Nisarg
RG-MH-15335 · RERA P52100024092 · Last updated on MahaRERA portal: 5 Apr 2023
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Nisarg is a Residential / Group Housing project by Nisarg Properties in Pune, Maharashtra, registered with MahaRERA as P52100024092 on 20 Jan 2020. The registration is recorded completed; possession was promised by 30 Jun 2022. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameNisarg
- TypeResidential / Group Housing
- Location
- Mohammadwadi Road
- Harihareshwar Nagar
- MOHAMMADWADI
- Haveli
- Pune
- 411028
- Pincode411028
- RERA no.P52100024092
- ReraGenie IDRG-MH-15335
Builder
- NameNisarg Properties
- Entity typePartnership
- PartnersSudhir Ganpat Sasane, Nitin Ganpat Sasane
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on20 Jan 2020
- Promised completion30 Jun 2022
- Revised completionRevised to 30 Jun 2022 (originally 30 Jun 2021)
- Buildings2 building records
- Documents filed28 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 3 | 0 | 0 | 0 | 0 |
| Wing B | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 5 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.
Wing A97%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Wing B97%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities16
As on 5 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Entrance Gate | Yes | 0% |
Parking filed8
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing A | 4 | 4 |
| Wing B | 4 | 4 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Nisarg Properties | Hadapsar | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Space Associates |
| Engineer | Abhijeet Landge |
| Chartered Accountant | D P Shewale & Co |
| Partner | Role in project |
|---|---|
| Nisarg Properties | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the lockdown and the restrictions imposed by the government time to time in the light of covid-19 pandemic situation, the project could not be completed within the stipulated period.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Jan 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 5 Apr 2023
Documents filed28
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full Occupancy Certificate.pdf | 5 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARICHITECT CERITFICATE_compressed.pdf | 4 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEER CERTIFICATE_compressed-1.pdf | 4 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: UNSOLD FLATS.pdf | 4 Jan 2022 |
| Declaration about Commencement CertificateFile: Declaraction of C C.pdf | 28 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A 19 - 20.pdf | 28 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A 20-21.pdf | 28 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 28 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form_51.pdf | 28 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form_5.pdf | 28 Jul 2021 |
| Layout approvalFile: 1.pdf | 14 Jan 2020 |
| Layout approvalFile: 2.pdf | 14 Jan 2020 |
| Layout approvalFile: 3.pdf | 14 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 14 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: 2.pdf | 14 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: 3.pdf | 14 Jan 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 14 Jan 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CA CERTIFICATE.pdf | 14 Jan 2020 |
| Proforma of Allotment letterFile: Booking Letter - Nisarg.pdf | 14 Jan 2020 |
| Building plan approvalFile: NA Order.pdf | 6 Jan 2020 |
| Copy of the legal title reportFile: Search Tittle Report.pdf | 6 Jan 2020 |
| Details of encumbrancesFile: Encumbrances Certificate.pdf | 6 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: NA Order.pdf | 6 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 6 Jan 2020 |
| Declaration in FORM BFile: 1 (5).pdf | 6 Jan 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 6 Jan 2020 |
| PAN CardFile: Nisarg PAN.pdf | 12 Dec 2019 |
| Proforma of Allotment letterFile: Agr - RERA - Draft_ - Nisarg Properties - 12-12-19.pdf | 12 Dec 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 28 filed documents as one ZIP, foldered, with a manifest
Keep Nisarg on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Harihareshwar Nagar13,700+ in Pune
Amanora Arbano Towers 73,74,75 and 76
City Corporation Limited
Astrana
Dilip Baburao Tupe
Leisure Town Phase 1
Sai Proviso Homes
ARV Newtown Phase III
Vedant Infracon
Kumar Parc Residences - A2
Kumar Properties Infratech Developers Pvt
Kumar Parc residences - A1
Kumar Properties Infratech Developers Pvt
Builder: Nisarg Properties
Nisarg Properties has 1 registration on MahaRERA, including Nisarg. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Nisarg is delayed beyond 30 Jun 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Nisarg?
The registered promoter entity is Nisarg Properties, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Nisarg?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Nisarg?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Nisarg?
The professionals named in the filing: Architect: Space Associates; Engineer: Abhijeet Landge; Chartered Accountant: D P Shewale & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Nisarg?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.