ReraGenieLog inGet a buyer report

Home / Browse projects / NUSSER HOUSE

Registered No litigation declared Residential / Group Housing project

NUSSER HOUSE

By DR. NARANJI MONJI VORA CHARITABLE TRUST

RG-MH-06982 · RERA P51900054975 · Last updated on MahaRERA portal: 12 Feb 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: .
Dec 2027Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Basement (if any), 99%
0Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

NUSSER HOUSE is a Residential / Group Housing project by DR. NARANJI MONJI VORA CHARITABLE TRUST in GIRGAON, 400004, registered with MahaRERA as P51900054975 on 21 Feb 2024. Possession is promised by 31 Dec 2027.

At a glance

Project

  • NameNUSSER HOUSE
  • TypeResidential / Group Housing
  • Location
    • MAMA PARMANAND MARG
    • GIRGAON
    • 400004
  • Pincode400004
  • RERA no.P51900054975
  • ReraGenie IDRG-MH-06982

Builder

  • NameDR. NARANJI MONJI VORA CHARITABLE TRUST
  • Entity typeTrust
  • TrusteesJUGAL KISHOR JAIN

Key dates

this monthRegisteredFeb 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Feb 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NUSSER HOUSENA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 99%.

NUSSER HOUSE: 39% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)99%
Podiums (if any)99%
Plinth99%
Stilt Floor0%
Slabs of Super Structure16%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area712 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI8797.41
Proposed, not sanctioned4,344 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOPERA HOUSE BRANCH Lamington Rd, Charni Road East, Opera House, Girgaon, Mumbai

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA SQAURE CONSULTANT
EngineerANAND KAMBLE
Chartered AccountantB N BHADRICHA & CO
PartnerRole in project
DR. NARANJI MONJI VORA CHARITABLE TRUST-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECHTS CERTIFICATE_LETTER HEAD 1.pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Naranji Monji Trust-.pdf12 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE_LETTER HEAD.pdf12 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEERS CERTIFICATE FOR QUALTIY ASSURANCE_LH.pdf12 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: CC_merged.pdf9 Feb 2024
Other - TechnicalFile: DocScanner Feb 8, 2024 4-52 PM.pdf8 Feb 2024
Layout approvalFile: GetUserDocumentFileContent.pdf9 Jan 2024
Copy of Layout Approval (in case of layout)File: GetUserDocumentFileContent.pdf9 Jan 2024
Declaration about Commencement CertificateFile: eclaaaa.pdf1 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ilovepdf_merged (34).pdf1 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bankkkkkk.pdf1 Jan 2024
Proforma of Agreement for saleFile: Model_AFS_in_English (3).pdf30 Nov 2023
Declaration in FORM BFile: Form B (3).pdf3 Nov 2023
Copy of the legal title reportFile: TC.pdf2 Nov 2023
Details of encumbrances concerned to FinanceFile: Finance Encumbrance Disclosure.pdf2 Nov 2023
Details of encumbrances concerned to FinanceFile: Legal Encumbrance Disclosure (1).pdf2 Nov 2023
Details of encumbrances concerned to LegalFile: Finance Encumbrance Disclosure.pdf2 Nov 2023
Details of encumbrances concerned to LegalFile: Legal Encumbrance Disclosure (1).pdf2 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Project Disclosure Letter.pdf2 Nov 2023
Proforma of Allotment letterFile: Allotment Letter - without deviation (1).pdf2 Nov 2023
Deviation Report with respect to Allotment letterFile: Allotment Letter Deviation Disclosure Letter.pdf2 Nov 2023
Deviation Report with respect to model copy of AgreementFile: AFS Deviation Disclosure Letter.pdf2 Nov 2023
CERSAI detailsFile: CERSAI_Search_Report_200285475229_For_Asset_Based_Search_01_11_2023_18_06_28_928.pdf1 Nov 2023
Building plan approvalFile: P_9287_2300628_IOD_SIGNED_23NOV2021.pdf31 Oct 2023
Building plan approvalFile: IOD DRAWING_23NOV2021.pdf31 Oct 2023
PAN CardFile: NMV_PAN CARD.pdf31 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: P_9287_2300628_IOD_SIGNED_23NOV2021.pdf31 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: IOD DRAWING_23NOV2021.pdf31 Oct 2023

Keep NUSSER HOUSE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GIRGAON

Builder: DR. NARANJI MONJI VORA CHARITABLE TRUST

DR. NARANJI MONJI VORA CHARITABLE TRUST has 1 registration on MahaRERA, including NUSSER HOUSE. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if NUSSER HOUSE is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NUSSER HOUSE?

The registered promoter entity is DR. NARANJI MONJI VORA CHARITABLE TRUST, a trust as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NUSSER HOUSE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NUSSER HOUSE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NUSSER HOUSE?

The professionals named in the filing: Architect: A SQAURE CONSULTANT; Engineer: ANAND KAMBLE; Chartered Accountant: B N BHADRICHA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NUSSER HOUSE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NUSSER HOUSE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NUSSER HOUSE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.