plan.pdf26 Jul 2017
Building Plan Approval (IOD)File: Sale Typical Floor Plan 1.pdf26 Jul 2017
Building Plan Approval (IOD)File: Sale Typical Floor Plan 2.pdf26 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 49 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep OM PALACE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALAD WEST6,700+ in Mumbai Suburban

2 kmOM PALACECompleted 140Lapsed / revoked 84Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 376 registered projects within 2 km.

Builder: P. G. ENTERPRISES

P. G. ENTERPRISES has 2 registrations on MahaRERA, including OM PALACE and P G GARDEN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that OM PALACE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if OM PALACE is delayed beyond 31 Jul 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OM PALACE?

The registered promoter entity is P. G. ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OM PALACE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against OM PALACE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for OM PALACE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OM PALACE?

The professionals named in the filing: Architect: KAHAANPROJECTCONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OM PALACE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OM PALACE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OM PALACE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.