ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / New Deepali Co-Op. housing Society ltd.

Completed No litigation declared Residential / Group Housing project

New Deepali Co-Op. housing Society ltd.

By AKME PROPERTIES

RG-MH-59241 · RERA P51800016260 · Last updated on MahaRERA portal: 27 Mar 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 27 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

New Deepali Co-Op. housing Society ltd. is a Residential / Group Housing project by AKME PROPERTIES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800016260 on 2 May 2018. The registration is recorded completed; possession was promised by 25 Mar 2025. The completion date has moved by 27 months from the original filing.

At a glance

Project

  • NameNew Deepali Co-Op. housing Society ltd.
  • TypeResidential / Group Housing
  • Location
    • V. M. Ghanekar Road
    • Vile Parle East
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800016260
  • ReraGenie IDRG-MH-59241

Builder

  • NameAKME PROPERTIES
  • Entity typePartnership
  • PartnersRAJESH SHAH, BHAVESH SANDHA

Key dates

this monthRegisteredMay 2018First promiseDec 2022Revised toMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on2 May 2018
  • Promised completion25 Mar 2025
  • Revised completionRevised to 25 Mar 2025 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed89 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
New Deepali coop housing society limitedNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

New Deepali coop housing society limited: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered25

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area663 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1788.75
Proposed, not sanctioned512 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShantinath Modi Road, Kandivali West

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
AKME PROPERTIES-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013187Dec 2022 → Dec 2023

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS

EXT51800018332Dec 2022 → Jun 2024

Reason as filed by the promoterdue to covid 19 not able get complete project please grant us extension still 30/06/2024

EXT51800024384Dec 2022 → Mar 2025

Reason as filed by the promoterTILL OC DATE 25/03/2025

Litigation declared2

CaseCourtStatus
ARBPL/603/2017/2017BOMBAY HIGH COURTfor Rejection original side matters
ARBPL/369/2018/2018BOMBAY HIGH COURTARBP for hearing and final disposal

