Neumec Niwara
RG-MH-19898 · RERA P51800003319 · Last updated on MahaRERA portal: 6 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 90 months
- 5 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Neumec Niwara is a Others project by Neumec Venture in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003319 on 5 Aug 2017. Possession is promised by 30 Sep 2027. The completion date has moved by 90 months from the original filing. 16 of the 16 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameNeumec Niwara
- TypeOthers
- Location
- Mumbai Suburban
- Andheri
- 400057
- Pincode400057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003319
- ReraGenie IDRG-MH-19898
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Aug 2017
- Promised completion30 Sep 2027
- Revised completionRevised to 30 Sep 2027 (originally 30 Mar 2020)
- Buildings1 building record
- Documents filed131 files
Current status
Figures as on 6 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NEUMEC NIWARA | NA | 11 | 11 | 14 | 2 | 16 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.
NEUMEC NIWARA: 85% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Progress on shared amenities15
As on 6 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 80% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 60% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed20
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| NEUMEC NIWARA | NA | Rs 11.10 cr | Rs 5.63 cr |
| - | NA | Rs 58.40 lakh | Rs 37.23 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Bhalwankar Associates |
| Engineer | SK Consultants & Engineers |
| Engineer | HARDIK RAJESH SHAH |
| Chartered Accountant | N B Sayed & Associates |
| Chartered Accountant | CA Rutuja Narsingh & Associates |
| Chartered Accountant | JASUJA KAPOOR & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Neumec Venture | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterREASON EXPLAINED IN ATTACHMENT
Reason as filed by the promoterThe Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry. We would be highly obliged if you accept our application for the extension of the proje
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 62.5% allottees for purpose of extension of RERA registration period of the said project.
Reason as filed by the promoterThe delay was mainly occurred due to realignment of PG reservation on the Project land and obtaining various sanctions approvals etc. from the competent authority in that behalf including handing over process, procurement issues, financial constraints and site challenges. Due to such unforeseen circumstances, we were unable to complete the project within the time disclosed on the website. Despite these setbacks we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30-09-2026 to complete the project and f
Reason as filed by the promoterThe project completion has been delayed due to pending finishing and development work, along with delays in obtaining necessary approvals from concerned authorities. The remaining work is in progress, and additional time is required to complete the project and fulfill all regulatory requirements. We kindly request an extension for the completion of the project.In view of the above, we kindly request an extension for project completion until 30-09-2027
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001670 | Parshuram Mahadev Shirsat | Mr. Nilesh H. Gunjal,Mr. Ghevarchand Jain,Mr. Rajesh Jain | 02/11/2017 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Sep 2027
Documents filed131
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 131 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Neumec_Niwara_Form1_Q1_2026-27_03-07-2026_10-05.pdf | 6 Aug 2026 |
| Withdrawal Update Form 2File: Neumec_Niwara_Form2_Q1_2026-27_05-08-2026_08-10.pdf | 6 Aug 2026 |
| Withdrawal Update Form 3File: Neumec_Niwara_Form3_Q1_2026-27_29-07-2026_13-06_doc1.pdf | 6 Aug 2026 |
| Form 2A (FY 2024-2025)File: Form 2A FY 2024-25.pdf | 10 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A FY 2025-26.pdf | 10 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 (as per 31-03-2026).pdf | 2 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 2 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 2 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 - Neumec Niwara as on Sep 2025.pdf | 1 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 (as per 31-03-2026).pdf | 1 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 (as per 31-03-2026).pdf | 1 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 (as per 31-03-2026).pdf | 1 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - Neumec Niwara as on Sep 2025.pdf | 1 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 1 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 1 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 1 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - Neumec Niwara as on Sep 2025.pdf | 1 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 1 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 1 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 1 Jul 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - Neumec Niwara for FY 2024-25.pdf | 5 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Neumec Niwara as on Sep 2025.pdf | 29 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Neumec Niwara as on Sep 2025.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Neumec Niwara as on June 2025.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Neumec Niwara as on Sep 2025.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Neumec Niwara as on June 2025.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Neumec Niwara as on Sep 2025.pdf | 29 May 2026 |
| Form 1File: 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project) (2).pdf | 17 Jul 2025 |
