Home / Browse projects / Pune, Maharashtra / Netizen

Registered No litigation declared Others project

Netizen

By Arun Venunath Kharde Patil

RG-MH-49877 · RERA P52100052811 · Last updated on MahaRERA portal: 10 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 22 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedmoved 22 months from the original
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 95%
38 of 70Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

Netizen is a Others project by Arun Venunath Kharde Patil in Pune, Maharashtra, registered with MahaRERA as P52100052811 on 5 Oct 2023. Possession is promised by 15 Jul 2027. The completion date has moved by 22 months from the original filing. 32 of the 70 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameNetizen
  • TypeOthers
  • Location
    • s no 114/3/1
    • Hinjewadi
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052811
  • ReraGenie IDRG-MH-49877

Builder

  • NameArun Venunath Kharde Patil
  • Entity typeIndividual
  • GSTIN27AFZPK6766M1Z8

Key dates

this monthRegisteredOct 2023First promiseSep 2025Revised toJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Oct 2023
  • Promised completion15 Jul 2027
  • Revised completionRevised to 15 Jul 2027 (originally 15 Sep 2025)
  • Buildings1 building record
  • Documents filed96 files

Current status

46%32 of 70 units booked
97.5%Work done, per cost certificate

Figures as on 10 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MHADA AND COMM WINGNA1211145670

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

MHADA AND COMM WING: 86% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 10 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed49

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots49
Closed/Covered49

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area588 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Sep 2024
LandownerVillageDistrict
Mangnova RealtyPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI4598.0
Proposed, not sanctioned4,298 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchB 161/162 Supriya Towers New Dp Road Aundh Pune 411007
Estimated costRs 17.00 cr
Cost incurredRs 16.58 cr
Work done97.51%
BuildingWingEstimatedIncurred
MHADA AND COMM WINGNARs 17.00 crRs 16.58 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSachin Sutar
ArchitectAr. Sachin Sutar
EngineerSomnath Balu Rode
Chartered AccountantP N JAGTAP & Co
Chartered AccountantM/s. P.N. Jagtap & Co
Chartered AccountantAnil V Jagtap
Chartered AccountantDARSHAN ARUNKUMAR TOTALA
PartnerRole in project
Arun Venunath Kharde Patil-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20082502398Sep 2025 → Jul 2026

Reason as filed by the promoterTo, The Respected Authority, Maharashtra Real Estate Regulatory Authority (MahaRERA) Subject: Request for Extension under Section 7(3) for Registered Project - P52100052811 Respected Sir, We humbly request an extension under Section 7(3) of the Real Estate (Regulation and Development) Act for our registered project bearing Registration No. P52100052811. The current date of completion for the said project is 15/10/2025. However, due to unforeseen site conditions and delays beyond our control, we request that the completion date be extended to 15/07/2026. During the initial phase of construction

EA17072621781Sep 2025 → Jul 2027

Reason as filed by the promoterThe current date of part completion for the said project is 17/03/2026. We seek an extension under Section 7(3) as the MHADA Lottery process, for which the application was submitted on 13/04/2026, is still pending. Further, the construction of the 9th Floor could not be commenced due to the delay in obtaining the PCMC Road sanction and the consequent Road TDR sanction from the competent authority. These circumstances are beyond our control and have resulted in an unavoidable delay in completing the project. Accordingly, we request that the completion date be extended to 15/07/2027.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 15 Jul 2027

