Namdev Vihar

By Namdev Construction

RG-MH-50736 · RERA P51700015782 · Last updated on MahaRERA portal: 23 Jul 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 63 documents Report an error

Namdev Vihar is a Residential / Group Housing project by Namdev Construction in Thane, Maharashtra, registered with MahaRERA as P51700015782 on 26 Mar 2018. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameNamdev Vihar
  • TypeResidential / Group Housing
  • Location
    • Rambaugh 4 End
    • Chickanghar
    • Chikanghar
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700015782
  • ReraGenie IDRG-MH-50736

Builder

  • NameNamdev Construction
  • Entity typePartnership
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

34 months past promisethis monthRegisteredMar 2018First promiseDec 2021Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Mar 2018
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 30 Dec 2021)
  • Buildings2 building records
  • Documents filed63 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C WingNA118000
A WingNA44000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

C Wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A Wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed7

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots7
Closed/Covered3
Open Space4
BuildingClosed/CoveredOpen SpaceTotal
C Wing336
A Wing011

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area714 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityKALYAN-DOMBIVLI MUNICIPAL CORPORATION (KDMC)
Permissible FSI1944.23
Proposed, not sanctioned1,202 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFlower Valley Complex Khadakpada Kalyan West 421301

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANTOSH R MADAN
EngineerARUN R KHASNIS
EngineerRamesh MANILAL Bhundere
Chartered AccountantDESHKAR & ASSOCIATES
PartnerRole in project
Namdev Construction-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700011350Dec 2021 → Dec 2022

Reason as filed by the promoterAs per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 30th December 2021 as the project completion date. We could not complete the project due to various unavoidable reason. Such as a) Implementation of the GST Act in 2017 also affected the construction activities. b) We have faced the situation of the water logging due to rain in 2018 and 2019. Due to which we could not process with the construction activities in rainy seasons. c) Again, in 2020 and 2021 due to Pandemic situation of COVID-19 and locked down imposed by the government w

EXT51700013661Dec 2021 → Dec 2023

Reason as filed by the promoter1. In 2020 due to the Pandemic situation of COVID-19 and locked down imposed by the government we could not proceed with the construction activities. 2. Also, due to the pandemic, there was a shortage of Materials, Labour and transportation service. 3. Due to the issuance of the UNIFIED DEVELOPMENT CONTROL AND PROMOTION REGULATIONS, 2021, there were changes in the FSI of the project, hence we needed to apply for the revised Plan approvals and Amended Commencement Certificate 4. Therefore we would like to seek an extension period of One Year ie. Till 31st DECEMBER 2023.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Dec 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Mar 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Jul 2024

Documents filed63

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CC.pdf23 Jul 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: s.pdf23 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf1 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf1 Feb 2023
Certificates of CA (Form 3)File: FORM 3.pdf1 Feb 2023
Disclosure of sold/ booked inventoryFile: sold unsold.pdf19 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed.pdf5 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed.pdf5 Nov 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOL.pdf5 Nov 2022
Certificates of CA (Form 3)File: FORM 3_compressed.pdf5 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf5 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf3 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engr crtfct_compressed (1).pdf3 Aug 2022
Disclosure of sold/ booked inventoryFile: sold unsold.pdf3 Aug 2022
Certificates of CA (Form 3)File: 3_compressed.pdf3 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed.pdf18 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed.pdf18 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf18 May 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf18 May 2022
Certificates of CA (Form 3)File: FORM 3_compressed.pdf18 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5_compressed.pdf18 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5_compressed.pdf18 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A 2020.pdf20 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2021.pdf20 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed.pdf19 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed.pdf19 Jan 2022
Disclosure of sold/ booked inventoryFile: SOLD_UNSOL.pdf19 Jan 2022
CERSAI detailsFile: CERSAI.pdf19 Jan 2022
Certificates of CA (Form 3)File: FORM 3_compressed (4).pdf19 Jan 2022
Declaration about Commencement CertificateFile: CC DECLARATION .pdf26 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf26 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE_compressed.pdf26 Aug 2021
Disclosure of sold/ booked inventoryFile: SOLD:UNSOLD.pdf26 Aug 2021
Certificates of CA (Form 3)File: FORM 3_compressed.pdf26 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 1018-19.pdf26 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 2019-20.pdf26 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2020-21.pdf26 Aug 2021
Layout approvalFile: Layout Revised.pdf7 Dec 2020
Layout approvalFile: C Wing 1 to 4 Flr Revised.pdf7 Dec 2020
Layout approvalFile: C Wing 5 Flr Revised.pdf7 Dec 2020
Copy of Layout Approval (in case of layout)File: Layout Revised.pdf7 Dec 2020
Copy of Layout Approval (in case of layout)File: C Wing 1 to 4 Flr Revised.pdf7 Dec 2020
Copy of Layout Approval (in case of layout)File: C Wing 5 Flr Revised.pdf7 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: CC Revised.pdf7 Dec 2020
Building plan approvalFile: IOD1.pdf18 Mar 2018
Building plan approvalFile: IOD2.pdf18 Mar 2018
Building Plan Approval (IOD)File: IOD1.pdf18 Mar 2018
Building Plan Approval (IOD)File: IOD2.pdf18 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: CC01.pdf18 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: CC02.pdf18 Mar 2018
Certificates of CA (Form 3)File: CA Crtft Cmprsd.pdf18 Mar 2018
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf18 Mar 2018
Proforma of Allotment letterFile: SALE DEED.pdf18 Mar 2018
Copy of the legal title reportFile: title-compressed.pdf9 Mar 2018
Details of encumbrancesFile: encum.pdf9 Mar 2018
Declaration in FORM BFile: fb01.pdf9 Mar 2018
Declaration in FORM BFile: fb02.pdf9 Mar 2018
Layout approvalFile: LAYOUT.pdf27 Feb 2018
Layout approvalFile: A Wing.pdf27 Feb 2018
Layout approvalFile: C WING.pdf27 Feb 2018
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf27 Feb 2018
Copy of Layout Approval (in case of layout)File: A Wing.pdf27 Feb 2018
Copy of Layout Approval (in case of layout)File: C WING.pdf27 Feb 2018

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Namdev Vihar on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chickanghar7,600+ in Thane

2 kmNamdev ViharCompleted 92Lapsed / revoked 59Other 155Dot size: filed unitsN

Filed coordinates, straight-line distance. 306 registered projects within 2 km.

Builder: Namdev Construction

Namdev Construction has 2 registrations on MahaRERA, including Namdev Vihar and Abhimanyu Residency. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Namdev Vihar shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Namdev Vihar is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Namdev Vihar?

The registered promoter entity is Namdev Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Namdev Vihar?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Namdev Vihar?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Namdev Vihar?

The professionals named in the filing: Architect: SANTOSH R MADAN; Engineer: ARUN R KHASNIS; Engineer: Ramesh MANILAL Bhundere; Chartered Accountant: DESHKAR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Namdev Vihar?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Namdev Vihar. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Namdev Vihar to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.