| Form 2File: 20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project) (2).pdf | 17 Jul 2025 |
| Form 3File: 21 Certificates of CA (Form 3) (1).pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 6 Disclosure of sold_ booked inventory (1).pdf | 17 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Dec 2024 Signed_11zon.pdf | 30 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Mar 2025.pdf | 30 May 2025 |
| Certificates of CA (Form 3)File: Form_3_Mar_2025.pdf | 27 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_Mar_2025-1.pdf | 27 May 2025 |
| Disclosure of sold/ booked inventoryFile: Circular_29_Mar_2025.pdf | 27 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf | 27 May 2025 |
| Disclosure of sold/ booked inventoryFile: Cir 29 Dec 2024.pdf | 24 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24_compressed.pdf | 24 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 (Dec 2024)_11zon.pdf | 23 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (Dec 2024)_11zon.pdf | 23 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (FY 2022-23)_11zon.pdf | 23 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 - Neumec Niwara as on 31-12-2024.pdf | 15 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Niwara as on 31-12-2024.pdf | 15 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29 Neumec Niwara as on Sep 2024.pdf | 2 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 - Neumec Niwara as on 30-09-2024.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Niwara as on 30-09-2024.pdf | 26 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Niwara as on June 2024.pdf | 29 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 - Neumec Niwara as on 30-06-2024.pdf | 29 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf | 20 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf | 20 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Niwara as on March 2024.pdf | 4 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3 - Neumec Niwara as on March 2024.pdf | 4 Jun 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Neumec Niwara CC.pdf | 22 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Niwara June 23.pdf | 22 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Niwara as on Sep 2023.pdf | 22 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Niwara as on Dec 2023.pdf | 22 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - Neumec Niwara as on Sep 2023.pdf | 22 May 2024 |
| Certificates of CA (Form 3)File: Form 3 - Neumec Niwara as on Dec 2023.pdf | 22 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Neumec Niwara FY 2022-23.pdf | 22 Sep 2023 |
| Declaration in FORM BFile: Document 24.pdf | 12 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM_1.pdf | 12 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 M23.pdf | 12 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf | 12 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM_2A.pdf | 12 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Circular_29.pdf | 12 Sep 2023 |
| Certificates of CA (Form 3)File: Form 3 M 23.pdf | 12 Sep 2023 |
| Certificates of CA (Form 3)File: Form 3 J 23.pdf | 12 Sep 2023 |
| Certificates of CA (Form 5)File: Form 5 17-18.pdf | 12 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM_5-_2018_-_19.pdf | 12 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf | 12 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf | 12 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf | 12 Sep 2023 |
| Certificates of CA (Form 3)File: Form 3- Neumec Niwara as on 30-06-2023.pdf | 11 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Neumec Niwara- 2021-22.pdf | 25 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Niwara_Form_1.pdf | 29 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Neumec Niwara Mar 23 - Form 2.pdf | 28 Apr 2023 |
| Certificates of CA (Form 3)File: Form 3- Neumec Niwara as on 31-03-2023.pdf | 28 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Circular 29- Neumec Niwara.pdf | 3 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Neumec Niwara 30th June 2022.pdf | 27 Jan 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| NEUMEC VINAYAKP51800001651 | Andheri, Mumbai Suburban | Jul 2017 | Certificate Signed | Sep 2020Registered original: Mar 2019 | Sep 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 131 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Neumec Niwara on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 343 registered projects within 2 km.
Vijayraj Residency
Vijayraj Realtors
ZEE HAPPY VEENA
ZEE LIFESPACES
Romell Espalier
ROMELL REAL ESTATE PRIVATE LIMITED
ZEE SHAAN
TRISUL DEVELOPERS
SALE BUILDING 1 - CHAMUNDA CROWN AND SALE BUIL
Chamunda Builders & Developers
ARKADE PEARL 1
ARKADE DEVELOPERS LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: Neumec Venture
Neumec Venture has 2 registrations on MahaRERA, including Neumec Niwara and NEUMEC VINAYAK. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Neumec Niwara is delayed beyond 30 Sep 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Neumec Niwara?
The registered promoter entity is Neumec Venture, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Neumec Niwara?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Neumec Niwara?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Neumec Niwara?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Neumec Niwara?
The professionals named in the filing: Architect: Bhalwankar Associates; Engineer: SK Consultants & Engineers; Engineer: HARDIK RAJESH SHAH; Chartered Accountant: N B Sayed & Associates; Chartered Accountant: CA Rutuja Narsingh & Associates; Chartered Accountant: JASUJA KAPOOR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Neumec Niwara?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback