Namoville
RG-MH-14598 · RERA P52100022808 · Last updated on MahaRERA portal: 5 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 56 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Namoville is a Residential / Group Housing project by ROYAL NAMOVILLE VENTURES in Pune, Maharashtra, registered with MahaRERA as P52100022808 on 30 Oct 2019. Possession is promised by 31 Dec 2028. The completion date has moved by 56 months from the original filing. 112 of the 118 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.
At a glance
Project
- NameNamoville
- TypeResidential / Group Housing
- Location
- Balewadi Highstreet DP
- Balewadi
- Haveli
- Pune
- 411045
- Pincode411045
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100022808
- ReraGenie IDRG-MH-14598
Builder
- NameROYAL NAMOVILLE VENTURES
- Entity typeOthers
- Named personsRoyal Vasturachana LLP, Royal Vastunirman LLP, Samruddhi Buildwel LLP, Rafique Amirhamja Motiwala, Yasin Amirhamja Motiwala
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on30 Oct 2019
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 30 Apr 2024)
- Buildings2 building records
- Documents filed256 files
Current status
Figures as on 5 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing C | NA | 18 | 15 | 58 | 0 | 58 |
| Wing B | NA | 17 | 15 | 60 | 0 | 60 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 5 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 90%.
Wing C75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
Wing B87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 5 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 35% |
| Water Supply | Yes | 25% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 10% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 25% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed354
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing C | 174 | 174 |
| Wing B | 180 | 180 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing C | NA | Rs 12.50 cr | Rs 11.39 cr |
| Wing B | NA | Rs 12.50 cr | Rs 11.39 cr |
| - | NA | Rs 2.00 cr | Rs 1.30 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VK a Architecture |
| Architect | Raviraj Gosavi |
| Architect | Archmaze Associates |
| Engineer | Mahendra Kale |
| Chartered Accountant | DSD and Associates |
| Chartered Accountant | K K S S AND ASSOCIATES |
| Chartered Accountant | N N Bagwan and Associates |
| Chartered Accountant | A H V & Associates |
| Partner | Role in project |
|---|---|
| ROYAL NAMOVILLE VENTURES | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe request you to Grant the Extension of 1 year u/s 6 of Maharera Act. As the occurrence of unexpected global pandemic situation of COVID -19 has direct effect on the work due to shortage of material, labour & other necessary resources of project leads to the delay in completion of the project.
Reason as filed by the promoterReasons for Delay in Project/Grounds for Extension of the Project NAMOVILLE - 1. One of the landowner namely Mr. Jeeva Narayanan Vishwakarma expired during the year 2020. Due to tragic death of the Mr. Jeeva Narayanan Vishwakarma his family members got panicked and were unable to make any decision for 1-2 years. As per development agreement No. 3717/2018 landowner has to vacate the bungalow situated on the land S No 32/2/3 & 32/2/4 and need to give peaceful possession to us after executing the DAPA. However due ailment he cannot vacate his land and bungalow till his death. After his demise his
Reason as filed by the promoter1. As per updated UDCPR, 2020 promoters are eligible for additional FSI area and also promoters intend to take paid TDR for additional construction at NAMOVILLE building. Additional FSI and paid TDR will result in additional 2 floors at Wing B & Wing C. Sanction process of these area and procedural matters will take 6-8 months and construction of it will take additional 12-15 months. Effectively promoters can complete the Wing B & C upto June 2028. Promoters are hopeful that they will get additional FSI area as per updated UDCPR, 2020. 2. Also promoters intend to add Wing A part and parcel of
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Oct 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Jan 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Jan 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed256
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 256 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Namo June 26.pdf | 5 Aug 2026 |
| Withdrawal Update Form 2File: FORM 2 Namo.pdf | 5 Aug 2026 |
| Withdrawal Update Form 3File: FORM-3 Namo-compressed.pdf | 5 Aug 2026 |
| Form 1File: Form 1 2019.pdf | 12 May 2026 |
| Form 2File: Q3-2019-20.pdf | 12 May 2026 |
| Form 3File: 1Dec 19 Final_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Discl.pdf | 12 May 2026 |
| Form 1File: Form 1.pdf | 12 May 2026 |
| Form 2File: Q4-2019-20.pdf | 12 May 2026 |
