Home / Browse projects / Mumbai Suburban, Maharashtra / Nirmaan Heena

Completed No litigation declared Residential / Group Housing project

Nirmaan Heena

By M/s. Ramkripa Enterprises

RG-MH-07287 · RERA P51800056079 · Last updated on MahaRERA portal: 13 May 2026

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
20 of 21Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

Nirmaan Heena is a Residential / Group Housing project by M/s. Ramkripa Enterprises in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800056079 on 10 May 2024. The registration is recorded completed; possession was promised by 29 Dec 2025. 1 of the 21 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameNirmaan Heena
  • TypeResidential / Group Housing
  • Location
    • Tilak Mandir Road
    • Vile Parle East
    • Vileparle
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800056079
  • ReraGenie IDRG-MH-07287

Builder

  • NameM/s. Ramkripa Enterprises
  • Entity typePartnership
  • PartnersAnju Narayan Parmar, Veena Kishor Rathod, Kishor Ramji Rathod, Bipin Shivshankar Jani, Hansaben Mahesh Jani, Nandkishor Narayan Parmar
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2024First promiseDec 2025Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 May 2024
  • Promised completion29 Dec 2025
  • Revised completionRevised to 29 Dec 2025 (originally 9 Dec 2025)
  • Buildings1 building record
  • Documents filed63 files

Current status

5%1 of 21 units booked
84.4%Work done, per cost certificate

Figures as on 13 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Nirmaan HeenaNA9019221

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Nirmaan Heena: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,296 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Jul 2025
LandownerVillageDistrict
New Heena Co-operative Housing Society Ltd.VileparleMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI1295.99
Proposed, not sanctioned1,044 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchE Square Gr Floor Subhash Road Vile parle east 400057
Estimated costRs 9.87 cr
Cost incurredRs 8.33 cr
Work done84.42%
BuildingWingEstimatedIncurred
Nirmaan HeenaNARs 9.38 crRs 8.33 cr
-NARs 49.35 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPranjal Mahendra Mehta
ArchitectAMIT KATE
EngineerAVP CONSULTANT (ABHIJIT PHATARPEKAR)
Chartered AccountantVyas and Joshi
Chartered AccountantDharmesh Parekh & Associates
PartnerRole in project
M/s. Ramkripa Enterprises-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA04052620817Dec 2025 → Dec 2025

Reason as filed by the promoterWe have applied for OC on 29.11.2025 well before the completion date 9.12.2025 under Maharera. However MCGM issued the OC on 29.12.2025 and hence due to this there is a small delay of 20 days. We are seeking extension only for uploading OC.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: 2498050_OC_signed.pdf13 May 2026
Withdrawal Update Form 1File: Form 1 Q3 FY 25-26.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 Q3 FY25 26.pdf24 Apr 2026
Withdrawal Update Form 3File: form3Q3FY2526.pdf24 Apr 2026
Form 5 (FY 2024-2025)File: Form 5 FY 202425.pdf24 Mar 2026
Withdrawal Update Form 1File: Form 1 dated 31_10_2025.pdf10 Nov 2025
Withdrawal Update Form 2File: Form 2q2fy25-26.pdf10 Nov 2025
Withdrawal Update Form 3File: Form3Q2FY2526.pdf10 Nov 2025
Withdrawal Update Form 1File: Form1Q115072025.pdf30 Jul 2025
Withdrawal Update Form 2File: Form2Q1FY25-26.pdf30 Jul 2025
Withdrawal Update Form 3File: Q1Form3FY25-26.pdf30 Jul 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf9 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1Q12425.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1Q22425.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1Q32425.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1Q42425.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3Q12425.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3Q22425.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3Q32425.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3Q42425.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2Q12425.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2Q22425.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2Q32425.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2Q22425.pdf19 Apr 2025
Other - TechnicalFile: Form2A2425.pdf19 Apr 2025
Other - FinanceFile: III Certificate Regarding Deposit of Amounts.pdf17 Jan 2025
Other - FinanceFile: Certificate Regarding Deposit of Amounts.pdf28 Oct 2024
Building plan approvalFile: IOD Drawing 30-05-2024.pdf24 Jul 2024
Building plan approvalFile: Full IOD 30-05-2024.pdf24 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD Drawing 30-05-2024.pdf24 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: Full IOD 30-05-2024.pdf24 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: Further CC 21-06-2024.pdf24 Jul 2024
Other - FinanceFile: Certificate For Deposit in Rera Bank acc.pdf24 Jul 2024
Other - LegalFile: Declaration.pdf6 May 2024
Other - TechnicalFile: Declaration.pdf6 May 2024
Building plan approvalFile: Drawing Approved IOD till 7th Floor B_compressed 5.pdf3 May 2024
Layout approvalFile: Drawing Approved IOD till 7th Floor B_.pdf3 May 2024
Copy of Layout Approval (in case of layout)File: Drawing Approved IOD till 7th Floor B_.pdf3 May 2024
Building Plan Approval / NA Order for plotted developmentFile: Drawing Approved IOD till 7th Floor B_compressed 5.pdf3 May 2024
Details of encumbrances concerned to FinanceFile: Certificate of Encumbrances.pdf6 Mar 2024
Details of encumbrances concerned to LegalFile: Certificate of Encumbrances.pdf6 Mar 2024
Status of ConveyanceFile: Conveyance Deed_11zon.pdf6 Mar 2024
Other - FinanceFile: Declaration for Accepting consideration .pdf12 Feb 2024
Other - TechnicalFile: Declaration Cum Undertaking.pdf30 Jan 2024
CERSAI detailsFile: Undertaking Cersai Report.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3-_11zon.pdf25 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Org_compressed.pdf25 Jan 2024
Proforma of Agreement for saleFile: 25-Agreement for Sale Proforma.pdf25 Jan 2024
Proforma of Allotment letterFile: Proforma of Allotment Letter.pdf25 Jan 2024
Deviation Report with respect to Allotment letterFile: 37-Deviation Report for Allotment Letter.pdf25 Jan 2024
Deviation Report with respect to model copy of AgreementFile: 38-Deviation Report for AFS.pdf25 Jan 2024
Building plan approvalFile: 6-IOD_signed.pdf24 Jan 2024
PAN CardFile: 1-Pan card RKE.pdf24 Jan 2024
Copy of the legal title reportFile: TITLE CERTIFICATE 05-03-2024.pdf24 Jan 2024
Details of encumbrances concerned to FinanceFile: Reconcile Certificate of Encumbrances.pdf24 Jan 2024
Details of encumbrances concerned to LegalFile: Reconcile Certificate of Encumbrances.pdf24 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 6-IOD_signed.pdf24 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: 7-FirstCC-signed.pdf24 Jan 2024
Declaration about Commencement CertificateFile: 8-Declaration about Commencement Certifica.pdf24 Jan 2024
Declaration in FORM BFile: Form B for Rera RKE.pdf24 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11-Form 2 for Rera RKE 2023-2024.pdf24 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Bank Account.pdf24 Jan 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Manek PlazaCST Road Kalina Mumbai 4000989CompletedApr 2016Late, May 2016

How this compares with Mumbai Suburban

5%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nirmaan Heena on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vile Parle East6,700+ in Mumbai Suburban

2 kmNirmaan HeenaCompleted 138Lapsed / revoked 66Other 136Dot size: filed unitsN

Filed coordinates, straight-line distance. 340 registered projects within 2 km.

Builder: M/s. Ramkripa Enterprises

M/s. Ramkripa Enterprises has 1 registration on MahaRERA, including Nirmaan Heena. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Nirmaan Heena is delayed beyond 29 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nirmaan Heena?

The registered promoter entity is M/s. Ramkripa Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nirmaan Heena?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Nirmaan Heena?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nirmaan Heena?

The professionals named in the filing: Architect: Pranjal Mahendra Mehta; Architect: AMIT KATE; Engineer: AVP CONSULTANT (ABHIJIT PHATARPEKAR); Chartered Accountant: Vyas and Joshi; Chartered Accountant: Dharmesh Parekh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nirmaan Heena?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nirmaan Heena. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nirmaan Heena to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.