Home / Browse projects / NEHA RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

NEHA RESIDENCY

By SHISHIR MANGEH SHIVAPURKAR

RG-MH-21001 · RERA P51900008710 · Last updated on MahaRERA portal: 23 Jun 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 29 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 58 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
May 2024Possession promised29 months past this date
7 of 11Construction stages donefurthest along: Internal walls, 95%
1Complaints at MahaRERAon this registration
Jump to the 32 documents Report an error

NEHA RESIDENCY is a Residential / Group Housing project by SHISHIR MANGEH SHIVAPURKAR in PAREL SEWREE DIVISION, 400015, registered with MahaRERA as P51900008710 on 19 Aug 2017. Possession was promised by 30 May 2024 and is now 29 months past that date. The completion date has moved by 58 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameNEHA RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • RAM TEKADI ROAD
    • PAREL SEWREE DIVISION
    • 400015
  • Pincode400015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900008710
  • ReraGenie IDRG-MH-21001

Builder

  • NameSHISHIR MANGEH SHIVAPURKAR
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

29 months past promisethis monthRegisteredAug 2017First promiseJul 2019Revised toMay 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion30 May 2024
  • Revised completionRevised to 30 May 2024 (originally 30 Jul 2019)
  • Buildings1 building record
  • Documents filed32 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NEHA RESIDENCYNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jun 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

NEHA RESIDENCY: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Jun 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area507 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3277.0
Proposed, not sanctioned3,277 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPRABHADEVI MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPAGNIS AND PAGNIS
EngineerSTRUCT BOMBAY CONSULTANTS
PartnerRole in project
SHISHIR MANGEH SHIVAPURKAR-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900009778Jul 2019 → Nov 2023

Reason as filed by the promoterIn Current Pandemic with lots of hardship it is very difficult to work on site last year due to corona from 19/03/2020 to till date the construction activities not done due to shortage of skilled workers like carpenters, fitters , etc. and also delay due to lock down impact on work. Our Project Car Parking Tower work is in progress and it is came near to complication but due to 1st Cyclone Nisarga impact on 3/6/2020 our part of Carpaking tower was badly damaged Photos Attached. After that the second Cyclone Tauktae impact on 17/05/2021 our Car parking tower was totally damaged. We want to rewo

EXT51900001967Jul 2019 → Jul 2020

Reason as filed by the promoterThe entire building is almost ready for occupation except mechanical car parking tower. Which is delayed due to some technical reason. The entire work is of steel fabrication and electronic components are to be installed. Therefore the said work can not be done in the monsoon period. Which may take 180 working days after monsoon. Therefore the date of possession after obtaing occupation certificate from MCGM is extended upto 30th June 2020

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12401003Pegasus Assets Reconstruction Private LimitedSHISHIR MANGEH SHIVAPURKAR03/12/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed32

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate.pdf23 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate.pdf23 Jun 2021
Disclosure of sold/ booked inventoryFile: Sold inventory details.pdf23 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Neha Residency - FORM 5.pdf9 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: MAHARERA FORM 5 For annual report of CA fy 19 - 20.pdf9 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 For annual report of CA FY 20 21.pdf9 Jun 2021
Certificates of CA (Form 5)File: Neha Residency - FORM 5.pdf10 Jul 2019
Layout approvalFile: Lay out -PLAN _180.pdf31 Jul 2017
Building plan approvalFile: EB 6553 FS IOD -PLAN _497.pdf31 Jul 2017
Building plan approvalFile: EB 6553 FS IOD -PLAN _498.pdf31 Jul 2017
PAN CardFile: Shishir Shivapurkar - PAN_Card.pdf31 Jul 2017
Copy of the legal title reportFile: Report on Title_1.pdf31 Jul 2017
Details of encumbrancesFile: NR Reliance - Index II.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Lay out -PLAN _180.pdf31 Jul 2017
Building Plan Approval (IOD)File: EB 6553 FS IOD -PLAN _497.pdf31 Jul 2017
Building Plan Approval (IOD)File: EB 6553 FS IOD -PLAN _498.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf31 Jul 2017
Declaration in FORM BFile: NR Form B_001.pdf31 Jul 2017
Declaration in FORM BFile: NR Form B_002.pdf31 Jul 2017
Declaration in FORM BFile: NR Form B_003.pdf31 Jul 2017
Declaration in FORM BFile: NR Form B_004.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arichitect 1.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect2.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 engineer page 2.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer page 3.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer page 1.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Cert 1.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA Certif 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: C A Certrifcat 3).pdf31 Jul 2017
Proforma of Allotment letterFile: Draft Sale AgreementRERE(1).pdf31 Jul 2017
Copy of the legal title reportFile: Report on Title_2.pdf29 Jul 2017
Copy of the legal title reportFile: Report on Title_3.pdf29 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Empire Builders and DevelpersKeer House Bhandar Gally Mahim Mumbai 1696CompletedDec 2009Oct 2009

Keep NEHA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PAREL SEWREE DIVISION

2 kmNEHA RESIDENCYCompleted 5Lapsed / revoked 5Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: SHISHIR MANGEH SHIVAPURKAR

SHISHIR MANGEH SHIVAPURKAR has 2 registrations on MahaRERA, including NEHA RESIDENCY and NEHA GALAXY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record.

Frequently asked questions

What does it mean that NEHA RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NEHA RESIDENCY is delayed beyond 30 May 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NEHA RESIDENCY?

The registered promoter entity is SHISHIR MANGEH SHIVAPURKAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NEHA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NEHA RESIDENCY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for NEHA RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NEHA RESIDENCY?

The professionals named in the filing: Architect: PAGNIS AND PAGNIS; Engineer: STRUCT BOMBAY CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NEHA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NEHA RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NEHA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.