NEHA GALAXY
RG-MH-27139 · RERA P51900010851 · Last updated on MahaRERA portal: 6 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 61 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NEHA GALAXY is a Residential / Group Housing project by SHISHIR MANGEH SHIVAPURKAR in DADAR, 400028, registered with MahaRERA as P51900010851 on 31 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 61 months from the original filing. 14 of the 82 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameNEHA GALAXY
- TypeResidential / Group Housing
- Location
- Veer Sawarkar Marg
- DADAR
- 400028
- Pincode400028
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900010851
- ReraGenie IDRG-MH-27139
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Aug 2017
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 26 May 2021)
- Buildings1 building record
- Documents filed317 files
Current status
Figures as on 6 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NEHA GALAXY | NA | 23 | 22 | 72 | 10 | 82 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 85%.
NEHA GALAXY: 51% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Progress on shared amenities15
As on 6 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 20% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PAGNIS AND PAGNISS |
| Chartered Accountant | PRAVINKUMAR DHARAMSIBHAI BHRASADIYA |
| Chartered Accountant | Rahul Bera |
| Partner | Role in project |
|---|---|
| SHISHIR MANGEH SHIVAPURKAR | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn Current Pandemic with lots of hardship it is very difficult to work on site last year due to corona from 19/03/2020 to till date the construction activities not done due to shortage of skilled workers like carpenters, fitters , etc. and also delay due to lock down impact on work. from 19/03/2020 after open of current lockdwon we start the work so there for we request you grant us the extension for more the 18th Months On 25/11/2022 to complete the project
Reason as filed by the promoterDue to some Personal reasons promotor was not able to give proper attension to the compliances of MahaRERA, As we have not received OC yet from the respective authorities we are going to get OC after receiving extension from the MahaRERA. We have paid penalty of rs. 50000, which was imposed by RERA authorities. Promotor undertakles to comply with any future compliances of MahaRERA. Promotor assures that he will do all compliances for the rest of the extension period. Previous resubmission is not proper due to some technical problem. Now i am resubmitting proper resubmission with all documents.
Reason as filed by the promoterThe Promoter respectfully submits that the delay in completion of the project is on account of execution of an additional Parking Tower, which involves installation of specialized mechanized parking systems. The required machinery for the said parking tower has been ordered from European manufacturers, as such equipment is not available domestically and must meet specific technical and safety standards. However, due to ongoing war and geopolitical disturbances in the Middle East region, there have been severe disruptions in international logistics, shipping routes, and supply chains. As a resu
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000000797 | RAJANIKANT DESHMUKH | SHISHIR MANGESH SHIVAPURKAR | 29/11/2017 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed317
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 317 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Q1.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Q2.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Q3.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer page 3.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer page 3.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer page 3.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3 v2 25-26 _Q1 Neha developers.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3 v2 25-26 _Q2 Neha developers.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3 v2 25-26 _Q3 Neha developers.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 04072025.pdf | 3 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer page 3.pdf | 3 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3 v2 25-26 _Q3 Neha developers.pdf | 3 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 04072025.pdf | 6 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer page 3.pdf | 6 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3 v2 25-26 _Q1 Neha developers.pdf | 6 Jan 2026 |
| Withdrawal Update Form 1File: sayani road rera form_003.pdf | 2 Jan 2026 |
| Withdrawal Update Form 1File: sayani road rera form_003.pdf | 2 Jan 2026 |
| Withdrawal Update Form 1File: sayani road rera form_003.pdf | 2 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 06102025.pdf | 2 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 04072025.pdf | 2 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer page 3.pdf | 2 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer page 3.pdf | 2 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer page 3.pdf | 2 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer page 3.pdf | 2 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer page 3.pdf | 2 Jan 2026 |
