Home / Browse projects / Dakshina Kannada, Karnataka / NORTHERNSKY TRANQUILLO

Registration approved No litigation declared Residential/Group Housing project

NORTHERNSKY TRANQUILLO

By M/S. JV BUILDERS

RG-KA-60258 · RERA PRM/KA/RERA/1257/334/PR/260925/008122 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2031Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 60%
31 of 56Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 97 documents Report an error

NORTHERNSKY TRANQUILLO is a Residential/Group Housing project by M/S. JV BUILDERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/260925/008122 on 26 Sep 2025. Possession is promised by 31 Dec 2031. 25 of the 56 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameNORTHERNSKY TRANQUILLO
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575006
  • Pincode575006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/260925/008122
  • ReraGenie IDRG-KA-60258

Builder

  • NameM/S. JV BUILDERS
  • Entity typeProprietorship
  • GSTIN29ADPPD6279E1Z6
  • Authorized SignatoryDHEERAJ AMIN
  • Declared earlier projects2 →

Key dates

this monthRegisteredSep 2025PromisedDec 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 Sep 2025
  • Promised completion31 Dec 2031
  • Revised completionNone
  • Buildings1 building record
  • Documents filed97 files

Current status

45%25 of 56 units booked
36.4%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRANQUILO---56056

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 60%.

Building: 53% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work60%
Foundation footing work60%
Upto Plinth Level60%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)60%
Retaining wall (All types)60%
RCC or MS Framed structure50%
Masonry Construction50%
Plastering inside , outside & Ceiling50%
Joinery: Doors, Windows, Ventilators etc50%
Basic work of Water supply, Sanitary and Electrification50%
Dadoing, Skirting, Flooring, Tiles work (All types)50%
Railing and Grill fixing50%
Electrification, Water supply and Sanitary Finishing50%
Painting50%
Fire prevention and fire fighting fitting and fixture with network50%
Weather Proof work(tile,concrete)50%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work50%
Internal and External work including landscapes as per sanctioned drawings50%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes50%
Sewage and Drainage SystemYes50%
Water conservation/rain water harvesting/recharge of ground waterYes50%
Energy managementYes50%
Fire protection and fire safety requirementsYes50%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes50%
Storm water drainsYes50%
Use of renewable energyYes50%
Sewage Treatment Plant (STP)Yes50%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes50%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes50%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes50%
Piped GasYes50%
Water and SanitationYes50%
Air ConditioningNoNot applicable
StaircasesYes50%
LiftsYes50%
Corridor/LobbiesYes50%
Fire escapesYes50%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes50%
Outer WallYes50%
Open parking areasYes50%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes50%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,462 sq m
Named landowners1
LandownerVillageDistrict
DHEERAJ AMIN--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 31.05 cr
Cost incurredRs 11.31 cr
Spent of the estimate36.41%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 25.99 crRs 10.58 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 4.05 crRs 72.31 lakh
Administrative CostRs 52.00 lakh-
On-site expenditure-Consultants FeesRs 49.65 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHANA PAI
EngineerAnil K Hegde
Chartered AccountantCA. GOPALAKRISHNA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed97

As listed on the registration, under the names the promoter filed them with; the newest 80 of 97 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/260925/008122 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CATQL.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: ArcTql.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Eng certificate - tarnquillo.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: ca tranquillo (1).pdf15 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Tranquilo architect (1).pdf15 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENG - NS Tranquillo (1).pdf15 Jul 2026
Q4 2025-26 Water supply and sewage board15 Jul 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q4 2025-26 Fire and Safety15 Jul 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA certificate Q2 TRANQUILLO .pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: arc certificate tranquillo.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineers certificae - Ns Tranquillo.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA TRANQUILLO Q3.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: ARCHITECT CERTIFICATE - TRANQUILLO.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENG CERTIFICATE - TRANQUILLO.pdf15 Jan 2026
Form 1 CA CertificateFile: 1 Form 1 CA Certificate.pdf17 Sep 2025
BS with Schedules 21-22File: 2 BS with Schedules 21-22.pdf17 Sep 2025
BS with Schedules 22-23File: 2 BS with Schedules 22-23.pdf17 Sep 2025
BS with Schedules 23-24File: 2 BS with Schedules 23-24.pdf17 Sep 2025
P&L 21-22File: 2 P&L 21-22.pdf17 Sep 2025
P&L 22-23File: 2 P&L 22-23.pdf17 Sep 2025
P&L 23-24File: 2 P&L 23-24.pdf17 Sep 2025
Bank AffidavitFile: 3 Bank Affidavit.pdf17 Sep 2025
30% Current AccountFile: 4 30% Current Account.pdf17 Sep 2025
70% Designated AccountFile: 4 70% Designated Account.pdf17 Sep 2025
100% Collection AccountFile: 4 100% Collection Account.pdf17 Sep 2025
Barrio- Annual AuditFile: 6 Barrio- Annual Audit.pdf17 Sep 2025
West valley- Annual AuditFile: 6 West valley- Annual Audit.pdf17 Sep 2025
Single Layout PlanFile: 10 Single Layout Plan.pdf17 Sep 2025
Single Layout OrderFile: 11 Single Layout Order.pdf17 Sep 2025
ADLR SketchFile: 13 ADLR Sketch.pdf17 Sep 2025
commencement certificateFile: 17 commencement certificate.pdf17 Sep 2025
Details of source of Drinking waterFile: 21 Details of source of Drinking water.pdf17 Sep 2025
Proforma of AOSFile: 25 Proforma of AOS.pdf17 Sep 2025
Allotment LetterFile: 26 Allotment Letter.pdf17 Sep 2025
MESCOM nocFile: 28 MESCOM noc.pdf17 Sep 2025
Brief EstimationFile: 30 Brief Estimation.pdf17 Sep 2025
Sources of water supplyFile: 32 Sources of water supply.pdf17 Sep 2025
Building LicenseFile: 12 Building License.pdf17 Sep 2025
Approved Building PlanFile: 15 Approved Building Plan.pdf17 Sep 2025
Sectional Building PlanFile: 16 Sectional Building Plan.pdf17 Sep 2025
section 3 1 AffidavitFile: 27 section 3 1 Affidavit.pdf17 Sep 2025
land cost calculationFile: 31 land cost calculation.pdf17 Sep 2025
Master PlanFile: 18 Master Plan.pdf17 Sep 2025
MR H70 MainFile: 7 MR H70 Main.pdf17 Sep 2025
ECFile: 8 EC.pdf17 Sep 2025
Sources of Fund with Supporting DocFile: 5 Sources of Fund with Supporting Doc.pdf17 Sep 2025
Query Reply - NORTHERNSKY TRANQUILLOFile: Query Reply - NORTHERNSKY TRANQUILLO.pdf17 Sep 2025
RTC, survey 12/1B1(P)-
Mutation, survey 12/1B1(P)-
Encumbrance Certificate, survey 12/1B1(P)-
Conversion/Alienation Order, survey 12/1B1(P)-
Sale/Title/Gift Deed, survey 12/1B1(P)-
Khatha, survey 12/1B1(P)-
Registration CertificateFile: Trade License JVB 2025-26.pdf-
GST CertificateFile: GST Certificate JVB.pdf-
Certificate issued by CA Form 1File: 1 Form 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Annexure 61 Certificate issued by Architect Form 2.pdf-
Certificate issued by Engineer Form 3File: Annexure 60 Certificate issued by Engineer Form 3.pdf-
TDR Purchase Deed / Sale DeedFile: Annexure 58 TDR Sale deed and Utilisation.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Annexure 49 affidavit non litigation RERA.pdf-
Balance Sheet 2023 - 2024File: Annexure 70 JVB Balance Sheet FY 2023-24.pdf-
Balance Sheet 2022 - 2023File: Annexure 70 JVB Balance Sheet FY 2022-23.pdf-
Balance Sheet 2021 - 2022File: Annexure 70 JVB Balance Sheet FY 2021-22.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Annexure 71 JVB Profit & Loss FY 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Annexure 71 JVB Profit & Loss FY 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Annexure 71 JVB Profit & Loss FY 2021-22.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: Annexure 72 JVB ITR Ack FY 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: Annexure 72 JVB ITR Ack FY 2022-23.pdf-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Northernsky WESTVALLEYSy.No.60/1B 1A-P1 OF MARAKADA VILLAGE, BONDEL MANGALORECompleted-No date filed
NORTHERNSKY BARRIOSY.NO.105-2B1P1,105-2B,105-2B(P), Balmatta, Road, MANGALORECompleted-No date filed

How this compares with Dakshina Kannada

45%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep NORTHERNSKY TRANQUILLO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmNORTHERNSKY TRANQUILLOOther 93Dot size: filed unitsN

Filed coordinates, straight-line distance. 93 registered projects within 2 km.

Builder: M/S. JV BUILDERS

M/S. JV BUILDERS has 1 registration on RERA Karnataka, including NORTHERNSKY TRANQUILLO. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if NORTHERNSKY TRANQUILLO is delayed beyond 31 Dec 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NORTHERNSKY TRANQUILLO?

The registered promoter entity is M/S. JV BUILDERS, a proprietorship as per the filing. Its GSTIN 29ADPPD6279E1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NORTHERNSKY TRANQUILLO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NORTHERNSKY TRANQUILLO?

The professionals named in the filing: Architect: ARCHANA PAI; Engineer: Anil K Hegde; Chartered Accountant: CA. GOPALAKRISHNA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NORTHERNSKY TRANQUILLO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NORTHERNSKY TRANQUILLO. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NORTHERNSKY TRANQUILLO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.