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf10 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf10 Jul 2026
Withdrawal Update Form 3File: FORM 3.pdf10 Jul 2026
Form 5 (FY 2025-2026)File: Form 5.pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf7 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf7 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf7 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf7 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf23 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf23 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf23 Dec 2025
Form 5 (FY 2023-2024)File: Form 5 23-24.pdf23 Jul 2025
Form 5 (FY 2024-2025)File: Form 5 24-25.pdf23 Jul 2025
Withdrawal Update Form 1File: Form 1 2025.pdf15 Jul 2025
Withdrawal Update Form 1File: Form 1 2025.pdf15 Jul 2025
Withdrawal Update Form 1File: Form 1 2025.pdf15 Jul 2025
Withdrawal Update Form 1File: Form 1 2025.pdf15 Jul 2025
Withdrawal Update Form 2File: Form 2 2025.pdf15 Jul 2025
Withdrawal Update Form 2File: Form 2 2025.pdf15 Jul 2025
Withdrawal Update Form 2File: Form 2 2025.pdf15 Jul 2025
Withdrawal Update Form 2File: Form 2 2025.pdf15 Jul 2025
Withdrawal Update Form 3File: Form 3 June 25.pdf15 Jul 2025
Withdrawal Update Form 3File: Form 3 June 25.pdf15 Jul 2025
Withdrawal Update Form 3File: Form 3 June 25.pdf15 Jul 2025
Withdrawal Update Form 3File: Form 3 June 25.pdf15 Jul 2025
Form 2A (FY 2023-2024)File: Form 2A No 01 2024.pdf15 Jul 2025
Form 2A (FY 2024-2025)File: Form 2A No 02 2025.pdf15 Jul 2025
Form 1File: form 1.pdf12 Jun 2025
Form 2File: Form 2.pdf12 Jun 2025
Form 3File: form 3..pdf12 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold unsold Inventory.pdf12 Jun 2025
Form 1File: Form 1...pdf12 Jun 2025
Form 2File: Form 2..pdf12 Jun 2025
Form 3File: Form 3...pdf12 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf12 Jun 2025
Form 1File: Form 1.....pdf12 Jun 2025
Form 2File: Form 2....pdf12 Jun 2025
Form 3File: Form 3.....pdf12 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold Inventory.pdf12 Jun 2025
Form 1File: form 1....pdf12 Jun 2025
Form 2File: Form 2.pdf12 Jun 2025
Form 3File: Form 3....pdf12 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf12 Jun 2025
Form 1File: Form 1......pdf12 Jun 2025
Form 2File: Form 2.....pdf12 Jun 2025
Form 3File: Form 3......pdf12 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold unsold inventory.pdf12 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate_compressed.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 2025.pdf15 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: aRCHITECT LETTER.pdf7 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory 2.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form -3_.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form-2.pdf14 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf4 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf27 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf27 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_.pdf27 Jun 2024
Proforma of Agreement for saleFile: AGREEMENT To SALE Model.pdf14 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 april 2024.pdf6 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Letter FORM 1.pdf25 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Letter FORM - 2.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jan 2024.pdf25 Jan 2024
Other - FinanceFile: Declaration Form 3 unit mismatch.pdf29 Aug 2023
Layout approvalFile: 1 Building Plan Approval.pdf17 Aug 2023
Building plan approvalFile: 2 Building Plan Approval.pdf17 Aug 2023
Building plan approvalFile: 3 Building Plan Approval.pdf17 Aug 2023
Building plan approvalFile: 4 Building Plan Approval.pdf17 Aug 2023
Building plan approvalFile: 5 Building Plan Approval.pdf17 Aug 2023
PAN CardFile: 1 PAN Card.pdf17 Aug 2023
Copy of the legal title reportFile: legal report netizen.pdf17 Aug 2023
Details of encumbrances concerned to FinanceFile: Encumbrances Finance.pdf17 Aug 2023
Details of encumbrances concerned to FinanceFile: encumbrances concerned to LEGALL.pdf17 Aug 2023
Details of encumbrances concerned to LegalFile: Encumbrances Finance.pdf17 Aug 2023
Details of encumbrances concerned to LegalFile: encumbrances concerned to LEGALL.pdf17 Aug 2023

How this compares with Pune

46%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 22 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Netizen on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hinjewadi13,700+ in Pune

2 kmNetizenCompleted 106Lapsed / revoked 36Other 64Dot size: filed unitsN

Filed coordinates, straight-line distance. 206 registered projects within 2 km.

Builder: Arun Venunath Kharde Patil

Arun Venunath Kharde Patil has 1 registration on MahaRERA, including Netizen. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Netizen is delayed beyond 15 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Netizen?

The registered promoter entity is Arun Venunath Kharde Patil, an individual as per the filing. Its GSTIN 27AFZPK6766M1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Netizen?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Netizen?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Netizen?

The professionals named in the filing: Architect: Sachin Sutar; Architect: Ar. Sachin Sutar; Engineer: Somnath Balu Rode; Chartered Accountant: P N JAGTAP & Co; Chartered Accountant: M/s. P.N. Jagtap & Co; Chartered Accountant: Anil V Jagtap. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Netizen?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Netizen. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Netizen to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.