| Withdrawal Update Form 3File: NG Form 3 CA Certification 042_003.pdf | 2 Jan 2026 |
| Withdrawal Update Form 3File: NG Form 3 CA Certification 042_003.pdf | 2 Jan 2026 |
| Withdrawal Update Form 3File: NG Form 3 CA Certification 042_003.pdf | 2 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3 v2 25-26 _Q2 Neha developers.pdf | 2 Jan 2026 |
| Withdrawal Update Form 3File: FORM 3 v2 25-26 _Q1 Neha developers.pdf | 2 Jan 2026 |
| Form 1File: Form 1 22-23 4.pdf | 3 Jul 2025 |
| Form 2File: Form - 2 Q4.pdf | 3 Jul 2025 |
| Form 3File: FORM 3 v2 22-23 _Q4 Neha developers.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Booked Inventory 22-23 Q4.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Booked Inventory 23-24 Q1.pdf | 3 Jul 2025 |
| Form 1File: Form 1 23-24 1.pdf | 3 Jul 2025 |
| Form 2File: Form - 2 Q1.pdf | 3 Jul 2025 |
| Form 3File: FORM 3 v2 23-24 _Q1 Neha developers.pdf | 3 Jul 2025 |
| Form 3File: FORM 3 v2 23-24 _Q2 Neha developers.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Booked Inventory 23-24 Q2.pdf | 3 Jul 2025 |
| Form 1File: Form 1 23-24 2.pdf | 3 Jul 2025 |
| Form 2File: Form - 2 Q2.pdf | 3 Jul 2025 |
| Form 1File: Form 1 23-24 3.pdf | 3 Jul 2025 |
| Form 2File: Form - 2 Q3.pdf | 3 Jul 2025 |
| Form 3File: FORM 3 v2 23-24 _Q3 Neha developers.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Booked Inventory 23-24 Q3.pdf | 3 Jul 2025 |
| Form 1File: Form 1 23-24 4.pdf | 3 Jul 2025 |
| Form 2File: Form - 2 Q4.pdf | 3 Jul 2025 |
| Form 3File: FORM 3 v2 23-24 _Q4 Neha developers.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Booked Inventory 23-24 Q4.pdf | 3 Jul 2025 |
| Form 1File: Form 1 24-25 1.pdf | 3 Jul 2025 |
| Form 2File: Form - 2 Q1.pdf | 3 Jul 2025 |
| Form 3File: FORM 3 v2 24-25 _Q1 Neha developers.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Booked Inventory 24-25 Q1.pdf | 3 Jul 2025 |
| Form 1File: Form 1 24-25 2.pdf | 3 Jul 2025 |
| Form 2File: Form - 2 Q2.pdf | 3 Jul 2025 |
| Form 3File: FORM 3 v2 24-25 _Q2 Neha developers.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Booked Inventory 24-25 Q2.pdf | 3 Jul 2025 |
| Form 1File: Form 1 24-25 3.pdf | 3 Jul 2025 |
| Form 2File: Form - 2 Q3.pdf | 3 Jul 2025 |
| Form 3File: FORM 3 v2 24-25 _Q3 Neha developers.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Booked Inventory 24-25 Q3.pdf | 3 Jul 2025 |
| Form 1File: Form 1 24-25 4.pdf | 3 Jul 2025 |
| Form 2File: Form - 2 Q4.pdf | 3 Jul 2025 |
| Form 3File: FORM 3 v2 24-25 _Q4 Neha developers.pdf | 3 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Booked Inventory 24-25 Q4.pdf | 3 Jul 2025 |
| Form 5 (FY 2017-2018)File: Neha developers-Form-5 17-18.pdf | 3 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 22-23 4.pdf | 7 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 23-24 1.pdf | 7 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 23-24 2.pdf | 7 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 23-24 3.pdf | 7 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 23-24 4.pdf | 7 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 24-25 1.pdf | 7 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 24-25 2.pdf | 7 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 24-25 3.pdf | 7 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 24-25 4.pdf | 7 Jun 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Letter -Neha- LEGAL.pdf | 5 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 17-18 1.pdf | 5 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 22-23 3.pdf | 5 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 22-23 2.pdf | 5 Jun 2025 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Empire Builders and Develpers | Keer House Bhandar Gally Mahim Mumbai 16 | 96 | Completed | Dec 2009 | Oct 2009 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 317 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep NEHA GALAXY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DADAR
Filed coordinates, straight-line distance. 123 registered projects within 2 km.
Kohinoor Square Phase 1
Kohinoor CTNL Infrastructure Company Priva
Sigma Garnet
COLO COLOR PRIVATE LIMITED
PALETTE
SURAJ ESTATE DEVELOPERS LTD
Eon One
Firstlight Properties Private Limited
Ratan Address
Shri Nakoda Enterprises
Promesa West End
M/s. virtue Enterprises
Builder: SHISHIR MANGEH SHIVAPURKAR
SHISHIR MANGEH SHIVAPURKAR has 2 registrations on MahaRERA, including NEHA RESIDENCY and NEHA GALAXY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What does it mean that NEHA GALAXY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if NEHA GALAXY is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NEHA GALAXY?
The registered promoter entity is SHISHIR MANGEH SHIVAPURKAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NEHA GALAXY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against NEHA GALAXY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for NEHA GALAXY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NEHA GALAXY?
The professionals named in the filing: Architect: PAGNIS AND PAGNISS; Chartered Accountant: PRAVINKUMAR DHARAMSIBHAI BHRASADIYA; Chartered Accountant: Rahul Bera. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NEHA GALAXY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback