NIRMITI ELITE

By NIRMITI VASTU CREATION LLP

RG-MH-11964 · RERA P52100004507 · Last updated on MahaRERA portal: 15 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 39 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2023Possession promised39 months past this date
8 of 11Construction stages donefurthest along: Basement (if any), 0%
12 of 22Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

NIRMITI ELITE is a Others project by NIRMITI VASTU CREATION LLP in Pune, Maharashtra, registered with MahaRERA as P52100004507 on 9 Aug 2017. Possession was promised by 30 Jul 2023 and is now 39 months past that date. The completion date has moved by 12 months from the original filing. 10 of the 22 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameNIRMITI ELITE
  • TypeOthers
  • Location
    • Law College Road
    • Erandwana
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411004
  • Pincode411004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004507
  • ReraGenie IDRG-MH-11964

Builder

  • NameNIRMITI VASTU CREATION LLP
  • Entity typePartnership
  • GSTIN27AAKFN7894D1ZR
  • PartnersSHARMILA NITIN PURANIK, SUJATA SUNIL PURANIK
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

39 months past promisethis monthRegisteredAug 2017First promiseJul 2022Revised toJul 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion30 Jul 2023
  • Revised completionRevised to 30 Jul 2023 (originally 31 Jul 2022)
  • Buildings1 building record
  • Documents filed104 files

Current status

45%10 of 22 units booked

Figures as on 15 Mar 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NIRMITI ELITENA8651722

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

NIRMITI ELITE: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed28

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots28
Closed/Covered24
Open Space4

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area953 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
ANAND JOGPune (M Corp.)Pune
MEDHA JOGPune (M Corp.)Pune
JAYANT JOGPune (M Corp.)Pune
KANCHAN JOGPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI2053.61
Proposed, not sanctioned867 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAGDISH DESHPANDE
EngineerRAMESH CHINCHANI
Chartered AccountantCA PUSHPAK BOGATI
Chartered AccountantCA ABHIJIT MUNDADA
Chartered AccountantBogati & Co.
Chartered AccountantSPAK & Co.
PartnerRole in project
NIRMITI VASTU CREATION LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012452Jul 2022 → Jul 2023

Reason as filed by the promoterDue to Covid-19 pandemic which caused the slow-down in the construction industry we were not able to complete the project as per the stipulated time. Also, the rise in the cost of materials, labours, etc. made it difficult to complete the project in the decided cost for the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Nov 2021

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Jun 21.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 24.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 24.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 24.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 24.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 23.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 23.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 23.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 23.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 22.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 22.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 22.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 22.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 21.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 21.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 17.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 21.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 20.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 20.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 20.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 20.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 19.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 19.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 19.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 19.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 18.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Sep 18.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Jun 18.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Mar 18.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: Dec 17.pdf15 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 17.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 17.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 18.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: June 2018.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 18 (1).pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 18.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 19 (1).pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: June 2019.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 2019.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 2019.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 20 (1).pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 21.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 22 (1).pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 22.pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 23 (1).pdf4 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jun 23.pdf4 Mar 2025
Certificates of CA (Form 3)File: Form 3 June 2023.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Mar 2023.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Dec 2022.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Sep 2022.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 June 2022_11zon.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Mar 2022.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Dec 2021.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Sep 2021.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 June 2021_11zon.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Mar 2021_11zon.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Dec 2020_11zon.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Sep 2020_11zon.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 June 2020.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Mar 2020.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Dec 2019.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Sep 2019.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 June 2019.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Mar 2019.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Dec 2018.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Sep 2018.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 June 2018.pdf12 Dec 2024
Certificates of CA (Form 3)File: Form 3 Mar 2018.pdf11 Dec 2024
Certificates of CA (Form 3)File: Form 3 Dec 2017.pdf11 Dec 2024
Certificates of CA (Form 3)File: Form 3 Sep 2017.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Dec 2017_11zon.pdf7 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mar 2018.pdf7 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sep 2017_11zon.pdf7 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_Nirmiti Elite.pdf4 Mar 2024
Disclosure of sold/ booked inventoryFile: Nirmiti Elite_Inventory Details (1)_compressed.pdf8 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_Engineers Quality Assurance Certificate March 22.pdf4 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_Engineers Quality Assurance Certificate 2 M21.pdf12 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Nirmiti Elite_RERA Audit_FY 20-21.pdf30 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Nirmiti Elite_RERA Audit_FY 21-22.pdf30 Sep 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf17 Sep 2022

How this compares with Pune

45%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NIRMITI ELITE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Erandwana13,700+ in Pune

2 kmNIRMITI ELITECompleted 85Lapsed / revoked 32Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 269 registered projects within 2 km.

Builder: NIRMITI VASTU CREATION LLP

NIRMITI VASTU CREATION LLP has 2 registrations on MahaRERA, including NIRMITI 25 EAST and NIRMITI ELITE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that NIRMITI ELITE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NIRMITI ELITE is delayed beyond 30 Jul 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NIRMITI ELITE?

The registered promoter entity is NIRMITI VASTU CREATION LLP, a partnership as per the filing. Its GSTIN 27AAKFN7894D1ZR can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NIRMITI ELITE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NIRMITI ELITE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NIRMITI ELITE?

The professionals named in the filing: Architect: JAGDISH DESHPANDE; Engineer: RAMESH CHINCHANI; Chartered Accountant: CA PUSHPAK BOGATI; Chartered Accountant: CA ABHIJIT MUNDADA; Chartered Accountant: Bogati & Co.; Chartered Accountant: SPAK & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NIRMITI ELITE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NIRMITI ELITE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NIRMITI ELITE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.