OM PALACE
RG-MH-11171 · RERA P51800002838 · Last updated on MahaRERA portal: 5 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 39 months past the filed date
- 8 complaints at MahaRERA
- Completion date moved by 49 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OM PALACE is a Residential / Group Housing project by P. G. ENTERPRISES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002838 on 4 Aug 2017. Possession was promised by 31 Jul 2023 and is now 39 months past that date. The completion date has moved by 49 months from the original filing. 8 complaints are on record with the regulator.
At a glance
Project
- NameOM PALACE
- TypeResidential / Group Housing
- Location
- MITTAL COLLEGE ROAD
- MALAD WEST
- Borivali
- Mumbai Suburban
- 400064
- Pincode400064
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800002838
- ReraGenie IDRG-MH-11171
Builder
- NameP. G. ENTERPRISES
- Entity typePartnership
- PartnerBHAVESH NAVNITLAL SHAH
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Aug 2017
- Promised completion31 Jul 2023
- Revised completionRevised to 31 Jul 2023 (originally 30 Jun 2019)
- Buildings2 building records
- Documents filed86 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| OM PALACE | NA | 23 | 0 | 0 | 0 | 0 |
| SNEHAL SADAN SRA CHSL | NA | 28 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 5 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 98%.
OM PALACE68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SNEHAL SADAN SRA CHSL89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 98% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 5 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 40% |
| Aggregate area of recreational Open Space | Yes | 50% |
| Open Parking | No | Not applicable |
Parking filed29
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| OM PALACE | 21 | 21 |
| SNEHAL SADAN SRA CHSL | 8 | 8 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KAHAANPROJECTCONSULTANTS |
| Partner | Role in project |
|---|---|
| P. G. ENTERPRISES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe are hereby explaining the delay in completion the project on time. The primary reasons of delay was non availability of the Staff due to COVID-19 pandemic and delay in obtaining approvals on-time for the Rehab Building and Sale Building. As well as we obtained Part OC for Rehab Building & handover the possession to Rehab Tenants. Now we are trying to Full OC of Rehab Building & Sale Building so we are seeking an extended date of completion of the project.
Reason as filed by the promoterDeclaration We are hereby explaining the delay in completion of the project on time. The primary reason of delay was obtaining approvals ontime for the Rehab Building and Sale Building. Enormous numbers of compliances, lengthy procedures for required permissions, unfavourable market conditions and non availability of the Staff due to National general elections attributed to this delay which was beyond our control.Hence we are seeking an extended date of completion of the project.
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 1266/2016 | CITY CIVIL COURT DINDOSHI | CHAMBER SUMMONS ON BEHALF OF THE SLUM SOCIETY ADMITTED |
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000012519 | girish chopra | p g enterprises | 21/12/2017 |
| CC006000000012532 | umma tekchandani | p g enterprises | 21/12/2017 |
| CC006000000044518 | Nimesh Pandya | Mukesh Makwana | 16/05/2018 |
| CC006000000056599 | SMT.KAILASHGOURI G PUROHIT & MR.PRAGNESH G PUROHIT | BHAVESH.N.SHAH | 16/10/2018 |
| CC006000000079452 | Ms. Mekhola Ganguly | Makwana Group | 09/06/2019 |
| CC006000000196101 | Mekhola Ganguly | P. G. Enterprises | 22/02/2021 |
| CC006000000195165 | Snehal Sadan Sale | Makwana / P G | 06/12/2020 |
| CC006000000209617 | Mr Suresh R Shettyar and Mrs Surya S Shettyar | P G Enterprises | 04/01/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Jan 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed86
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: P G Enterprises RERA Form 5 2023-2024.pdf | 5 Dec 2024 |
| Declaration about Commencement CertificateFile: CC Declaration.PDF | 18 Aug 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate.PDF | 18 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold List.PDF | 18 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Certificate.pdf | 18 Aug 2022 |
| Certificates of CA (Form 3)File: PG Enterprises.PDF | 26 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: P G Engineers.PDF | 24 Oct 2020 |
| Certificates of CA (Form 3)File: CA Certificate P G Enterprises.PDF | 24 Oct 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect From P G 30092020.PDF | 3 Oct 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2.PDF | 21 Aug 2020 |
| Certificates of CA (Form 3)File: Certificate of CA Form 3.PDF | 21 Aug 2020 |
| Certificates of CA (Form 5)File: Form 5 of RERA 2018-2019- PG.pdf | 12 Jul 2019 |
| OtherFile: Part Occupation Permission.PDF | 26 Jun 2019 |
| Certificates of CA (Form 3)File: CA CERTIFICATE 31032019.PDF | 23 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 31032019.PDF | 17 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31032019.PDF | 17 Apr 2019 |
| Certificates of CA (Form 3)File: CA CERTIFICATE 31032019.PDF | 17 Apr 2019 |
| Details of encumbrancesFile: 1.PDF | 2 Feb 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF | 1 Dec 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF | 1 Dec 2018 |
| Certificates of CA (Form 3)File: CA Certificate.PDF | 1 Dec 2018 |
| Certificates of CA (Form 3)File: CA Certificate.PDF | 1 Dec 2018 |
| Details of encumbrancesFile: Encumberance.PDF | 11 May 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.PDF | 24 Apr 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.PDF | 24 Apr 2018 |
| Certificates of CA (Form 3)File: CERTIFICATE OF CA.PDF | 24 Apr 2018 |
| Building plan approvalFile: IOA.PDF | 23 Jan 2018 |
| Building plan approvalFile: IOA.PDF | 23 Jan 2018 |
| Building plan approvalFile: IOA.PDF | 23 Jan 2018 |
| Building plan approvalFile: Layout Plan 1.pdf | 23 Jan 2018 |
| Building plan approvalFile: Ground Floor Plan 2.pdf | 23 Jan 2018 |
| Building plan approvalFile: Floor Plan 3.pdf | 23 Jan 2018 |
| Building plan approvalFile: Typical Floor Plan 4.pdf | 23 Jan 2018 |
| Building plan approvalFile: Refuge Floor Plan 5.pdf | 23 Jan 2018 |
| Building plan approvalFile: Section Plan 6.pdf | 23 Jan 2018 |
| Building Plan Approval (IOD)File: IOA.PDF | 23 Jan 2018 |
| Building Plan Approval (IOD)File: IOA.PDF | 23 Jan 2018 |
| Building Plan Approval (IOD)File: IOA.PDF | 23 Jan 2018 |
| Building Plan Approval (IOD)File: Layout Plan 1.pdf | 23 Jan 2018 |
| Building Plan Approval (IOD)File: Ground Floor Plan 2.pdf | 23 Jan 2018 |
| Building Plan Approval (IOD)File: Floor Plan 3.pdf | 23 Jan 2018 |
| Building Plan Approval (IOD)File: Typical Floor Plan 4.pdf | 23 Jan 2018 |
| Building Plan Approval (IOD)File: Refuge Floor Plan 5.pdf | 23 Jan 2018 |
| Building Plan Approval (IOD)File: Section Plan 6.pdf | 23 Jan 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Rehab CC.pdf | 23 Jan 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Sale CC.pdf | 23 Jan 2018 |
| Building plan approvalFile: Rehab Ground Floor Plan.pdf | 26 Jul 2017 |
| Building plan approvalFile: Rehab Typical Floor Plan 1.pdf | 26 Jul 2017 |
| Building plan approvalFile: Sale Typical Floor Plan 2.pdf | 26 Jul 2017 |
| Building plan approvalFile: Sale Typical Floor Plan 3.pdf | 26 Jul 2017 |
| Building plan approvalFile: Sale Plot Area Statement.pdf | 26 Jul 2017 |
| Building plan approvalFile: Sale Section Plan.pdf | 26 Jul 2017 |
| Building plan approvalFile: Sale Section Plan.pdf | 26 Jul 2017 |
| Building plan approvalFile: Sale Typical Floor Plan 1.pdf | 26 Jul 2017 |
| Building plan approvalFile: Rehab Typical Floor Plan 2.pdf | 26 Jul 2017 |
| Building plan approvalFile: Rehab Plot Area Statement.pdf | 26 Jul 2017 |
| Building plan approvalFile: Rehab Typical Floor Plan 5.pdf | 26 Jul 2017 |
| Building plan approvalFile: Rehab Section Plan.pdf | 26 Jul 2017 |
| Building plan approvalFile: Rehab Typical Floor Plan 3.pdf | 26 Jul 2017 |
| Building plan approvalFile: Rehab Typical Floor Plan 4.pdf | 26 Jul 2017 |
| Building plan approvalFile: Sale Ground Floor Plan.pdf | 26 Jul 2017 |
| Layout approvalFile: Copy of Layout Approval.pdf | 26 Jul 2017 |
| PAN CardFile: PANCARD.pdf | 26 Jul 2017 |
| Copy of the legal title reportFile: Legal Title Report.pdf | 26 Jul 2017 |
| Details of encumbrancesFile: Details of encumbrances.PDF | 26 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Copy of Layout Approval.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Rehab Ground Floor Plan.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Rehab Plot Area Statement.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Rehab Typical Floor Plan 1.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Rehab Typical Floor Plan 2.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Rehab Typical Floor Plan 5.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Rehab Section Plan.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Rehab Typical Floor Plan 3.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Rehab Typical Floor Plan 4.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Sale Ground Floor Plan.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Sale Plot Area Statement.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Sale Section Plan.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Sale Section Plan.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Sale Typical Floor Plan 1.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Sale Typical Floor Plan 2.pdf | 26 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 86 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep OM PALACE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MALAD WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 376 registered projects within 2 km.
Ruparel Stardom
AMI MODISPACES LLP
Chandak Treesourus
CHANDAK REALTORS PRIVATE LIMITED
ANCHORPOINT AVIARA
YUKTI INFRAPROJECTS LLP
AURIS ILARIA TOWER A
TRANSCON-SHETH CREATORS PRIVATE LIMITED
ADHRIT
MUNDARA DEVELOPERS
IRENE WING B PHASE 1
Sheth Creators and Sunvision Private Limit
See every Mumbai Suburban project, with the district possession charts
Builder: P. G. ENTERPRISES
P. G. ENTERPRISES has 2 registrations on MahaRERA, including OM PALACE and P G GARDEN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that OM PALACE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if OM PALACE is delayed beyond 31 Jul 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OM PALACE?
The registered promoter entity is P. G. ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OM PALACE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against OM PALACE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for OM PALACE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OM PALACE?
The professionals named in the filing: Architect: KAHAANPROJECTCONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OM PALACE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback