Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Oct 2021Possession promisedmoved 9 months from the original
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 0%
23 of 23Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 35 documents Report an error

NAYAAB RESIDENCY is a Mixed Development project by M/S NAYAAB DEVELOPERS in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/318/PR/190301/002465 on 1 Mar 2019. Possession is promised by 25 Oct 2021. The completion date has moved by 9 months from the original filing. 0 of the 23 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.

At a glance

Project

  • NameNAYAAB RESIDENCY
  • TypeMixed Development
  • Location
    • Udupi
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1273/318/PR/190301/002465
  • ReraGenie IDRG-KA-26691

Builder

  • NameM/S NAYAAB DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryBAIKADI MOHAMMED ZAFFER

Key dates

this monthRegisteredMar 2019First promiseJan 2021Revised toOct 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on1 Mar 2019
  • Promised completion25 Oct 2021
  • Revised completionRevised to 25 Oct 2021 (originally 25 Jan 2021)
  • Buildings1 building record
  • Documents filed35 files

Current status

0%0 of 23 units booked

Figures as on Not stated, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NAYAAB RESIDENCY-----23

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on Not stated, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.

Building: 0% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on Not stated, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area965 sq m
Land owned byNot the promoter
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.91 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAMANI HANDE P.S.
EngineerU RAJENDRA MAIYA

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJan 2021 → Oct 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed35

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/318/PR/190301/002465 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: NAYAB CERTIFICATE OF FIRM20181124_10402614.pdf-
COMMENCEMENT CERTIFICATE-
BUILDING PLAN APPROVED(2)-
approved layout plan-
PROFORMA OF AGREEMENT OF SALE - NAYAAB-
SALE DEED-
SECTION OF BUILDING APPROVED-
AREA DEVELOPMENT PLAN APPROVED-
Allotment_Letter (1)-
PROJECT SPECIFICATION-
ENCUMBRANCE CERTIFICATE-
Notorized Affidavit Us 3(1)-
KHATHA-
MOU-
LAND REVENUE ACT AND LEGAL OPINION-
PCB120190119_15490430-
approved layout plan-
approved section of building-
Prospectus/BrochureFile: Nayaab brochure.pdf-
Advertisement Copy 1File: Nayaab brochure.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1273_318_PR_190301_002465.xlsx-
Stability CertificateFile: Stability Certificate.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: approval of drainage.pdf-
Occupancy CertificateFile: Occupancy Certificate.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift Licence.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Electrical Approval.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: approval of drainage.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: NOT DONE.pdf-
Details of undivided share of land handed over to the association of allotteesFile: NOT DONE.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect's Certificate[Completed].pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Ca's Certificate.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Anil.pdf-
ENGINEER CERTIFICATEFile: Engineer's Certificate[Completed].pdf-
NOC FROM ELECTRIAL DEPARTMENTFile: NOC for Electricity.pdf-
OTHER DOCUMENTSFile: conveyance deed.pdf-

How this compares with Udupi

0%of this project is bookeddistrict median 0%
22%of Udupi projects moved their completion datethis one moved by 9 months
0%of Udupi registrations have lapsed or been cancelledthis one is on the register

Computed across the 260+ Udupi projects on ReraGenie, from their own filings.

Keep NAYAAB RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Udupi260+ in Udupi

2 kmNAYAAB RESIDENCYOther 47Dot size: filed unitsN

Filed coordinates, straight-line distance. 47 registered projects within 2 km.

Builder: M/S NAYAAB DEVELOPERS

M/S NAYAAB DEVELOPERS has 1 registration on RERA Karnataka, including NAYAAB RESIDENCY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Udupi district page.

Frequently asked questions

What are my rights if NAYAAB RESIDENCY is delayed beyond 25 Oct 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NAYAAB RESIDENCY?

The registered promoter entity is M/S NAYAAB DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NAYAAB RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NAYAAB RESIDENCY?

The professionals named in the filing: Architect: RAMANI HANDE P.S.; Engineer: U RAJENDRA MAIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAYAAB RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAYAAB RESIDENCY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAYAAB RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.