| Form 3File: 2March 20 Final_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Discl.pdf | 12 May 2026 |
| Form 1File: 1Form 1.pdf | 12 May 2026 |
| Form 2File: Q1-20-21.pdf | 12 May 2026 |
| Form 3File: 3June 20_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Discl.pdf | 12 May 2026 |
| Form 1File: 11Form 1 March 25.pdf | 12 May 2026 |
| Form 2File: Q4-24-25.pdf | 12 May 2026 |
| Form 3File: 22March 25_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 16 March 25.pdf | 12 May 2026 |
| Form 1File: 10Form 1 Dec 24.pdf | 12 May 2026 |
| Form 2File: Q3-24-25.pdf | 12 May 2026 |
| Form 3File: 21Dec24_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 15 Dec24.pdf | 12 May 2026 |
| Form 1File: 9Form 1 Sept 24.pdf | 12 May 2026 |
| Form 2File: Q2-24-25.pdf | 12 May 2026 |
| Form 3File: 20Sept 24_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 14Sept 24.pdf | 12 May 2026 |
| Form 1File: 8Form 1 June 24.pdf | 12 May 2026 |
| Form 2File: Q1-24-25.pdf | 12 May 2026 |
| Form 3File: 19June 24_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 13June 24.pdf | 12 May 2026 |
| Form 1File: 1Form 1.pdf | 12 May 2026 |
| Form 2File: Q4-21-22.pdf | 12 May 2026 |
| Form 3File: 10March22_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 4March 22.pdf | 12 May 2026 |
| Form 1File: 3Form 1 March 23.pdf | 12 May 2026 |
| Form 2File: Q4-22-23.pdf | 12 May 2026 |
| Form 3File: 14Mar 2023_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 8March 23.pdf | 12 May 2026 |
| Form 1File: 7Form 1 March24.pdf | 12 May 2026 |
| Form 2File: Q4-23-24.pdf | 12 May 2026 |
| Form 3File: 18March 24_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 12March 24.pdf | 12 May 2026 |
| Form 1File: 6Form 1 Dec 23.pdf | 12 May 2026 |
| Form 2File: Q3-22-23.pdf | 12 May 2026 |
| Form 3File: 17Dec 23_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 11Dec 23.pdf | 12 May 2026 |
| Form 1File: 5Form 1 Sept 23.pdf | 12 May 2026 |
| Form 2File: Q2-23-24.pdf | 12 May 2026 |
| Form 3File: 16Sept23_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 10Sept 23.pdf | 12 May 2026 |
| Form 1File: 1Form 1.pdf | 12 May 2026 |
| Form 2File: Q4-20-21.pdf | 12 May 2026 |
| Form 3File: 6Mar 21_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Discl.pdf | 12 May 2026 |
| Form 1File: 4Form 1 June 23.pdf | 12 May 2026 |
| Form 2File: Q1-23-24.pdf | 12 May 2026 |
| Form 3File: 15June23_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 9June 23.pdf | 12 May 2026 |
| Form 1File: 2Form 1 Dec 22.pdf | 12 May 2026 |
| Form 2File: Q3-21-22.pdf | 12 May 2026 |
| Form 3File: 13Dec 2022_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 7Dec 22.pdf | 12 May 2026 |
| Form 1File: 1Form 1 Sept 22.pdf | 12 May 2026 |
| Form 2File: Q2-22-23.pdf | 12 May 2026 |
| Form 3File: 12Sep 2022_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 6Sept 22.pdf | 12 May 2026 |
| Form 1File: 1Form 1.pdf | 12 May 2026 |
| Form 2File: Q1-22-23.pdf | 12 May 2026 |
| Form 3File: 11June 2022_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 5June 22.pdf | 12 May 2026 |
| Form 1File: 1Form 1.pdf | 12 May 2026 |
| Form 2File: Q3-21-22.pdf | 12 May 2026 |
| Form 3File: 9Dec21_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 3Dec 21.pdf | 12 May 2026 |
| Form 1File: 1Form 1.pdf | 12 May 2026 |
| Form 2File: Q2-21-22.pdf | 12 May 2026 |
| Form 3File: 8Sept21_compressed.pdf | 12 May 2026 |
| Disclosure of Sold and Booked InventoryFile: 2Sept 21.pdf | 12 May 2026 |
| Form 1File: 1Form 1.pdf | 12 May 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 256 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Namoville on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Balewadi13,700+ in Pune
Filed coordinates, straight-line distance. 268 registered projects within 2 km.
EARTH 1 BY VTP LUXE PHASE 1
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
Godrej Meadows
Mahalunge Township Developers Private Limi
Godrej Green Vistas
Mahalunge Township Developers Private Limi
Godrej Hill Retreat
Mahalunge Township Developers Private Limi
Godrej Green Cove
Mahalunge Township Developers Private Limi
NYATI EMERALD I
NYATI BUILDERS PRIVATE LIMITED
Builder: ROYAL NAMOVILLE VENTURES
ROYAL NAMOVILLE VENTURES has 1 registration on MahaRERA, including Namoville. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Namoville is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Namoville?
The registered promoter entity is ROYAL NAMOVILLE VENTURES, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Namoville?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Namoville?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Namoville?
The professionals named in the filing: Architect: VK a Architecture; Architect: Raviraj Gosavi; Architect: Archmaze Associates; Engineer: Mahendra Kale; Chartered Accountant: DSD and Associates; Chartered Accountant: K K S S AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Namoville?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback