Home / Browse projects / Thane, Maharashtra / Olive - Phase III - Pranjee Garden City

Registration lapsed No litigation declared Others project

Olive - Phase III - Pranjee Garden City

By Pranjee Properties Pvt. Ltd

RG-MH-28231 · RERA P51700025487 · Last updated on MahaRERA portal: 29 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 24 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
7 of 11Construction stages donefurthest along: Internal walls, 96%
56 of 172Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

Olive - Phase III - Pranjee Garden City is a Others project by Pranjee Properties Pvt. Ltd in Thane, Maharashtra, registered with MahaRERA as P51700025487 on 8 Jun 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 24 months from the original filing. 116 of the 172 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameOlive - Phase III - Pranjee Garden City
  • TypeOthers
  • Location
    • near ganesh ghat
    • Katrap
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700025487
  • ReraGenie IDRG-MH-28231

Builder

  • NamePranjee Properties Pvt. Ltd
  • Entity typeCompany
  • CINU70102MH2006PTC161302
  • Managing DirectorPrakash Sharma
  • Other registrations5 more →
  • Completed4 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

4 months past promisethis monthRegisteredJun 2020First promiseJun 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Jun 2020
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed79 files

Current status

67%116 of 172 units booked
97.2%Work done, per cost certificate

Figures as on 29 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OliveNA13121720172

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 96%.

Olive: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed98

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots98
Closed/Covered98

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,801 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Jul 2025
LandownerVillageDistrict
Pranjee Properties Pvt. Ltd.Greater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authorityKulgoan Badlapur Muncipal council
Permissible FSI9795.83
Proposed, not sanctioned7,738 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSion Trombay Road Branch, Shree Devakinandan Building, Next to Celebration Restaurant, Chembur, Mum
Estimated costRs 28.20 cr
Cost incurredRs 27.40 cr
Work done97.16%
BuildingWingEstimatedIncurred
OliveNARs 26.70 crRs 26.05 cr
-NARs 1.50 crRs 1.35 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArvind Mahtre
ArchitectSatish Oak
EngineerVIKAAS SHARMA
EngineerVaibhav kanase
Chartered AccountantShirish Pandit & Associates
Chartered AccountantAHIRE & ASSOCIATES
Chartered AccountantM D Deshpande & Co Chartered accountans
PartnerRole in project
Pranjee Properties Pvt. Ltd-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700024058Jun 2024 → Jun 2025

Reason as filed by the promoterAs it very well aware about bad situation/phase of Real Estate / Construction Industry, due to Covid 19 Pandemic and its after effects , which there has been drastically slow down in speed of construction throughout the industry, we are also facing same issues at our project too. We hereby request to please provide us extension of 12 months till 30th June, 25 for completion of all pending work and handover peaceful possession to customer in our project.

EA15072502070Jun 2024 → Dec 2025

Reason as filed by the promoterWe respectfully request an extension for the OLIVE - PHASE III - PRANJEE GARDEN CITY project. While construction is substantially complete and interior finishing works are currently in progress, we have encountered certain unanticipated site challenges and delays in obtaining statutory approvals required for securing the Occupancy Certificate (OC). These unforeseen factors have affected the final stages of the project timeline. Although we are actively addressing these issues and are optimistic about obtaining the OC within the next six months, we are seeking this extension as a precautionary

EA12122518659Jun 2024 → Jun 2026

Reason as filed by the promoterThe Promoter requests an extension for the project, as construction is nearly complete but certain site challenges and delays in obtaining approvals have caused unforeseen delays. The required compliances for securing the Occupancy Certificate (OC) and related NOCs are currently being completed, and the OC application is expected to be submitted around December. Additionally, during the previous extension cycle, a delay in processing caused the project to temporarily lapse, resulting in the halt of new-flat registrations on the portal and disrupting the project’s cash flow. Despite this setbac

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 May 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Nov 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Q4 .pdf29 Jun 2026
Withdrawal Update Form 2File: Form 2 - Q4 .pdf29 Jun 2026
Withdrawal Update Form 3File: Form 3 -Q4 -revised.pdf29 Jun 2026
Withdrawal Update Form 1File: Form 1 - Q4 .pdf29 May 2026
Withdrawal Update Form 2File: Form 2 - Q4 .pdf29 May 2026
Withdrawal Update Form 3File: Form 3 -Q4 -revised.pdf29 May 2026
Form 2A (FY 2024-2025)File: Form - 2 A.pdf17 Mar 2026
Withdrawal Update Form 1File: Olive Form 1 Dec-25.pdf13 Mar 2026
Withdrawal Update Form 2File: Olive Form 2 Dec-25.pdf13 Mar 2026
Withdrawal Update Form 3File: CA RERA Certificate Olive Oct-2025_11zon.pdf13 Mar 2026
Withdrawal Update Form 1File: Olive Form 1 Dec-25.pdf6 Mar 2026
Withdrawal Update Form 2File: Olive Form 2 Dec-25.pdf6 Mar 2026
Withdrawal Update Form 3File: CA RERA Certificate Olive Oct-2025_11zon.pdf6 Mar 2026
Form 5 (FY 2024-2025)File: PPPL_RERA_Form 5_FY 2024-25.pdf6 Mar 2026
Withdrawal Update Form 1File: 1 Architect’s Certificate Sept-2025.pdf2 Dec 2025
Withdrawal Update Form 2File: Form 2 September 25.pdf2 Dec 2025
Withdrawal Update Form 3File: Form 3 Sept.pdf2 Dec 2025
Building plan approvalFile: flat plan.pdf13 Nov 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Mar,25 - Olive.pdf19 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3, Rera Certificate Upto Dec 2024.pdf19 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rera Certificate 31st Mar'25.pdf19 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Olive Engineer's Certificate Mar 25.pdf19 Jun 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold - booked 310325 - Olive.pdf19 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Olive Engineer's Certificate Mar 25.pdf19 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Annual Report Statement.pdf19 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Olive Architect’s Certificate Sep 2024.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RERA Certificate upto Sept 2024.pdf13 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Olive Engineer's Certificate Sep 24.pdf13 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Olive Engineer's Certificate Sep 24.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Olive Engineer's Certificate Mar'24-Director attasted.pdf10 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: OlivevArchitect’s Certificate June'24)attasted by Director.pdf4 Jul 2024
Disclosure for secured/unsecured finance availed for the projectFile: Form - 2A (annexure C ) attasted by Director.pdf4 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold - booked Inventory - Olive.pdf4 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of intrest Other Real Estate - Olive.pdf4 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: RERE Certificate Olive Form 3 Mar'24 Director attasted.pdf4 Jul 2024
Declaration in FORM BFile: Declaration Form B.pdf26 Jun 2024
Details of encumbrances concerned to FinanceFile: Self Declaration.pdf14 Jun 2024
Details of encumbrances concerned to LegalFile: Self Declaration.pdf14 Jun 2024
Declaration about Commencement CertificateFile: Declaration about C C Certificate.pdf14 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Olive Engineer's Certificate Mar'24.pdf14 Jun 2024
CERSAI detailsFile: Annexure - A.pdf14 Jun 2024
Disclosure of sold/ booked inventoryFile: Sold and unsold Olive 310324.pdf14 Jun 2024
Proforma of Agreement for saleFile: finalAgreement phase 3 olive buiding.pdf14 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Certificate Form 3 311223.pdf20 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: PPPL_Form_5_FY_2022-23.pdf4 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Detail- Rera.pdf14 Dec 2023
Details of encumbrancesFile: Encumberance Certificate Phase - III Olive.pdf4 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Detail- Rera.pdf4 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate of Completion of Work - Olive Sept'23.pdf27 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Sept'23_0001.pdf27 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERE Certificate Olive Form 3.pdf27 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold unsold units.pdf21 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Certificate Olive Form 5.pdf13 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificate RERA PHASE-III-Olive-New Form-3.pdf9 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA architect Certificate Phase III Olive till Mar'22.pdf1 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE PHASE III Olive till'Mar'22.pdf1 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE PHASE III Olive mar-21 Compress.pdf25 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Olive March-21.pdf25 Jul 2022
Disclosure of sold/ booked inventoryFile: Declration Ph III Olive.pdf16 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf1 Jun 2020
Copy of the legal title reportFile: Title certificate.pdf22 May 2020
Layout approvalFile: Plan Copy 1.pdf12 Mar 2020
Building plan approvalFile: Plan Copy 1.pdf12 Mar 2020
Building plan approvalFile: Plan Copy 2.pdf12 Mar 2020
Building plan approvalFile: Plan Copy 3.pdf12 Mar 2020
Building plan approvalFile: Plan Copy 4.pdf12 Mar 2020
PAN CardFile: PAN CARD (3).pdf12 Mar 2020
Details of encumbrancesFile: Encumbrance Certificate.pdf12 Mar 2020
Copy of Layout Approval (in case of layout)File: Plan Copy 1.pdf12 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan Copy 1.pdf12 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan Copy 2.pdf12 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan Copy 3.pdf12 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan Copy 4.pdf12 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf12 Mar 2020
Declaration in FORM BFile: Form-B.pdf12 Mar 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 11 03 2020.pdf12 Mar 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf12 Mar 2020
Proforma of Allotment letterFile: allotment letter and agreement for sale.pdf12 Mar 2020
OtherFile: Declaration.pdf12 Mar 2020

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise3 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
PalmP51700004695Katrap, Thane-Aug 2017Certificate SignedMay 2021Late, Nov 2022
Pranjee Garden City Phase - IIPranjee Garden City Phase - II opp Ganesh Ghat Katrap Road Badlapur East 421503266-CompletedNov 2018Late, Sep 2019
Pranjee Marinaplot no. 1 and 2 opposite Bonkode lake Sector 13 Koparkhairne Navi Mumbai 40070953-CompletedDec 2017Sep 2017
Pranjee Garden City Phase - I extPranjee Garden City Phase - I Ext opp Ganesh Ghat Katrap Road Badlapur East 421503103-CompletedApr 2015Late, Oct 2015

How this compares with Thane

67%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Olive - Phase III - Pranjee Garden City on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Katrap7,600+ in Thane

2 kmOlive - Phase III - PranCompleted 203Lapsed / revoked 78Other 128Dot size: filed unitsN

Filed coordinates, straight-line distance. 409 registered projects within 2 km.

Builder: Pranjee Properties Pvt. Ltd

Pranjee Properties Pvt. Ltd has 6 registrations on MahaRERA, including Pranjee Garden City Phase -II and Palm. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Olive - Phase III - Pranjee Garden City shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Olive - Phase III - Pranjee Garden City is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Olive - Phase III - Pranjee Garden City?

The registered promoter entity is Pranjee Properties Pvt. Ltd, a company as per the filing. Its CIN U70102MH2006PTC161302 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Olive - Phase III - Pranjee Garden City?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Olive - Phase III - Pranjee Garden City?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Olive - Phase III - Pranjee Garden City?

The professionals named in the filing: Architect: Arvind Mahtre; Architect: Satish Oak; Engineer: VIKAAS SHARMA; Engineer: Vaibhav kanase; Chartered Accountant: Shirish Pandit & Associates; Chartered Accountant: AHIRE & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Olive - Phase III - Pranjee Garden City?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Olive - Phase III - Pranjee Garden City. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Olive - Phase III - Pranjee Garden City to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.