NAV BALAJI CO-OP HSG. SOC. LTD.

By RUTURAJ DEVELOPERS

RG-MH-06647 · RERA P51700053006 · Last updated on MahaRERA portal: 4 Aug 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 85%
28 of 35Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

NAV BALAJI CO-OP HSG. SOC. LTD. is a Others project by RUTURAJ DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700053006 on 10 Oct 2023. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 6 months from the original filing. 7 of the 35 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameNAV BALAJI CO-OP HSG. SOC. LTD.
  • TypeOthers
  • Location
    • Survey No 29/A
    • Hissa No 3
    • Survey No 29/A
    • Hissa No 4
    • Village Shirgaon
    • Taluka -Ambarnath
    • Badlapur
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700053006
  • ReraGenie IDRG-MH-06647

Builder

  • NameRUTURAJ DEVELOPERS
  • Entity typePartnership
  • PartnersJIGNESH BHARATBHAI SHAH, JANARDAN LAHU DAYARE, RAJENDRA RAMANBHAI PATEL, NARAYAN CHANGO DAYRE, CHANDRAKANT KASHINATH MHASKAR, NEERAJ JAYESHKUMAR SHAH, BALIRAM RAGHUNATH KARALE

Key dates

4 months past promisethis monthRegisteredOct 2023First promiseDec 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Oct 2023
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed56 files

Current status

20%7 of 35 units booked
80.8%Work done, per cost certificate

Figures as on 4 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NAV BALAJI CO-OP HSG SOC LTDNA8729635

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 85%.

NAV BALAJI CO-OP HSG SOC LTD: 74% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed42

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots42
Open Space42

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area641 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NAV BALAJI CO-0P HSG. SOC. LTD.Badlapur (M Cl)Thane

Approvals and building plan

Sanctioning authorityKulgaon Badlapur Nagar Parishad
Permissible FSI1698.94
Proposed, not sanctioned1,699 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLOTUS HOUSE SHOP NO 5-12 KATRAP ROAD BADLAPUR EAST
Estimated costRs 4.39 cr
Cost incurredRs 3.54 cr
Work done80.75%
BuildingWingEstimatedIncurred
NAV BALAJI CO-OP HSG SOC LTDNARs 4.17 crRs 3.54 cr
-NARs 21.93 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJ ASSOCIATES
EngineerATUL KUDTARKAR AND ASSOCIATES PVT LTD
Chartered AccountantMUKESH GURNANI
Chartered AccountantVRP & Associates
PartnerRole in project
RUTURAJ DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA16012619470Dec 2025 → Jun 2026

Reason as filed by the promoter.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Ruturaj Developers Form 1.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 Ruturaj Developers-1-3.pdf4 Aug 2026
Withdrawal Update Form 2File: Ruturaj Developers Form 2.pdf4 Aug 2026
Withdrawal Update Form 2File: Form 2 Ruturaj Developers-4-6.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 Ruturaj developers 31122025.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 Ruturaj developers 30062026.pdf4 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 31122025.pdf17 Feb 2026
Withdrawal Update Form 2File: Form 2 31122025.pdf17 Feb 2026
Withdrawal Update Form 3File: Form 3 Ruturaj developers 31122025.pdf17 Feb 2026
Form 2A (FY 2024-2025)File: Form 2A_compressed.pdf17 Feb 2026
Withdrawal Update Form 1File: ruturaj Developers Form 1 30092025.pdf16 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf16 Jan 2026
Withdrawal Update Form 3File: Form 3 Ruturaj developers.pdf16 Jan 2026
Form 5 (FY 2024-2025)File: From 5 Ruturaj Developers Signed.pdf27 Sep 2025
Withdrawal Update Form 1File: Form 1.pdf19 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf19 Jul 2025
Withdrawal Update Form 3File: Form 3 Ruturaj developers.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certifiacte RD Q4.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certifiacte RD Q4.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf9 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf9 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf2 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf2 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: signedForm 5 Ruturaj Developers.pdf2 Dec 2024
Details of encumbrances concerned to FinanceFile: Financial Encumbrance - Sharda Homes.pdf21 Sep 2023
Details of encumbrances concerned to LegalFile: Financial Encumbrance - Sharda Homes.pdf21 Sep 2023
Other - FinanceFile: Financial Encumbrance.pdf14 Sep 2023
CERSAI detailsFile: CERSAI_Search_Report_200279617340_For_Asset_Based_Search_06_09_2023_13_54_09_566.pdf6 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ruturaj developers.pdf6 Sep 2023
Layout approvalFile: LAYOUT.pdf2 Sep 2023
Building plan approvalFile: LAYOUT.pdf2 Sep 2023
PAN CardFile: PAN.pdf2 Sep 2023
Copy of the legal title reportFile: Legal Title.pdf2 Sep 2023
Details of encumbrances concerned to FinanceFile: NO ENCUMBERNACES.pdf2 Sep 2023
Details of encumbrances concerned to LegalFile: NO ENCUMBERNACES.pdf2 Sep 2023
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf2 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: LAYOUT.pdf2 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf2 Sep 2023
Declaration about Commencement CertificateFile: FORM D.pdf2 Sep 2023
Declaration in FORM BFile: FORM B JIGNESH.pdf2 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf2 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf2 Sep 2023
CERSAI detailsFile: CERSAI.pdf2 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: BALIRAM.pdf2 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: CHANDRAKANT.pdf2 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: JANARDAN.pdf2 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: JIGNESH.pdf2 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: NEERAJ.pdf2 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: RAJENDRA.pdf2 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: NARAYAN.pdf2 Sep 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER 1_11zon.pdf2 Sep 2023
Proforma of Agreement for saleFile: AFS.pdf2 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORM A.pdf2 Sep 2023
Deviation Report with respect to Allotment letterFile: NO DEVIATION ALLOTMENT LETTER.pdf2 Sep 2023
Deviation Report with respect to model copy of AgreementFile: NO DEVIATION AGREEMENT.pdf2 Sep 2023

How this compares with Thane

20%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 6 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NAV BALAJI CO-OP HSG. SOC. LTD. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Village Shirgaon, Taluka -Ambarnath, Badlapur7,600+ in Thane

2 kmNAV BALAJI CO-OP HSG. SOCompleted 150Lapsed / revoked 52Other 107Dot size: filed unitsN

Filed coordinates, straight-line distance. 309 registered projects within 2 km.

Builder: RUTURAJ DEVELOPERS

RUTURAJ DEVELOPERS has 1 registration on MahaRERA, including NAV BALAJI CO-OP HSG. SOC. LTD.. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that NAV BALAJI CO-OP HSG. SOC. LTD. shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NAV BALAJI CO-OP HSG. SOC. LTD. is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NAV BALAJI CO-OP HSG. SOC. LTD.?

The registered promoter entity is RUTURAJ DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NAV BALAJI CO-OP HSG. SOC. LTD.?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NAV BALAJI CO-OP HSG. SOC. LTD.?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NAV BALAJI CO-OP HSG. SOC. LTD.?

The professionals named in the filing: Architect: RAJ ASSOCIATES; Engineer: ATUL KUDTARKAR AND ASSOCIATES PVT LTD; Chartered Accountant: MUKESH GURNANI; Chartered Accountant: VRP & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAV BALAJI CO-OP HSG. SOC. LTD.?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAV BALAJI CO-OP HSG. SOC. LTD.. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAV BALAJI CO-OP HSG. SOC. LTD. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.