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Nov 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B Notary.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Invetory Disclosure signed 1.pdf27 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf17 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form 5 23-24.pdf17 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf16 Jan 2025
Certificates of CA (Form 3)File: form 3.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf16 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect CERTIFICATE.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate form 2.pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: Inventory Disclosure.pdf13 Aug 2024
Certificates of CA (Form 3)File: Form 3 CA.pdf13 Aug 2024
Declaration in FORM BFile: Form B.pdf17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf9 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf9 Apr 2024
Certificates of CA (Form 3)File: form 3.pdf9 Apr 2024
Disclosure of sold/ booked inventoryFile: inventory disclosure format.pdf28 Dec 2023
Certificates of CA (Form 3)File: Form 3 - AKME PROPERTIES.pdf28 Dec 2023
Declaration in FORM BFile: Form B.pdf19 Dec 2023
Disclosure of sold/ booked inventoryFile: AKME PROP FORM 5 22-23.pdf19 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: AKME PROP FORM 5 22-23.pdf19 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1997 RERA CERTIFICATE dt 04 10 2023.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2 (12-10-2023).pdf17 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer form 2A new (12-10-23).pdf17 Oct 2023
Certificates of CA (Form 3)File: Signed Ca Certificate Akme sep'23.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2 ( Engg certificate July 2022- Sept 2022 ).pdf1 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2 ( Engg Certificate April 2023- June 2023 ).pdf1 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2A ( Engg Certificate 2022-2023).pdf1 Sep 2023
Certificates of CA (Form 3)File: Signed Ca Certificate Akme june'23.pdf1 Sep 2023
Other - LegalFile: ND - Supplementary Agreement_compressed (1)_1-40.pdf8 Jul 2023
Other - LegalFile: ND - Supplementary Agreement_compressed (1)_41-80.pdf8 Jul 2023
Other - LegalFile: ND - Supplementary Agreement_compressed (1)_81-120.pdf8 Jul 2023
Other - LegalFile: ND - Supplementary Agreement_compressed (1)_121-160.pdf8 Jul 2023
Other - LegalFile: ND - Supplementary Agreement_compressed (1)_161-200.pdf8 Jul 2023
Other - LegalFile: ND - Supplementary Agreement_compressed (1)_201-220.pdf8 Jul 2023
Other - LegalFile: ND - Supplementary Agreement_compressed (1)_221-240.pdf8 Jul 2023
Other - LegalFile: ND - Supplementary Agreement_compressed (1)_241-280.pdf8 Jul 2023
Other - LegalFile: ND - Supplementary Agreement_compressed (1)_281-320.pdf8 Jul 2023
Other - LegalFile: ND - Supplementary Agreement_compressed (1)_321-end.pdf8 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf11 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer form 2A 21-22.pdf11 Jan 2023
Certificates of CA (Form 3)File: signed Ca Certificate Akme dec22.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer FORM 2A 19-20.pdf19 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer form 2A 21-22.pdf19 Dec 2022
CERSAI detailsFile: CERSAI DECLARATION.PDF19 Dec 2022
Disclosure of sold/ booked inventoryFile: inventory disclosure format.PDF19 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA Form 5 18-19.PDF19 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Form 5 21-22.PDF19 Dec 2022
Certificates of CA (Form 3)File: Signed Ca Certificate Akme New Format (1).pdf15 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1997 RERA CERTIFICATE.pdf14 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 (1).pdf14 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: 2313351_FurtherCC_signed.pdf6 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT FORM 1.pdf7 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER FORM 2.PDF7 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER FORM 2A.PDF7 Apr 2022
Certificates of CA (Form 3)File: CA FORM 3.PDF7 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20.pdf8 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-21.pdf8 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.PDF7 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.PDF7 Jan 2022
Certificates of CA (Form 3)File: fORM 3.PDF7 Jan 2022
Declaration about Commencement CertificateFile: DECLARATION OF CC AKME.PDF11 Oct 2021
Certificates of CA (Form 3)File: Signed CA Certificate AKME.pdf11 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: AKME FORM 2A.PDF8 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AKME PROPERTIES ARCHITECT CERTIFICATE.PDF7 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: akme properties Engineer Certificate.PDF7 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: Stilt CC.pdf25 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: 2nd flr CC VAILD UP TO 25 NOV 2020.pdf25 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: 2236444_FurtherCC.pdf25 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: Plinth CC.pdf4 Dec 2018
Building plan approvalFile: Renewed IOD.pdf30 Nov 2018
Building Plan Approval (IOD)File: Renewed IOD.pdf30 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: Plinth CC.pdf30 Nov 2018
Layout approvalFile: No layout declaration.pdf23 Apr 2018
Copy of Layout Approval (in case of layout)File: No layout declaration.pdf23 Apr 2018
Certificates of CA (Form 3)File: RERA 02.PDF23 Apr 2018

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 27 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep New Deepali Co-Op. housing Society ltd. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vile Parle East6,700+ in Mumbai Suburban

2 kmNew Deepali Co-Op. housiCompleted 138Lapsed / revoked 69Other 136Dot size: filed unitsN

Filed coordinates, straight-line distance. 343 registered projects within 2 km.

Builder: AKME PROPERTIES

AKME PROPERTIES has 1 registration on MahaRERA, including New Deepali Co-Op. housing Society ltd.. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if New Deepali Co-Op. housing Society ltd. is delayed beyond 25 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of New Deepali Co-Op. housing Society ltd.?

The registered promoter entity is AKME PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in New Deepali Co-Op. housing Society ltd.?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for New Deepali Co-Op. housing Society ltd.?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in New Deepali Co-Op. housing Society ltd.?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About New Deepali Co-Op. housing Society ltd.. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save New Deepali Co-Op. housing Society ltd. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.