Home / Browse projects / Ratnagiri, Maharashtra / NirmanSrushti

Registration lapsed No litigation declared Residential / Group Housing project

NirmanSrushti

By Nirmanshelters

RG-MH-29635 · RERA P52800028916 · Last updated on MahaRERA portal: 2 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
31 of 55Construction stages doneacross 5 buildings; furthest along: Staircases, 80%
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

NirmanSrushti is a Residential / Group Housing project by Nirmanshelters in Ratnagiri, Maharashtra, registered with MahaRERA as P52800028916 on 12 Apr 2021. Possession was promised by 30 Jun 2025 and is now 16 months past that date.

At a glance

Project

  • NameNirmanSrushti
  • TypeResidential / Group Housing
  • Location
    • Salvistop
    • Nachane (CT)
    • Ratnagiri
    • 415639
  • Pincode415639
  • RERA no.P52800028916
  • ReraGenie IDRG-MH-29635

Builder

  • NameNirmanshelters
  • Entity typePartnership
  • PartnersSachin Narayan Kamble, Vishal Shamsundar Nalawade, Vijay Prapatrao Patil, Ashish Harischandra Hatiskar, Chandan Appasaheb Khanvilkar, Sanket Prabhakar Kadam

Key dates

16 months past promisethis monthRegisteredApr 2021PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on12 Apr 2021
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings5 building records
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NirmanSrushti B1NA20000
NirmanSrushti B2NA20000
NirmanSrushti B3NA20000
NirmanSrushti B4NA20000
NirmanSrushti B5NA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 2 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

31 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Staircases, at 80%.

NirmanSrushti B164%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
NirmanSrushti B264%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
NirmanSrushti B364%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
NirmanSrushti B464%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
NirmanSrushti B549%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure4%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 2 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered1
Open Space4
BuildingClosed/CoveredOpen SpaceTotal
NirmanSrushti B1011
NirmanSrushti B2011
NirmanSrushti B3011
NirmanSrushti B4011
NirmanSrushti B5101

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,700 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4092.87
Proposed, not sanctioned2,915 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJaystamba, Ratnagiri

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Nirmanshelters-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Jul 2025

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Nirman Srushti Final OC.pdf2 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (31-03-2024)_compressed.pdf13 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC Nirman Srushti_compressed.pdf13 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: scan2974_compressed.pdf13 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: scan2976_compressed.pdf13 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: scan2977_compressed.pdf13 Jan 2025
Disclosure of sold/ booked inventoryFile: Nirman Srushti up to Sep 24 Sold List.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (31-03-2024)_compressed.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: Nirman Srushti up to Sep 24 Sold List.pdf26 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 September 2024 srushti (2)_compressed.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nirman Srushti Form 2- 1-10-2024.pdf25 Dec 2024
Building plan approvalFile: 1basement 1,2.pdf4 Dec 2024
Building plan approvalFile: 2 floor plan.pdf4 Dec 2024
Building plan approvalFile: 3 floorplan.pdf4 Dec 2024
Building plan approvalFile: 4 section.pdf4 Dec 2024
Building plan approvalFile: 5site plan and bunglowplan.pdf4 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: New Permission Srushti_compressed.pdf4 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: 5site plan and bunglowplan.pdf4 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: 4 section.pdf4 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: 3 floorplan.pdf4 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: 2 floor plan.pdf4 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: 1basement 1,2.pdf4 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirman Srushti Form 3 March 24_compressed.pdf23 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nirman Srushti FORM 2 - 1-04-2024.pdf23 Nov 2024
Disclosure of sold/ booked inventoryFile: Srushti March 2024 Sold Unit.pdf23 Nov 2024
Other - FinanceFile: Nirman Srushti Letter of Engagement_compressed.pdf23 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Nirman Srushti Form 5 March 24_compressed.pdf23 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nirman Srushti form 1 5-4-22.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Nirman Srushti 10-4-2022.pdf20 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 6-2-2020.pdf20 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 6-4-2022.pdf20 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 6-4-2023.pdf20 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 6-4-2024.pdf20 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Oct 2023 Nirman Srushti_compressed.pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: Nirman Srushti Sold Inventory.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Nirman Srushti Form 5 2021-22.pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nirman Srushti Form 2 Oct 2022.pdf3 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirman Srushti Form 3 on Sep 22 (1).pdf3 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Nirman Srushti_compressed_compressed.pdf24 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirman Srushti CA Certificate for RERA_compressed.pdf25 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nirman Srushti Form 2_compressed.pdf20 Sep 2021
Disclosure of sold/ booked inventoryFile: Nirman Srushti Sold Unsold list.pdf20 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirman Srushti CA certificate For RERA_compressed.pdf20 Sep 2021
Copy of the legal title reportFile: 2Title Report Nirman Srushti.pdf5 Apr 2021
PAN CardFile: ss Company Pan.pdf1 Apr 2021
Layout approvalFile: ss Plot Nakasha.pdf21 Mar 2021
Copy of Layout Approval (in case of layout)File: ss Plot Nakasha.pdf21 Mar 2021
Details of encumbrancesFile: ss Encumbrances Certificate.pdf20 Mar 2021
Declaration in FORM BFile: ss form B_compressed_compressed_compressed.pdf20 Mar 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC.pdf20 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf20 Mar 2021
Copy of the legal title reportFile: Nirman Srushti Title Search Report.pdf15 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_compressed_compressed_compressed_compressed.pdf15 Mar 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ss RERA Architect Certificate_compressed.pdf15 Mar 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QA1.pdf15 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: ss Annual Audit Report_compressed.pdf15 Mar 2021
Building plan approvalFile: ss permission plan.pdf14 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: ss permission plan.pdf14 Mar 2021
Proforma of Allotment letterFile: ss rera agreement updated format_compressed.pdf14 Mar 2021

How this compares with Ratnagiri

15%of Ratnagiri projects moved their completion datethis one has not
30%of Ratnagiri registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep NirmanSrushti on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Salvistop1,100+ in Ratnagiri

Builder: Nirmanshelters

Nirmanshelters has 1 registration on MahaRERA, including NirmanSrushti. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What does it mean that NirmanSrushti shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NirmanSrushti is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NirmanSrushti?

The registered promoter entity is Nirmanshelters, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NirmanSrushti?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NirmanSrushti?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in NirmanSrushti?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NirmanSrushti. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NirmanSrushti to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.